Quarterlytics / Basic Materials / Gold / Petropavlovsk PLC / FY2016 Annual Report

Petropavlovsk PLC
Annual Report 2016

POG · LSE Basic Materials
Claim this profile
Ticker POG
Exchange LSE
Sector Basic Materials
Industry Gold
Employees 5001-10,000
← All annual reports
FY2016 Annual Report · Petropavlovsk PLC
Loading PDF…
l

P
e
t
r
o
p
a
v
o
v
s
k
P
L
C
A
n
n
u
a

l

R
e
p
o
r
t
2
0
1
6

Petropavlovsk PLC
11 Grosvenor Place
London
SW1X 7HH

T +44 (0)20 7201 8900
F +44 (0)20 7201 8901
E contact@petropavlovsk.net
www.petropavlovsk.net

Annual 
Report 
2016 

Investment case 

Solid foundations.
Building for the future.

Petropavlovsk PLC is an established, bulk tonnage, low cost gold exploration, 
development and mining company listed on the London Stock Exchange.

Near term strategy

Medium term strategy

Long term strategy

1 Assuming completion of the POX Hub, scheduled for commissioning from Q4 2018. 

The underlying objective is to transfer enterprise value from debt to equity holders, deleveraging via production growth, resource growth and disciplined cost structure. Maximising free cash flow from our solid and stable producing non-refractory operations to fund future growth development and generate shareholder returns.  –4 x open pit gold mines  –6.3Moz produced since 1999  –20.16Moz of JORC Resources including 7.95Moz of Reserves –implying a greater than 15 year life of mine1  –Sustainable long term production >450,000 ounces per annum – 16.2Mtpa of RIP capacity (4 x RIP plants)Optimal extraction from accessing our full asset base. Sustainable long term refractory and non-refractory production from the POX Hub and RIP plants respectively, with ongoing resource and production growth upside from high grade underground operations and highly prospective exploration prospects within the combined 3,600km² license holding.  –3 x open pit mines  –2 x underground mines –14.5Mtpa of RIP capacity (3x RIP plants) –500ktpa POX Hub processing refractory concentrate –Malomir and Pioneer combined 11.4Mtpa flotation capacity 
 
 
 
POX Hub – Our Refractory Growth Story 

Shareholder Information 

Solid foundations for 
sustainable growth

Pox highlights

Building for the future

Petropavlovsk’s POX Hub will be the second of its kind in Russia. 

2016 was a landmark year with the recommencement of this core growth project. With our 
existing 4.1Moz refractory ore reserves, the scheduled commissioning of POX in Q4 2018 will be 
transformative for the Group, as demonstrated by the robust updated project economics as of 
end of 2016, in line with current assumptions and development capex. 

Project construction is currently 65% complete and we look forward to updating you on key 
milestones throughout the project build and commissioning. 

Project highlights

Capacity

No. of Autoclaves 

500Ktpa

4

(design commissioning  
Q418)

Refractory Reserves and 
Resources 

4.1Moz Reserves and  
9.3Moz Resources

Project NPV (10%) 

Project IRR 

Project Payback 

US$603m

65%

3.25 years

(Assuming LT avg gold price US$1,200/
oz, FX USD:RUR 60)

Operating Parameters (based on Malomir concentrate)

Mass  
pull 

Concentrate  
grade 

Sulphur  
content 

Total avg gold 
recovery 

5.5% mass

24 g/t Au

24.9%

79%

Operating Parameters (based on Pioneer concentrate)

Mass  
pull 

Concentrate  
grade 

Sulphur  
content 

Total avg gold 
recovery 

2.9% mass

24 g/t Au

21.0%

80%

Est. cash cost (Malomir)

Est. cash cost (Pioneer) 

US$615-675/oz

US$785-865/oz

Please refer to Development Projects on pages 44 to 47, for more information.

Managing your shares online 
Shareholders can manage their holdings 
online by registering with Capita’s share portal 
service. This is an online service provided by 
Capita which enables you to view and 
manage all aspects of your shareholding 
securely. The service is free and available 
24/7 at your convenience. Shareholders, 
whose shares are registered in their own 
name, can:

 – view holdings plus indicative price and 

valuation

 – view movements on your holdings

 – view dividend payment history

 – change your address

 – register or change your email address

 – sign up to receive communications by email 

instead of post

 – access the online voting service.

Shareholder queries
The Company’s share register is maintained 
by the Company’s Registrar, Capita Asset 
Services. Shareholders with queries relating 
to their shareholding should contact Capita 
directly using one of the methods listed below.

Capita Asset Services  
The Registry 
34 Beckenham Road Beckenham 
Kent BR3 4TU

Telephone Helpline: 0871 664 0300

If shareholders have any questions, please 
call Capita on 0871 664 0300. Calls cost 12 
pence per minute plus the phone company’s 
access charge. Shareholders outside the 
United Kingdom, should call +44 371 664 
0300. Calls outside the United Kingdom will 
be charged at the applicable international 
rate. The Capita helpline is open between 
9.00am to 5.30pm, Monday to Friday 
excluding public holidays in England and 
Wales.

Online: shareholderenquiries@capita.co.uk 
(from here you will be able to email Capital 
with your enquiry).

For more general queries, shareholders 
should consult the ‘Investors’ section of the 
Company’s corporate website.

i

S
t
r
a
t
e
g
c
r
e
p
o
r
t

G
o
v
e
r
n
a
n
c
e

Useful contacts
Petropavlovsk Registered Office 
11 Grosvenor Place  
Belgravia 
London SW1X 7HH 
Telephone +44 (0) 20 7201 8900

Registered in England and Wales 
(no.4343841)

Online for general queries:  
contact@petropavlovsk.net 

Head of Investor Relations
Alexandra Carse

Company Secretary
Amanda Whalley ACIS

Additional documents
Shareholders are encouraged to sign up to 
receive news alerts by email. These include all 
of the financial news releases throughout the 
year that are not sent to Shareholders by post.

The Directors are responsible for the 
maintenance and integrity of the financial 
information on our website. This information 
has been prepared under the relevant 
accounting standards and legislation.

Annual General Meeting 2016
This year’s Annual General Meeting (AGM) will 
be held at 3 More London Riverside, London 
SE1 2AQ. The meeting is on 20 June 2017, 
commencing at 10 a.m. Shareholders who 
wish to attend the AGM are asked to read the 
accompanying notes to the Notice of the 
Meeting which explain the documentation 
required by Shareholders in order for them to 
gain entry to the meeting.

i

F
n
a
n
c
a

i

l

s
t
a
t
e
m
e
n
t
s

  Petropavlovsk Annual Report 2016  173

 
 
 
Highlights 

Key financial figures

Revenue

Total Cash Costs

All In Sustaining Costs

Underlying EBITDA

Net Profit/(loss)

US$540.7m
(2015: US$599.9m)

Our core assets

Pioneer

US$660/oz

US$807/oz

US$200.1m

US$31.7m

(2015: US$749/oz)

(2015: US$874/oz)

(2015: US$172.8m)

(2015: US$(297.5m)

Albyn

Malomir

Pokrovskiy

Licence area: c. 1,280km2

Licence area: c. 1,168km2

Licence area: c. 821km2

Licence area: c. 336km2

R&R:  5.52Moz >15year LOM 

R&R:  4.77Moz >15year LOM 

R&R: 7.06Moz implied >16 year LOM 

R&R: 1.39Moz Transitioning into the 
strategic location for the POX Hub

FY16 142koz Au @ AISC US$789/oz 

FY16 180koz Au @ AISC US$719/oz

FY16 57koz Au @ AISC US$1,004/oz

FY16 38koz Au @ AISC US$988/oz

Open pit (underground development)

Open pit

Open pit (underground development)

Open pit 

Processing capacity:  
6.7Mtpa RIP plant and heap leach 

Processing capacity:  
4.7Mtpa RIP plant

Processing capacity:  
3.0Mtpa RIP plant

Processing capacity:  
1.8Mtpa RIP plant and heap leach

Development projects

POX Hub

Transformative growth project 
unlocking 9.3Moz Mineral Resource 
base. POX Hub construction 
currently 65% complete. Malomir 
flotation plant (Stage 1) construction 
90% complete. Key contracts have 
been signed with Outotec and critical 
long lead item orders placed. Staged 
commissioning from Q4 2018.

Russian Federation

Underground Mine Development 

Pioneer, NE Bakhmut 
Total 299koz underground Mineral 
Resource, a 300% increase from 
2015. 675m decline development 
completed, including ventilation 
decline. First production Q2 2017.

Malomir, Quartzitovoye  
Total 283koz underground Mineral 
Resource, including 207koz Ore 
Reserve. Development has 
commenced Q1 2017. 
First production H2 2017. 

Exploration projects

Pioneer: NE Bakhmut 
underground resource and 
exploration drilling. Sosnovaya 
greenfield anomalies identified. 

Albyn: Elginskoye in fill drilling, 
Unglichikan resource drilling and 
Yasnoye exploration surveying.

 Malomir: Quartzitovoye 
underground resource and 
exploration drilling.

Amur region

Albyn

Malomir

Pioneer

Pokrovskiy

St Petersburg
- RDC Hydrometallurgy

Moscow
- Petropavlovsk Moscow
- PHM Engineering (Tech) 

Yamal 
region

Krasnoyarsk
region

IRC Limited
- Amur region – Kuranakh mine 
- Jewish autonomous region – K&S mine

Pioneer:

Albyn:

Pokrovskiy:

Malomir:

Amur
region

Irkutsk
- Irgiredmet Institute 

Blagoveschensk
- Petropavlovsk Amur Region 
- Regis Exploration
- Kapstoi Construction

Operating mine

IRC Limited Operations

Underground

POX

Analytical Labs

R&D

Offices

  Petropavlovsk Annual Report 2016 

1

Strategic reportFinancial statementsGovernance2 

Petropavlovsk Annual Report 2016    

Contents 

01

02

03

Inside this report

Strategic report
Highlights 

Contents 

Our Business Model 

Our Business Cycle 

Chairman’s Statement 

Chief Executive Officer’s 
Statement

Market Overview 

Our Strategy 

1

3

4

5

6

8 

10

12

Key Performance Indicators (KPIs)  14

Governance
Board of Directors 

Corporate Governance Report 

Nomination Committee Report 

Audit Committee Report 

Directors’ Remuneration Report 

Directors’ Report 

Directors’ Responsibilities 
Statement

Independent Auditor’s Report 
to the Members of  
Petropavlovsk PLC

70

72

79

80

87

104

111 

112 

Financial statements
Consolidated Income Statement  120

Consolidated Statement 
of Comprehensive Income

Consolidated Balance Sheet 

Consolidated Statement 
of Changes in Equity

Consolidated Cash 
Flow Statement

Notes to the Consolidated 
Financial Statements

121  

122

123  

124 

125 

Company Balance Sheet 

164

Risks to Our Performance 

20

POX Hub 

Environmental, Safety  
and Social Report

Operational Performance: 
Pioneer

Operational Performance: 
Albyn

Operational Performance: 
Malomir

Operational Performance: 
Pokrovskiy

Development Projects 

34 

Reserves and Resources 

IRC 

Chief Financial Officer’s 
Statement

36 

38 

40 

42 

44

46

48

56

58 

i

S
t
r
a
t
e
g
c
r
e
p
o
r
t

G
o
v
e
r
n
a
n
c
e

Company Statement 
of Changes in Equity

Notes to the Company 
Financial Statements

Appendix, Glossary 
and Definitions

Shareholder Information 

165 

166  

169 

173

i

F
n
a
n
c
a

i

l

s
t
a
t
e
m
e
n
t
s

  Petropavlovsk Annual Report 2016 

3

 
 
Our Business Model

Our  
Values

Innovation

Responsibility

Integrity

Sustainability

Excellence

Strategic 
Objectives

Sustainable cash 
generation

Focus on optimisation 
and cost control

Growth via exploration 
and development

HSE and Social 
Responsibility

Our  
Strengths

Quality of assets

Knowledge and 

experience

Highly skilled 

workforce

Location and 

infrastructure

Responsible mining

4 

Petropavlovsk Annual Report 2016    

Our Business Cycle

Explore & Evaluate

Develop

Mine and Process

Gold

Mine Closure and  
Rehabilitation

We aim to replenish, expand and improve 
our resource base through brownfield and 
greenfield exploration. Our experienced 
exploration team has a proven track record 
of identifying, exploring and appraising high 
value deposits.

We create value and drive future growth by 
developing our mines in a responsible and 
efficient manner, using our extensive in 
house expertise to maximise return on 
investment.

Our operating experience allows us to 
achieve optimal gold extraction, which 
coupled with industry leading expertise in 
processing technologies is conducive to 
healthy profit margins.

Gold doré bars are our end product. These 
are sent to refineries for smelting into bullion. 
Currently all our production is sold to 
Russian banks.

We integrate closure planning throughout 
the asset life cycle, ensuring prudent valuing 
and responsible environmental compliance. 
We have a strong reputation for sustainable 
and responsible development of mines 
throughout the production cycle.

  Petropavlovsk Annual Report 2016 

5

Strategic reportFinancial statementsGovernanceChairman’s Statement 

Reserves and resources, tonnes and grade 
are the watchwords of the gold mining 
industry and we have updated you 
accordingly. 2016 exploration has brought 
considerable infill success, including a 340% 
increase in Reserves at the Elginskoye/Albyn 
complex, approximately a 200% increase in 
underground Resource at Pioneer, as well as 
a brand new greenfield discovery between 
Pokrovskiy and Pioneer.

2016 was also a significant year for IRC, the 
iron ore producer on the Chinese border in 
which our company holds a 31% stake, and 
whose borrowings from ICBC we guarantee. 
Following a challenging period, I am delighted 
to say that, as of its first quarter’s results, it is 
now a cash generative operation and our 
shareholding in IRC is, in my view, of 
significant potential value to the Company. 
I am very grateful to our team, the financiers  
at ICBC and Sinosure, and the contractor 
CNEEC, for the way in which the issues were 
finally resolved.

The POX Hub remains our core organic 
growth development project and key value 
driver for the business. The bank refinancing, 
while increasing near term capex for the 
Company, means that we no longer needed 
to give away part of the value in the POX Hub. 
Construction is 65% complete and scheduled 
for commissioning in Q4 2018. In 2016, we 
also took our first steps underground, a 
natural progression for us as a hitherto open 
pit operation with a vast refractory reserve 
and resource base. Both Pioneer and 
Malomir licences host sources of high grade 
ore and the feasibility work supported 
operations. 

Our corporate strategy is to create value for 
equity investors by growing our sustainable 
cash flows and to do this by continuing our 
efficient and successful exploration and 
development programmes. It remains our 
intention to deliver a meaningful share of the 
cash flow to shareholders as soon as the debt 
burden is substantially reduced. The advent 
of our underground operations in the nearest 
future and that of our production from 
refractory ore is scheduled to do this. 
The team needs us to maximise the benefits 
inherent in our high quality assets – both 
material and personal, using the excellence 
and experience that is demonstrated by 
management’s track record.

Peter Hambro

At the end of another busy year, it is a 
pleasure to be able to say that Petropavlovsk 
has achieved in 2016 many of the goals that I 
set out in my Chairman’s Statement for 2015, 
and a pleasure to introduce you to our 2016 
Annual Report and Accounts. It was, indeed, 
a transformative year, not least because the 
Group returned to profitability. Our net profit 
increased by 111%, much of which was 
accomplished thanks to a 4th consecutive 
year of cost reduction in addition to reduction 
in impairment losses in IRC, and, with IRC 
becoming an associate to the Group, limiting 
exposure to their results to our ownership. We 
must thank the efforts of all concerned to 
maintain a disciplined focus on cost control, in 
turn enabling us to maximise the margin on 
which our success depends, though cost 
control by itself will not deliver profit. I am 
pleased to note that production from our 
established open pit operations was in line 
with our revised guidance, delivering the 
sustainable cash flow that my 2015 statement 
hoped for.

Following the 2015 capital restructure, our 
team began the refinancing process with our 
Russian lenders. In this task, we needed to 
get the banks to extend the maturity profile of 
their loans to us so that the new maturity 
profile would match our production. I am 
pleased to say that this was achieved 
successfully and that the banks, 
understanding the importance of our plans to 
restart the POX Hub project for the treatment 
of refractory ore, agreed to encompass the 
capital expenditure that this would involve in 
nearby years. This allows us to unlock 100% 
of the value otherwise encapsulated in the c.4 
million ounces of gold reserves in the quartz/
sulphur matrix that is refractory ore. We 
continue to expect that the cost per ounce to 
produce this will not be significantly different 
from those we have seen in our non-refractory 
operations. 

6 

Petropavlovsk Annual Report 2016    

I should like to thank Robert Jenkins for taking 
over the role of Senior Independent Director 
from Sir Roderic Lyne and also to thank my 
other colleagues on the Board for the time 
and effort they have devoted to the company 
during the year. In addition, and on behalf of 
my colleagues, I want to thank the executives, 
the managers and all the teams that have 
contributed to the success of 2016.

Peter Hambro
Chairman

With the refinancing and rescheduling of our 
bank debt behind us and the excellent 
prospects for underground mining, the 
pressure oxidation of refractory ore and the 
new discoveries of gold ahead of us, I feel 
confident about our long term plans; 
particularly so at today’s higher gold prices, 
even though we have protected ourselves by 
some 600,000 ounces of price hedging. 
Indeed so confident am I that the Board and I 
have felt it appropriate now to address the 
succession planning issues that our Board 
Review has highlighted. 

Petropavlovsk is unique in being a British 
company with a London Board and with all its 
assets located in the Russian Federation and 
managed and operated by local people. 
Having managed the London end of this 
business for 23 years, with Pavel Maslovskiy 
running the Russian end, in good times and in 
bad, I have a clear understanding of what is 
involved and realise that passing on the baton 
will not be an easy task. As is usual in such 
matters, the Board has decided that the task 
of advancing succession matters should be 
undertaken by the Nomination Committee. 
This is in progress: Alex Green has joined 
Andrew Vickerman and Robert Jenkins on 
this Committee and I will retire from the 
Committee and as its Chairman.

“  Our corporate strategy is to create  
value for equity investors by growing  
our sustainable cash flows and to  
do this by continuing our efficient  
and successful exploration and  
development programmes.”

  Petropavlovsk Annual Report 2016 

7

Strategic reportFinancial statementsGovernance 
Chief Executive Officer’s Statement 

Pavel Maslovskiy

2016 was a transformational year for 
Petropavlovsk shaped by the refinancing of 
our bank debt, enabling the construction 
ramp up of our landmark POX Hub. 
The business returned to profitability, 
as supported by a fourth consecutive year  
of cost reductions and the operational 
progression into underground mining as we 
access the high grade reserve and resource 
potential that extends below our existing pits, 
further sustaining our long life of mine. 

Solid Foundation 
Our established, bulk tonnage, open pit 
non-refractory operations enabled us to 
deliver total annual production of 416koz, in 
line with revised guidance. Unexpected 
weather conditions experienced throughout 
the year intermittently impaired mining and in 
particular access to scheduled high grade ore 
at Andreevskaya. These ounces were 
deferred to the 2017 mine plan and require 
increased blending of lower grade stockpile 
material. This resulted in a 20% reduction in 
average processed grade from 2015. Cost 
control and operational efficiencies remain 
critical to our strategy. Without these we 
would not have been able to deliver another 
year of reduced costs:

 – TCC of US$660/oz, a 12% reduction on 
2015 and below our US$700/oz 2016 
guidance

 – AISC of US$807/oz, an 8% reduction on 
2015 and in line with 2016 guidance. 

This marked the fourth consecutive annual 
reduction in TCC and AISC representing a 
35% reduction since 2013, due to cost 
optimisation measures and the positive effect 
of Rouble depreciation. 

In 2016, the Resin-in-Pulp (RIP) plants 
operated at full capacity with Group 
throughput of 16.2Mt, a 2% increase on 2015. 
The responsible optimisation of productivity 
and operational efficiency remains central to 
our way of working. As such, following 
extensive research and testing throughout the 
year, we implemented a dedicated resin 
treatment facility at Pokrovskiy designed to 
improve the processing efficiency of the resin 
sorption at the Group “RIP” plants. We expect 
this to significantly reduce the impact of gold 
in circuit, thereby increasing productivity. 

In 2016, our solid and stable asset base and 
operational excellence allowed us to generate 
positive operational cash flows and return to 
profitability. We achieved net profit of 
US$31.7m, resulting to a large extent from the 
higher profitability of our operations and the 
reduced impact from IRC. Underlying EBITDA 
was US$200.1 million, an improvement of 
16% on 2015 due to maximised margins. 

Underpinning our business model is our 
exploration success in unlocking the 
abundant gold potential within our 3,600km2 
licence holding. Our current 20.2Moz 
Resource, supporting a greater than a 15 year 
life of mine, demonstrates our value in 
investing in our long term sustainability. 

Targeted exploration on replenishing depleted 
ounces, resource to reserve conversion and 
exploring brownfield near term non-refractory 
potential was very successful in 2016. We 
converted 1.6Moz of Resources to Reserves 
of which the majority were at our 100% 
non-refractory Albyn mine, Elginskoye 
deposit. Instrumental to our strategic growth 
objectives, we defined our first underground 
Reserve of 370koz, underpinning an initial 6 
year life of mine at both Pioneer and Malomir. 

Building for the Future
It is important to remember that 
Petropavlovsk’s foundations lie at Pokrovskiy, 
acquired in the early stages of exploration in 
1994 and which subsequently became the 
backbone of the Group. As the mine nears the 
end of its reserve life, we made the strategic 
decision to develop it into the base for the 
POX Hub. Its excellent operational 
infrastructure, skilled labour, proximity to 
regional infrastructure and access to naturally 
occurring limestone drove our decision. 

The refinancing of our $530m bank debt was 
paramount to the achievements of 2016 and 
has opened up future opportunities. With the 
agreement that Petropavlovsk retained 100% 
of the value of our core growth project, the 
POX Hub, my colleagues and our partners, 
Sberbank and VTB, successfully extended 
the debt maturity profile in line with our 
production profile thereby enabling us to fund 
development out of free cash flows (assuming 
a prevailing gold price of $1,250/oz). 

Unlocking the 4Moz refractory Reserves 
embedded within our existing asset base, 
equivalent to approximately 50% of our 
current Ore Reserves, represents meaningful 
value to Petropavlovsk. Following the 
refinancing, together with independent 
consultants, we updated our project 
economics, giving an IRR of 65% and NPV10 
of US$603 million, adding a minimum of 
200koz per annum to our production profile  
at a steady rate. 

At Malomir, currently our smallest mine by 
production (57koz in 2016), completing the 
POX Hub will grow its production profile to 
make it the largest contributing Group asset 
by 2019 with a falling cost trajectory in line 
with current group operating costs of c.
US$700/oz. 

Development progresses at full scale and is 
currently under budget. In 2016, Outotec 
contracts were reinitiated and orders for long 
lead items placed. Flotation concentrate 
production is scheduled to commence at 
Malomir from H1 2018 for trucking and 
stockpiling ahead of the POX Hub 
commissioning from Q4 2018. 

8 

Petropavlovsk Annual Report 2016    

Positioning for Growth 
With the development of our POX Hub and 
underground firmly underway, as we emerge 
from a period of introspection and 
optimistically look ahead, 2017 is set to be 
another pivotal building block towards 
achieving our vision of being a mid tier 
producer of refractory and non-refractory ore 
from 2019. 

I would like to thank the Board and our 
stakeholders for their guidance in 2016. 
Further, I would like to thank the management 
team for their commitment, strength of 
character and ability to effectively navigate the 
challenges of the last few years enabling us to 
reach this juncture.

We look forward to sharing our key milestones 
throughout this next phase of growth, while 
maintaining our devoted commitment to 
maximising sustainable margins in 2017. 

Pavel Maslovskiy 
Chief Executive Officer

Expanding our Expertise 
Prior to 2016, Petropavlovsk was an exclusively 
open pit operation. Following successful 
feasibility studies, the development of our first 
underground mine at Pioneer began in 2016, 
with development at Malomir scheduled to 
commence early 2017. First production is 
scheduled for H2 2017. We have appointed 
contractors and development is under way, 
with 675m of decline development completed 
at Pioneer by year end.

By and large, Petropavlovsk has utilised an 
owner operator business model. However, 
given underground is a new mining method, 
with start up execution risk, we have utilised 
well respected local contractors to mitigate 
this risk during the development growth 
phase. Notwithstanding the long history of 
underground mining in the Amur region, 
access to highly skilled labour and existing 
expertise within the Group, we intend to bring 
the underground operational function in 
house over time. 

Our extensive regional experience in gold 
mining, not only within Russia but specifically 
the Amur region, gives us a competitive  
edge in a complex marketplace. We have 
established our presence as a leading 
employer and contributor to the local 
economy, nurturing the talent of its people, 
who in turn have built Petropavlovsk into  
the business it is today. Senior management, 
a number of whom have worked for 
Petropavlovsk for more than a decade, have 
extensive technical expertise. Together with 
our larger in house exploration, construction, 
research and engineering capabilities, we 
have established our strategic vision of being 
a fully integrated operating gold miner. 

“  The responsible optimisation of 
productivity and operational efficiency 
remains central to our way of working.”

  Petropavlovsk Annual Report 2016 

9

Strategic reportFinancial statementsGovernanceMarket Overview 

Oil prices recovered from a 13 year low  
of US$26/bbl to close the year at over 
US$50/bbl
The oil price was under great pressure at  
the start of the year, dipping to well below 
US$30/bbl. This was due to persistently high 
inventories, caused by continuous shale 
production, and rising output from OPEC as  
it continued to pump oil to compete with shale 
producers for market share. Petropavlovsk 
benefited from the lower oil price, which 
translated into lower fuel costs, an expense 
which accounts for approximately 15% of  
our total operating cash expense figure  
(c.US$40m in 2016, a decrease of 27% /  
c.US$55m vs. 2015).

The RUB strengthened by 15% against 
the USD in 2016
While Petropavlovsk’s gold sales are 
denominated in US$, approximately 80% of 
the Group’s costs are RUB based. A weaker 
RUB is beneficial for the business because 
operating costs are lower when translated 
into our reporting currency. The RUB traded 
within a range of 60.2RUB to 82.3RUB per 
US$, commencing the year at 72.5RUB and 
closing at 61.5RUB, appreciating by c.15%. 
A strengthening oil price alongside the 
possibility of reduced sanctions helped the 
RUB to strengthen.

2017 outlook for gold prices
For the first three months of 2017, gold was  
up 8%. What happens next will partly be 
determined by levels of macro uncertainty 
and real rates, hence what ultimately matters 
is the impact of politics on economic growth 
and US Federal policy. For instance, 
if economic growth remains weak and 
inflation stays low, it is likely that interest rates 
will remain lower for longer – a positive for 
gold. On the other hand, should we see 
acceleration in US and global growth or a 
large fiscal package with measures that have 
a high growth impact, this will likely push real 
rates higher. This would mean a greater 
opportunity cost to holding gold, while its safe 
haven appeal would be expected to diminish.

A positive albeit unremarkable 
performance for gold in 2016
Gold returned +8% in 2016, starting the year 
at US$1,060/oz and closing at US$1,146/oz. 
The precious metal traded in a range between 
US$1,060/oz – US$1,366/oz, averaging 
US$1,248/oz during the year, +8% vs. 2015 
(US$1,160/oz). On a relative basis, although 
gold outperformed platinum (+3%), its 
performance could not match the gains 
achieved by silver (18%), palladium (21%) and 
the Bloomberg Commodity Index (+11%). 

Lower jewellery and tech demand easily 
balanced by higher investment demand
Global gold demand amounted to c.139Moz in 
2016, up 2% vs. 2015 (c.136Moz), with lower 
jewellery and technology demand more than 
offset by investment demand. On a combined 
basis, China (down 17% vs. 2015) and India 
(down 22% vs. 2015), accounted for over half  
of global jewellery demand. One possible 
explanation is that a rising gold price, combined 
with local currency depreciation vs. the US$, 
made buying gold more expensive, dampening 
its appeal. In India specifically, Q1 2016 
demand was affected by a six week nationwide 
jewellers’ strike due to the government’s 
proposal to impose a 1% tax on gold jewellery 
sales, followed by the surprise demonetisation 
of 1,000 and 500 rupee notes announced in Q4 
2016, further disrupting economic activity.

Investment demand for gold has 
overshadowed the weakness in physical 
demand this year
Investment demand jumped 70% in 2016, 
driven primarily by robust Exchange Traded 
Funds (ETF) inflows, although appetite for bars 
and coins did not change materially from 2015. 
According to data compiled by UBS, ETFs 
added c.15Moz to their holdings, finishing 2016 
at c.65Moz. The market saw strong ETF 
demand in H1, slowing in H2 with some 
outflows seen towards the end of Q4, in part 
due to some post-US election profit taking. 
Nonetheless, the robust ETF demand lends 
support to the view that a lot of the flow this 
year represents strategic allocation into gold, 
hinged on the view of lower rates for longer.

Investment demand drivers included negative 
interest rates, sluggish global growth, 
unknown Brexit consequences, uncertainty 
surrounding the US elections, heightened 
macro uncertainty, as well as deteriorating 
confidence towards central banks. This 
combination of factors lent upward support to 
price action well into Q3 2016, suggesting that 
gold is still considered an effective portfolio 
diversification tool.

10  Petropavlovsk Annual Report 2016    

China saw its share of bar and coin demand 
increase by 25% vs. 2015 to c.9Moz as 
consumers digested the impact of a 
weakening Yuan and as new restrictions on 
property purchases highlighted gold’s appeal 
as an alternative asset. In contrast, demand in 
the Middle East shrunk by 71% to its lowest 
levels on record, as a slowdown in oil driven 
economies and higher local prices dampened 
demand. 

Central bank purchases slowed in 2016
Traditionally viewed as an asset class to help 
diversify reserves, central bank buying 
continued in 2016, albeit at a slower pace. 
Purchases amounted to c.12Moz, 
approximately a third lower vs. 2015 
(c.19Moz). Whilst the buying was led by 
Russia, China and Kazakhstan, the overall 
slowdown in purchases can be attributed to 
sales stemming from pressure on FX 
reserves. As at the end of December 2016, 
Russia held c.52Moz as part of its reserves, 
an increase of 14% on the year.

Slight increase in overall gold supply year 
on year, big increase in recycled gold
Total mine supply increased by 5% to 
c.147Moz,with recycled supply jumping 17% 
to c.42Moz. The bulk of the recycling took 
place in the first three quarters, as the price 
rallied from c.US$1,060/oz in January to just 
over US$1,350/oz by August (before 
beginning to lose momentum from October 
onwards), encouraging consumers to cash in 
their physical gold.

Since gold peaked in 2011, miners have been 
adjusting to a lower gold price environment by 
focusing on core operations, cutting back on 
development / exploration spend and 
controlling costs. 2016 saw a possible turning 
point in investment allocation by companies 
as the gold price showed signs of stabilising 
above the psychologically important 
US$1,000/oz level, which allowed gold miners 
to reconsider their capital allocation plans, 
with renewed appetite to invest and explore. 
However, due to the time lag involved 
between initial exploration and first 
production, increased exploration spend is 
unlikely to make an immediate and meaningful 
impact on supply.

Hedging activity is up on last year, but 
appears to be mainly related to protecting 
operating margins while specific new projects 
are developed, as opposed to sizeable 
hedging from major producers, seen in the 
previous cycle.

The average annual gold price increased 8% in 2016 to US$1,248/oz (in US$/oz)

2016 

2015 

2014 

2013 

2012 

2011 

2010 

2009 

2008 

2007 

1,160

1,248

1,265

1,224

1,410

1,668

1,570

973

872

697

Source: The London Gold Market Fixing Limited. Data provided for information purposes only.

Gold appreciated by 8% in 2016 (in US$/oz)

2,000

1,600

1,200

800

400

0

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

Source: The London Gold Market Fixing Limited. Data provided for information purposes only.

Gold ETFs finished 2016 with combined holdings of approximately 65Moz, up 30% on the year (in Moz)

100

80

60

40

20

0

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

Source: UBS.

  Petropavlovsk Annual Report 2016  11

Strategic reportFinancial statementsGovernanceOur Strategy 

Our strategy is to create value for equity investors by growing sustainable cash flows, and via 
expansion due to successful exploration and development. It is based on the quality of our 
assets, our focus on operational and development excellence, and our experience, 
demonstrated by management’s track record of driving meaningful organic growth. 

Our Strategic Objectives

Sustainable cash generation

Overview

2016 Progress

2016 KPIs

Sustainable growth in cash generation 
is a key strategic driver for us. We are 
focusing on expanding margins using 
our solid and stable producing asset 
base and applying our operational 
excellence. We operate one of the 
largest gold mines in Russia in terms  
of the volume of gold produced, the 
capacity of their processing facilities 
and the size of their mineral resource 
base. From the first stages of 
development, our highly qualified  
team ensures that each of our mines is 
correctly engineered based on optimal 
mine planning, and designed to deliver 
maximum cash flow. 

 – A total of 16,166kt combined total 

Total Attributable Gold production

material processed

 – Implementation of centralised 

procurement system, significantly 
improving the Company’s ability to 
negotiate purchase pricing.

416.3koz (2015: 504.1koz)

Average Realised Gold Sales Price 

US$1,222/oz (US$1,178/oz)

2017 Targets

Key Risks

 – Targeted gold production of 420-

 – Gold Price Risk 

460koz

 – Securing cash flow through partial 

hedging of gold output.

 – Production Related Risk

 – Exploration Related Risk

*Please refer to the Risk  
section on pages 20 to 33.

Growth via Exploration and Development

Overview

2016 Progress

2016 KPIs

Our in house expertise is key to our 
development strategy. While generating 
free cash flow from existing operations, 
we secure high quality sources of long 
term growth through our own 
exploration programme, and develop 
assets using the latest technologies. 
Our 3,600km2 licence footprint lies 
around a major belt of gold 
mineralisation and remains under 
explored, which together with our local 
knowledge and highly qualified 
geological team allows for significant 
additions to our mineral reserve and 
resource base every year. Our solid in 
house research and technology 
capabilities enable us to unlock the 
value of technologically complex ores 
by using modern and efficient methods 
of gold recovery.

 – 1.0 Moz uplift in Probable Ore  

Mineral Resources

Reserves at the Elginskoye deposit 

 – 76% increase in Mineral Resources 
for underground mining at Pioneer  
and Malomir. 

20.16 Moz (2015: 23.29Moz)

Ore Reserves

7.95 Moz (2015: 8.41Moz)

2017 Targets

Key Risks

 – To improve short and midterm cash 
flow by discovering and bringing 
non-refractory reserves into 
production that are suitable for rapid 
access and extraction via 
underground and open pit mining

 – To better facilitate long term 

sustainability by adding high quality 
open pit refractory and non-refractory 
underground resources to 
Group totals.

 – Project Related Risk

 – Legal and Regulatory Risk

 – Exploration Related Risk

*Please refer to the Reserves and  
Resources section on pages 48 to 55.

12  Petropavlovsk Annual Report 2016    

Focus on Optimisation and Cost Control

Overview

2016 Progress

Our approach to operational 
management is underpinned by the 
optimal extraction of gold reserves. 
We plan to achieve highly competitive 
operational costs and expand margins 
steadily, leveraging efficiencies resulting 
from full capacity utilisation, continued 
operational improvement and 
comprehensive cost control. We will 
implement these plans to achieve our 
production targets and generate healthy 
gold sales at competitive margins.

 – 12% reduction in total cash costs and 
8% reduction in all-in sustaining costs 
(most substantially at Albyn, by 
greater than 20%. 

2016 KPIs

Total Cash Costs

US$660/oz (2015: US$749/oz)

All-in Sustaining Costs

US$807/oz (2015: US$874/oz)

2017 Targets

 – Commence mining from 

underground, optimising the 
extraction of high grade reserves at 
Pioneer and Malomir.

Key Risks

 – FX Risk

 – Legal and Regulatory Risk

 – Production Related Risk

HSE and Social Responsibility

Overview

2016 Progress

2016 KPIs

We aim to have a transformative, 
positive effect on socioeconomic 
development in the areas we operate  
in as we build our successful and 
responsible mining business. 
Petropavlovsk is committed to providing 
its employees with a safe working 
environment. It is essential for us to 
safeguard the welfare of our people. 
We are minimising our environmental 
footprint, upholding the highest 
standards as required by Russian law 
and going beyond operating in line with 
international best practice, in order to 
mitigate the negative impact of our 
operations. We value the support of all 
our stakeholders – whether they are 
investors, NGOs, governments or local 
communities and maintain an open 
dialogue to constantly improve and 
grow our business, maximising the 
positive effect on every group.

 – Maintained excellence in training  

and raising awareness

GHG Emissions: Combustion of fuel and 
operation of facilities (Tonnes of CO2e)

 – Enhanced monitoring tools to ensure  

a safe environment for employees

182,407.9 (2015: 260,194.9) 

 – Proved compliance with local 

legislation and exceeded 
requirements by implementing  
global best practices.

Electricity, heat, steam and cooling purchased 
for own use (Tonnes of CO2e)

222,847.3 (2015: 276,144.1)

Emissions reported above normalised per 
ounce of gold produced (Tonnes of CO2e /oz)

0.97 (2015: 1.07)

2017 Targets

Key Risks

 – Further developing training systems  

 – Health, Safety and Environmental Risk

to enrich our HSE culture

 – Maximizing efforts to lower the LTIFR 
(Lost Time Injury Frequency Rate) 
across sites

 – Improving our holistic approach in 
localizing incidents and accidents.

  Petropavlovsk Annual Report 2016  13

Strategic reportFinancial statementsGovernanceKey Performance Indicators (KPIs) 

Total Attributable Gold Production (koz)  

Total Cash Costs per Ounce of Gold for 
Hard Rock Mines (US$/oz) 

All in Sustaining  
Costs 

All in Costs 

416

504

2016 

2015 

660

749

2016 

2015 

807 

2016 

838

874 

2015 

932

625

2014 

860

2014 

972

2014 

1,087

2016 

2015 

2014 

Definition 

Measured in troy ounces, attributable gold 
production is the total of the gold produced  
from the Group’s four hard rock mines for the 
applicable years. The gold production figure 
consists of gold recovered during the period  
and is adjusted for the movement of gold still 
in circuit.

Relevance
Gold production underpins our financial 
performance as the majority of Group revenue is 
attributable to the sale of the gold produced by 
the Group. The indicator also demonstrates the 
strength of our operational and managerial 
teams to deliver against the mine plan.

Performance in 2016
The Group produced 416.3koz of gold in 2016,  
in line with guidance revised due to adverse 
weather conditions during the second half of the 
year. In part due to these conditions, production 
was lower than the 504.1koz of gold produced 
in 2015.

Going Forward
Gold production for 2017 is forecast between 
420,000-460,000oz, predominantly from open 
pit operations as underground production is 
scheduled to commence in H2 2017. 

Petropavlovsk remains focused on optimising  
its current asset base whilst continuing to drive 
its key growth projects, the POX Hub and the 
development of underground operations, to 
first production.

14  Petropavlovsk Annual Report 2016    

Definition 
The total cash cost per ounce is the cost of 
producing and selling an ounce of gold from the 
Group’s hard rock operations. Cash costs for 
hard rock mines are the cost of producing and 
selling an ounce of gold from the Group’s hard 
rock mines (Pokrovskiy, Pioneer, Malomir and 
Albyn). The Group’s four hard rock mines are its 
key assets, in 2016 producing 100% of the 
Group’s total gold production for the year. The 
Board and Executive Committee constantly 
monitor cash costs at the Group’s hard rock 
mines and work on their improvement. 

The key components of operating cash 
expenses are wages, electricity, diesel, chemical 
reagents and consumables. The key cost drivers 
affecting the operating cash expenses are 
stripping ratios, production volumes of ore 
mined and processed, recovery rates, cost 
inflation and fluctuations in the rouble to US 
dollar exchange rate. Refinery and 
transportation costs are variable costs 
dependent on production volume. Mining tax, 
comprising 6% of the gold price, is also a 
variable cost dependent on production volume 
and the realised gold price.

Relevance
The Group closely monitors its current and 
projected costs to track and benchmark the 
ongoing efficiency and effectiveness of its 
operations. This monitoring includes analysing 
fluctuations in the components that constitute 
cash costs and cost per tonne mined and 
processed to identify whether and where 
efficiencies may be made.

Performance in 2016
Total cash costs for the Group’s mines 
decreased from US$749/oz in 2015 to US$660/
oz in 2016. This primarily reflects the effect of 
cost optimisation measures undertaken by  
the Group in response to the lower gold price 
environment as well as the positive effect of 
Rouble depreciation.

Going Forward
The Group expects its total average cash  
costs in 2017 to be c.US$700/oz at current 
exchange rates. 

Go to pages 61 to 63 for further information on 
cash costs.

Definition 
All in sustaining cash costs (“AISC”) include both 
operating and capital costs required to sustain 
gold production on an ongoing basis. All in costs 
(“AIC”) are comprised of AISC as well as capital 
expenditures for major growth projects or 
enhancement capital for significant improvements 
at existing operations. AISC and AIC are calculated 
in accordance with guidelines for reporting AISC 
and AIC published by the World Gold Council in 
June 2013. For a calculation of AISC and AIC, 
please refer to the section AISC and AIC of the 
Chief Financial Officer’s Statement on page 63  
of this report.

Relevance
In 2014, following the publication of the World 
Gold Council’s guidelines for reporting AISC and 
AIC, the Group took the decision to monitor its 
AIC and AISC, in addition to TCC/ oz. This 
enables the Group to track and benchmark the 
ongoing efficiency and effectiveness of its 
operations to ensure it maintains healthy 
margins.

Performance in 2016
Following industry best practices, the Group 
calculated and disclosed its AISC and AIC for 
the first time for the period of 2014, which have 
since demonstrated a continuous decrease.

In 2016, AISC decreased to US$807/oz from 
US$874/oz in 2015. This reflects the reduction in 
TCC as well as lower sustaining capital 
expenditure related to the existing mining 
operations.

AIC decreased from US$932/oz in 2015 to 
US$838/oz in 2016, reflecting the decrease in 
all-in sustaining costs explained above, reversal 
of impairment of refractory ore stockpiles due to 
gold price recovery and decrease in exploration 
expenditure.

Going Forward 
The Group expects its All in Sustaining Costs of 
production in 2017 to be c.US$900/oz at current 
exchange rates.

Go to pages 61 to 63 for further information on 
cash costs.

 
 
 
Average Realised Gold Sales Price 
 (US$/oz) 

Capital Expenditure (US$m) 

Net Debt (US$m) 

2016 

2015 

2014 

1,222

2016  29.4

1,178

2015 

32.6

1,331

2014 

96.8

(930) 

(599) 

(610) 

2016

2015

2014

Definition 
The average realised gold sales price is the 
mean price at which the Group sold its annual 
gold production output throughout the year. It is 
calculated by dividing total revenue received 
from gold sales by the total quantity of gold sold 
in the period.

Relevance
As gold is the key commodity produced and 
sold by the Group, the average realised gold 
sales price is a key driver behind the Group’s 
revenues.

Performance in 2016
In 2016, the average realised gold sales price 
was US$1,222/oz, including US$(21)/oz effect 
from forward sales contracts, compared to 
US$1,178/oz in 2015. 

Going Forward
Forward contracts to sell an aggregate of  
50,006 ounces of gold at an average price of 
US$1,303 per ounce were outstanding as at 
31 December 2016.

Forward contracts to sell an aggregate of 
546,968oz of gold at an average price of 
US$1,253/oz are outstanding as at 26 April 2017. 

Further details on the components of Group 
revenue, cash flow and hedge arrangements 
may be found on pages 59.

Definition 
Capital expenditure is the funds required by the 
Group to explore and develop its gold assets 
and keep its current plants and other equipment 
at its gold mines in good working order.

Definition 
Net debt is set out in note 29 to the consolidated 
financial statements. Net debt is incurred in 
order to assist with the financing of project 
development.

Relevance
Net debt is a measure of a company’s ability to 
repay its debts if they were all due today and 
thus, it helps the management to estimate 
whether a company is appropriately leveraged.

Performance in 2016
Net debt was reduced to US$599 million in 2016 
from US$610 million in 2015. 

Going Forward 
Net debt is expected to decrease to c.US$550 
million by the end of 2017, assuming an average 
gold price of US$1,200/oz for the remainder 
of 2017.

Net debt is set out in note 29 to the consolidated 
financial statements.

Relevance
Capital expenditure is necessary in order to both 
maintain and develop the business, however 
gold capex requirements need to be balanced in 
line with the Group’s strategy and provide an 
optimal allocation of the Group’s funds.

Performance in 2016
The Group invested an aggregate of 
US$29.4 million in its gold projects compared  
to US$32.6 million invested in 2015. The key 
areas of focus this year were on fulfilling existing 
contractual commitments in relation to the  
POX Hub project, exploration to support the 
underground mining at Pioneer, expansion of 
tailing dams at Pioneer and Albyn and ongoing 
exploration related to the areas adjacent to the 
ore bodies of the Group’s main mining operations. 

Going Forward
The Group’s capital expenditure requirements are 
estimated to be around c.US$105 million in 2017. 
This will be split between continuing the Group’s 
exploration programme (c. US$17 million) and 
development and maintenance (c. US$85 million). 
The development works will focus predominantly 
on constructing the POX Hub, the Malomir 
flotation plant, and underground operations  
at Pioneer and Malomir.

A breakdown of 2016 capital expenditure may be 
found on page 67.

  Petropavlovsk Annual Report 2016  15

Strategic reportFinancial statementsGovernanceKey Performance Indicators (KPIs)   continued

Earnings/Underlying EBITDA (US$m) 

Profit/(Loss) for the Period (US$m)  

Basic Earnings/(Loss) per Share (US$)  

2016 

2015 

2014 

200.1

172.8

(298) 

251.8

(348) 

2016

32

2015

2014

(1.33) 

2016

0.01

(0.09)

2015

2014

Definition 
Underlying EBITDA is the profit/(loss) for the 
period before financial income, financial 
expenses, foreign exchange gains and losses, 
fair value changes, taxation, depreciation, 
amortisation and impairment charges.

Definition 
Profit/(loss) for the period is calculated by 
deducting operating and net finance expenses, 
taxation and any relevant share of results in 
associates and joint ventures for the applicable 
years from total revenue.

Definition 
Basic earnings per share (‘EPS’) is the profit or 
loss for the period attributable to equity holders 
of Petropavlovsk PLC divided by the weighted 
average number of ordinary shares during the 
period.

Relevance
Underlying EBITDA is an indicator of the Group’s 
ability to generate operating cash flows, which 
are the source of funding for the Group’s working 
capital requirements, capital expenditure and 
debt service obligations.

Performance in 2016
In 2016, the Group generated underlying 
EBITDA of US$200 million, compared with 
US$173 million in 2015. That represents a 16% 
improvement on 2015 primarily due to the 
contribution from hard rock mines as a result of 
the higher realised gold price achieved and the 
improvement in TCC.

Going Forward 
The Group aims to continue to produce and sell 
gold at competitive margins, which will, amongst 
other factors, influence the Group’s future 
EBITDA levels. 

A reconciliation of profit for the period from 
continuing operations and underlying EBITDA is 
set out in note 34 to the consolidated financial 
statements.

Relevance
Profit/(loss) for the period is often referred to as 
the ‘bottom line’ of the income statement and is 
the income attributable on a per share basis 
when it is divided by the weighted average 
number of shares outstanding during the 
reporting period.

Relevance
Basic EPS is an indicator of the Group’s 
profitability and the value per Ordinary Share.

The total number of Ordinary Shares in issue as 
at 31 December 2016 was 3,303,768,532 (31 
December 2015: 3,300,561,697).

Performance in 2016
Net profit of US$31.7m compared to a net loss of 
US$297.5 million for 2015, which reflects the 
improvement in underlying EBITDA, substantially 
lower losses from IRC (reflecting the fact that no 
substantial impairments were required in 2016) 
and deferred tax credit (primarily as a result of 
foreign exchange effects). 

Going Forward
The Group aims to continue to produce and sell 
gold at competitive margins, which will, amongst 
other factors, influence the Group’s future profit/
(loss) for the Period.

Performance in 2016
Basic profit per share for 2016 was US$0.01 
compared with a basic loss of US$0.09 in 2015. 
Basic profit per share from continuing operations 
for 2016 was US$0.01 compared to the US$0.07 
basic loss per share from continuing operations 
for 2015. The key factor affecting the basic profit 
per share was the increase of the profitability of 
the Group’s operations. 

Going Forward
The Group aims to continue to sell gold at 
competitive margins, which will, amongst other 
factors, influence the Group’s future EPS.

A reconciliation of profit for the period from 
continuing operations and underlying EBITDA is 
set out in note 34 to the consolidated financial 
statements.

A reconciliation of profit for the period from 
continuing operations and Underlying EBITDA is 
set out in note 34 to the consolidated financial 
statements.

16  Petropavlovsk Annual Report 2016    

Mineral Resources

Ore Reserves

2016 

2015 

2014 

20.2

23.3

23.3

2016 

2015 

2014 

7.8

8.4

9.2

Definition 
A Mineral Resource is a concentration or 
occurrence of solid material of economic interest 
in or on the Earth’s crust in such form, grade (or 
quality), and quantity that there are reasonable 
prospects for eventual economic extraction. The 
location, quantity, grade (or quality), continuity 
and other geological characteristics of a Mineral 
Resource are known, estimated or interpreted 
from specific geological evidence and 
knowledge, including sampling. Mineral 
Resources are sub divided, in order of increasing 
geological confidence, into Inferred, Indicated 
and Measured categories.

Relevance
JORC Mineral Resources are a measure of the 
size of the Group’s mining and exploration 
assets, indicating medium to long term 
production growth potential. In line with its 
strategy, the Group has been placing emphasis 
on finding Mineral Resources through 
exploration at sites at or close to current 
operating plants. Implementing this has enabled 
the Group to replenish gold Resources depleted 
from its operations in recent years and increase 
its Mineral Resource base.

Progress in 2016
During 2016, due to the success of the Group’s 
exploration programme, Mineral Resources for 
potential underground mining increased by 
c.320koz (76%). New Mineral Resources for 
potential open pit extraction were established  
at Quartzitovoye, an increase of 106koz (24%). 
A total of 3.55Moz of Mineral Resources were 
disposed of with the undeveloped, potentially 
capital intensive Visokoye and Yamal projects. 
This was the main driver for the resource 
decrease.

Definition 
An Ore Reserve is the economically mineable part 
of a Measured or Indicated Mineral Resource. It 
includes diluting materials and allowances for 
losses which may occur when the material is 
mined. Appropriate assessments, which may 
include feasibility studies, have been carried out 
and include consideration of and modification by 
realistically assumed mining, metallurgical, 
economic, marketing, legal, environmental, social 
and governmental factors. These assessments 
demonstrate at the time of reporting that 
extraction could be reasonably justified. Ore 
Reserves are sub divided in order of increasing 
confidence into Proven and Probable.

Relevance
JORC Ore Reserves are a measure of the size 
and quality of the Group’s mining assets and its 
ability to support the life of operating mines at 
profitable levels. The Group has been placing a 
strong emphasis on finding new Ore Reserves 
through exploration in line with its strategy. By 
implementing this, the Group has been able to 
replenish the majority of its Ore Reserves 
depleted from its operations.

Progress in 2016
Successful exploration and technical studies 
increased Ore Reserves at the Elginskoye 
deposit (Albyn) by 340% to 1.24Moz. Maiden 
high grade Ore Reserves of 0.37Moz for 
underground mining were estimated at Pioneer 
and Malomir, supporting a 6 year underground 
mine plan. A total of 1.22Moz of Ore Reserves 
were disposed of with Visokoye which is an 
undeveloped project in Krasnoyarsk, far from 
the Amur region where the Group operates. 
The disposal was the main reason for the 
Reserve decrease. 

Going Forward
Going forward, the Group is striving to continue 
to develop a high quality non-refractory and 
refractory resource base for both open pit and 
underground mining.

Going Forward
Going forward, the Group is striving to continue 
to establish a high quality non-refractory and 
refractory reserve base for both open pit and 
underground mining at their operational mines. 

  Petropavlovsk Annual Report 2016  17

Strategic reportFinancial statementsGovernanceKey Performance Indicators (KPIs)   continued

2.64

2.63

2.50

The Group is striving towards a zero fatal 
accident target. In order to eliminate the root 
causes of similar fatalities, the following action 
was undertaken with the full support of the HSE 
Committee:

–  Safety meetings were held at all levels, across 
all sites, mines and ancillary entities, to discuss 
the reasons and circumstances behind the 
accident

–  Training sessions were conducted with all 

appropriate employees across the Group to 
refresh their knowledge of the relevant 
procedures and regulations 

–  Random testing was conducted amongst this 
group of employees to ensure that they were 
working in accordance with the Group’s 
procedures. 

Going Forward
The Group has a duty to provide a safe 
environment for its employees and is constantly 
looking for ways in which to improve our 
performance and achieve zero fatalities. The 
following actions were put in place during 2016: 

–  An improved accident alert system to better 

facilitate communication between employees 
in order to locate accidents and provide 
necessary assistance

–  A successful merging of the Russian three 
stage reporting system with global best 
practices to reduce the probability of 
accidents, identifying and removing potential 
danger

–  Meetings and discussions were held on a 
regular basis between health and safety 
officers to share information and raise 
awareness 

–  Rigorous control and monitoring of compliance 
with the Group’s health and safety regulations 
to ensure a safe environment is promoted

–  The Fatal Accidents List, as part of the safety 
induction and refresher course, is a tragic 
reminder of the importance to obey health and 
safety rules at all times with no exclusions.

LTIFR 

2016 

2015 

2014 

Definition 
Lost Time Injury Frequency Rate (LTIFR ) is the 
number of accidents, including fatalities, taking 
place on Group premises within the reported 
period, measured against the number of man 
hours worked during that period per million man 
hours worked. LTIFR for the Group excludes 
IRC, which has separate HSE management 
systems.

Relevance
To guarantee that the Group’s occupational 
health and safety policies are successful, which 
includes providing protective measures and 
equipment and mitigating risks, the health and 
safety team continues to strive to maintain a safe 
environment at the Group’s operations. One of 
the key indicators that the Group relies upon to 
identify trends and areas of focus is the LTIFR. 
This is an integral part of a complex system 
covering the database of statistics, training 
programmes and operating parameters used for 
regular analysis and control. The measure 
ensures the Group’s compliance with Russian 
legislation and provides the Group with a basis 
for continuous improvement.

Performance in 2016
For the year ended 31 December 2016, Group 
operations recorded a LTIFR of 2.64 accidents 
per million man hours worked.

Regrettably there was one fatal accident during 
the year, which took place at Pokrovskiy in May.  
The accident was immediately reported to the 
HSE Committee and the Board. Following a full 
investigation by the Russian authorities with the 
full support of management at the site and of the 
Group, the Company was found to have acted 
properly and was not responsible for the 
accident. Unfortunately the employee had not 
followed proper procedures in this case which 
had led to this unfortunate accident. 

Following the investigation and a full report and 
review by both management and the HSE 
Committee, further training was provided to all 
employees. It is the Company’s practice to 
ensure that any such incidences are 
communicated to all relevant employees within 
the Group in order that lessons can be learned 
and to prevent such incidences reoccurring. 

18  Petropavlovsk Annual Report 2016    

Greenhouse Gas (‘GHG’) Emissions 

Methodology 
We have reported on all of the emission sources 
required under the Companies Act 2006 
(Strategic Report and Directors’ Reports) 
Regulations 2013. These sources fall within our 
consolidated financial statement. We do not 
have responsibility for any emission sources that 
are not included in our consolidated statement. 

We have adopted methodology for the planning 
and reporting of Green House Gases (GHG) 
according to the laws of the Russian Federation 
and have used one of the formulae, as approved 
under this legislation, for calculating the CO2 
equivalent (CO2e) associated with our 
consumption of Diesel, Kerosene, Benzene, and 
Coal.

Under Russian legislation, the GHG emissions 
associated with grid electricity are reported by 
the generator. However, for transparency 
purposes, the GHG emissions associated with 
our consumption of electricity have been 
reported below. This is measured in tonnes of 
carbon dioxide and calculated using the 2016 
IEA electricity conversion factor for the Russian 
Federation of 0.37959 kilograms of CO2 
equivalent per kilowatt hour.

All emissions quoted below are Gross as no 
deductions, for export of renewable energy or 
purchase of certified emission reduction, are 
applicable.

As a producer of gold, our prime metric is the 
amount of gold produced in a calendar year, 
measured in ounces. In 2016, Petropavlovsk 
produced 416,300ozs and has used this figure 
to calculate our intensity metric.

Source of Emissions
Emissions come from the following sources:

Diesel – as used in our fixed equipment including 
crushers, screens and pumps, and mobile 
equipment including excavators, trucks, 
bulldozers and cars.

Kerosene – as used in our helicopters.

Benzene – as used in our cars.

Coal – as used in our heating plants. All heat 
produced is used for our own consumption. 

Verification / Assurance
Quarterly reports of emissions against an 
approved plan are sent to the Russian 
Environmental Agency Rosprirodnazor.

Relevance
Monitoring GHG emissions enables the Group 
to look for opportunities to minimize its carbon 
footprint. Reducing emissions may also help 
decrease operating expenditure.

Going Forward
The Group continues to monitor GHG emissions 
and reviews all relevant data in order to identify 
opportunities for improvement.

Global GHG emissions data for period 1 January 2016 to 31 December 2016

Emissions from:
Combustion of fuel and operation 
of facilities (Tonnes of CO2e)
Electricity, heat, steam and 
cooling purchased for own use.
(Tonnes of CO2e)
Emissions reported above 
normalised per ounce of gold 
produced. (Tonnes of CO2e / oz)

Reporting year 
01.01.2016 – 31 12.2016

Comparison year 
01.01.2015 – 31 12.2015

182,407.9

260,194.9

222,847.3

276,144.1

0.97

1.07

  Petropavlovsk Annual Report 2016  19

Strategic reportFinancial statementsGovernanceRisks to Our Performance 

Introduction 
Risk management is the responsibility of 
the Board and is integral to the ability of the 
Group to deliver on its strategic objectives. 
The Board is responsible for establishing and 
maintaining appropriate systems and controls 
to manage risk within the Group and to ensure 
compliance with regulation.

potential impact on the Group is assessed 
and mitigating controls which seek to remove 
or minimise the likelihood and impact of the 
risks before they occur are implemented. 
Risks are then re assessed once appropriate 
mitigation is in place, although some risks 
by their nature cannot be mitigated by the 
Company.

wherever possible, although some, such as 
political risks, are largely beyond the Group’s 
control. Summarised alongside each risk is 
a description of its potential impact on the 
Group. Measures in place to manage or 
mitigate against each specific risk, where 
this is within the Group’s control, are also 
described. 

The Group’s risk management system is 
monitored by the Board, with the exception 
of (i) financial risks which are monitored by 
the Audit Committee and (ii) health, safety 
and environmental (‘HSE’) risks which 
are monitored by the HSE Committee. 
Financial risks and HSE risks are monitored 
under delegation by the Board. The risk 
management system aims to ensure that the 
Board’s focus is on those risks with the 
highest potential impact. Risks that could 
impact the business are considered in the 
broad categories detailed in the table below. 

The Executive Committee evaluates which 
of the risks detailed in the risk matrices 
constitute the material risks for the Group, 
in terms of potential impact and financial 
cost, with reference to its strategy and the 
operating environment. Those risks with the 
highest potential impact are then presented 
to the Board. The Executive Committee also 
focuses on any new and emerging risks.

The Board is responsible for overseeing 
the effectiveness of the internal control 
environment of the Group.

Responsibility for each category is delegated 
to a ‘Risk Owner’ within the Executive 
Committee. Each Risk Owner is responsible 
for identifying risks in their risk area and the 
most significant risks are recorded in risk 
registers. The likelihood of occurrence and 

Principal risks relating to the Group
The most significant risks that may have an 
adverse impact on the Group’s ability to 
meet its strategic objectives and to deliver 
shareholder value are set out on pages 22 to 
33. The Group seeks to mitigate these risks 

The risks set out below should not be 
regarded as a complete or comprehensive list 
of all potential risks and uncertainties that the 
Group may face which could have an adverse 
impact on its performance. Additional risks 
may also exist that are currently unknown 
to the Group and certain risks which are 
currently believed to be immaterial could 
turn out to be material and significantly affect 
the Group’s business and financial results.

Petropavlovsk’s principal risks and 
uncertainties are detailed in the table on the 
following pages and are supported by the 
robust risk management and internal control 
systems and procedures outlined on pages 
85 to 86.

Risk management framework

Petropavlovsk PLC Board

Audit Committee

HSE Committee

Executive Committee

Categorisation of risks  
and risk owners

Operational

Financial 

Factors which 
impact output such 
as inadequate 
or failed internal 
processes, 
systems or people 
or external events

Financial risks 
include market, 
credit and liquidity 
risks, the ability 
to raise finance 
or meet loan 
covenants or 
foreign exchange 
exposure 

Health, Safety  
and Environmental 
(‘HSE’)

Workplace hazards 
that could result in 
liability for the Group 
or have an adverse 
impact on output

Legal and 
Regulatory 

Human 
Resources

Risks associated 
with the recruitment 
and ongoing 
management 
of people

Risks that create 
potential for loss 
arising from 
uncertainty due 
to legal actions or 
uncertainty in the 
application of laws 
or regulations

CEO/COO

Chief Financial 
Officer 

CEO/COO

Group Head  
of Legal Affairs 

Chief Executive 
Officer

Investor Relations  
and External 
Communications 

Includes risks 
such as poor 
management 
of market 
expectations and 
false investor 
perception 

Group Head  
of External 
Communications 

20  Petropavlovsk Annual Report 2016    

Major changes from risks identified 
in the 2015 Annual Report
IRC Related Risks:
Petropavlovsk has provided a guarantee 
against a US$340 million project loan 
facility provided to K&S by ICBC to fund 
the construction of IRC’s iron ore mining 
operation at K&S of which c.US$234million 
principal was outstanding as at 31 December 
2016. On 31 March 2017, IRC announced that 
ICBC has waived the obligation of K&S to 
repay all loan principal instalments due in 
2017 totalling US$42.5million. This amount 
will be spread equally between the five 
subsequent repayment instalments due 
under the project finance facility. 

In addition, with its commissioning, K&S is 
successfully operating at 75% production 
capacity and the iron ore price has increased 
considerably during the year.

The above factors represent a significant 
reduction in the risk that there will be a 
claim on the Company’s guarantee in the 
immediate future and hence represent a 
significant reduction in the Company’s 
risk profile.

All IRC’s risks, including the potential 
impact of a decrease in the iron ore price, 
are included as one risk in the table below 
for ease of reference.

Political risk due to operating in Russia
The Group’s operations are based in Russia. 
Details regarding the financial and economic 
sanctions imposed on Russia in 2014 by the 
United States and the EU on certain businesses 
and individuals and the subsequent response 
by Russia are well known. 

There have recently been further 
developments regarding the political situation 
between Russia and the West which have 
been widely reported in the media. The Board 
and the Executive monitor the relevant issues 
on a continual basis. However it is recognised 
that this and other geopolitical risks cannot be 
influenced by the Company.  

The Board has decided that given that these 
issues are widely known and the Company is 
unable to influence this risk, it should be 
removed from the table of Principal Risks 
provided in this report. The Board will 
continue to monitor this risk.

As detailed above the following table includes 
the most significant risks that may have 
an adverse impact on the Group’s ability to 
meet its strategic objectives. More focus is 
therefore provided in the table on the risks 
related to the construction of the POX Hub 
and the underground mining project given 
that these are the most critical to the future 
growth and the financial viability of the Group. 

Group’s Mineral Resource 
and Ore Reserves:
The Group’s activities are reliant on the 
quantity and quality of its Mineral Resources 
and Ore Reserves. However these are 
estimates based on a range of assumptions 
including the results of exploratory drilling, 
ongoing sampling of the ore bodies, past 
experience with mining properties and the 
experience of the expert engaged to carry 
out the Reserves estimates. The Group has 
a detailed process of assuring the accuracy 
of its Mineral Resources and Ore Reserves. 
In addition, the Mineral Resources and Ore 
Reserves estimates which are included in this 
Report for the Group’s existing mining 
licences have been prepared in accordance 
with the guidelines of the JORC Code (2012) 
and have been reviewed and signed off by 
Wardell Armstrong International (“WAI”) in 
April 2017. WAI is an independent consultancy 
that provides the mineral industry with 
specialised geological, mining, and 
processing expertise. The Group also adopts 
a prudent gold price assumption when 
estimating its Ore Reserves, with an assumed 
long term gold price assumption of 
US$1,200oz used for the current estimates.

Given the assurance programme undertaken 
by the Group when estimating its Mineral 
Resources and Ore Reserves the ongoing 
inclusion of this risk as a ‘Principal Risk’ is no 
longer considered appropriate for inclusion in 
this report although it will continue to be 
monitored by the Board to ensure that the 
assurance programme remains appropriate. 
Consequently this risk is no longer included in 
the table of Principal Risks.

  Petropavlovsk Annual Report 2016  21

Strategic reportFinancial statementsGovernance 
Risks to Our Performance   continued

Table of principal risks

Operational risks

PRODUCTION RELATED RISK – Failure to achieve the Group’s production plan

Risk

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

Risk to production from:

 – Severe weather conditions.

 – The availability of suitable machinery, 

equipment and consumables.

 – Logistics for the delivery of equipment 

and services. 

Operational 
performance on pages 
36 to 43.

The Group’s assets are located in the Russian Far East, a remote area 
that can be subject to severe climatic conditions. Severe weather 
conditions, such as cold temperatures in winter and torrential rain, 
potentially causing flooding in the region could have an adverse impact 
on operations, including the delivery of supplies, equipment and fuel; 
and exploration and extraction levels may fall as a result of such climatic 
factors.

The Group relies on the supply and availability of various services and 
equipment in order to successfully run its operations. For example, 
timely delivery of mining equipment and jaw crushers and their 
availability is essential to the Group’s ability to extract ore from the 
Group’s assets and to crush the mined ore prior to production. Delay in 
the delivery or the failure of mining equipment could significantly delay 
production and impact the Group’s profitability.

The Group is dependent on production from its operating mines in order 
to generate revenue and cash flow and comply with the production and 
sales covenants in certain of its borrowing facilities. 

High

Preventative maintenance procedures are 

Flooding and unusually cold weather prevented 

undertaken on a regular and periodic basis to 

the Group delivering on the original 2016 mine 

ensure that machines will function properly under 

schedule resulting in a lower average processed 

extreme cold weather conditions; heating plants 

grade for 2016 and lower production. However 

at operational bases are regularly maintained and 

with strong capital discipline and dedicated cost 

operational equipment is fitted with cold weather 

control the Group achieved TCC of US$660oz, 

options which could assist in ensuring that 

equipment does not fail as a result of adverse 

weather conditions. 

Pumping systems are in place and tested 

improving the Group margin per ounce.

The Executive team and operational management 

responded well to the bad weather at Pioneer’s 

Andreevskaya deposit. A full impact assessment 

periodically to ensure that they are functioning.

including detailed mapping, recording and 

Management monitor natural conditions in order 

to pre-empt any disaster and in order that 

appropriate mitigating action can be taken 

expediently. The Group aims to maintain 

monitoring of rock fractures was carried out. 

Whilst any available mining fleet was temporarily 

utilised at Pioneer’s other operating pits. 

However the Company’s overriding commitment 

several months of essential supplies at each site. 

to the safety of its employees meant that delays in 

Equipment is ordered with adequate lead time in 

production at Pioneer were inevitable.

order to prevent delays in their delivery.

The Group has a number of contingency plans in 

place to address any disruption to services. 

EXPLORATION RELATED RISK

Risk

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

The Group’s activities are reliant on the 
quantity and quality of the Mineral 
Resources and Ore Reserves available to it.

Exploration activities are high risk, time consuming and can be 
unproductive. In addition, these activities often require substantial 
expenditure to establish Reserves through drilling and metallurgical and 
other testing, determine appropriate recovery processes to extract gold 
from the ore and construct or expand mining and processing facilities. 
Once deposits are discovered it can take several years to determine 
whether Reserves exist. During this time, the economic viability of 
production may change. As a result of these uncertainties, 
the exploration programmes in which the Group is engaged in may not 
result in the expansion or replacement of current production with new 
Reserves or mining operations.

Operational 
performance on pages 
36 to 43.

The Group uses modern geophysical and 

geochemical exploration and surveying 

Defined within Petropavlovsk’s substantial 

20.16Moz JORC Resource (7.95Moz JORC 

techniques. The Group employs a world class 

Reserve) is a 9.26Moz refractory gold Resource 

team of geologists with considerable regional 

(4.07Moz refractory Ore Reserve), with under 

expertise and experience. They are supported by 

explored resource upside within the highly 

a network of fully accredited laboratories capable 

prospective 3,600km2 licence areas.

High

of performing a range of assay work to high 

standards. 

The completion of the POX Hub will unlock the 

9.26Moz refractory Resource which supports 

The Group’s exploration budget is fixed for each 

Petropavlovsk’s long term growth objectives in 

asset at the start of each financial year 

depending upon previous results. 

doubling the average life of mine and sustaining 

its production profile.

During 2016 the Group continued to explore the 

potential for further mine life extension and 

production expansion.

 – At Malomir, exploration work has identified 

several highly prospective satellite refractory 

targets for further exploration work, including 

Ozhidaemoe. 

 – At Pioneer, refractory targets have been 

identified south of the main Pioneer orebody 

zone. The Alexandra zone and Sosnovaya 

licence are also expected to provide further 

refractory resource upside. 

22  Petropavlovsk Annual Report 2016    

   
   
The symbols indicate how the Company 
considers that these risks have changed 
since 2015.

Increased risk

New risk

No change 

Decreased risk

Operational risks

PRODUCTION RELATED RISK – Failure to achieve the Group’s production plan

Risk to production from:

 – Severe weather conditions.

 – The availability of suitable machinery, 

equipment and consumables.

 – Logistics for the delivery of equipment 

factors.

and services. 

The Group’s assets are located in the Russian Far East, a remote area 

Operational 

that can be subject to severe climatic conditions. Severe weather 

conditions, such as cold temperatures in winter and torrential rain, 

potentially causing flooding in the region could have an adverse impact 

on operations, including the delivery of supplies, equipment and fuel; 

and exploration and extraction levels may fall as a result of such climatic 

performance on pages 

36 to 43.

The Group relies on the supply and availability of various services and 

equipment in order to successfully run its operations. For example, 

timely delivery of mining equipment and jaw crushers and their 

availability is essential to the Group’s ability to extract ore from the 

Group’s assets and to crush the mined ore prior to production. Delay in 

the delivery or the failure of mining equipment could significantly delay 

production and impact the Group’s profitability.

The Group is dependent on production from its operating mines in order 

to generate revenue and cash flow and comply with the production and 

sales covenants in certain of its borrowing facilities. 

Risk

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

Preventative maintenance procedures are 
undertaken on a regular and periodic basis to 
ensure that machines will function properly under 
extreme cold weather conditions; heating plants 
at operational bases are regularly maintained and 
operational equipment is fitted with cold weather 
options which could assist in ensuring that 
equipment does not fail as a result of adverse 
weather conditions. 

Pumping systems are in place and tested 
periodically to ensure that they are functioning.

Management monitor natural conditions in order 
to pre-empt any disaster and in order that 
appropriate mitigating action can be taken 
expediently. The Group aims to maintain 
several months of essential supplies at each site. 
Equipment is ordered with adequate lead time in 
order to prevent delays in their delivery.

The Group has a number of contingency plans in 
place to address any disruption to services. 

High

Flooding and unusually cold weather prevented 
the Group delivering on the original 2016 mine 
schedule resulting in a lower average processed 
grade for 2016 and lower production. However 
with strong capital discipline and dedicated cost 
control the Group achieved TCC of US$660oz, 
improving the Group margin per ounce.

The Executive team and operational management 
responded well to the bad weather at Pioneer’s 
Andreevskaya deposit. A full impact assessment 
including detailed mapping, recording and 
monitoring of rock fractures was carried out. 
Whilst any available mining fleet was temporarily 
utilised at Pioneer’s other operating pits. 

However the Company’s overriding commitment 
to the safety of its employees meant that delays in 
production at Pioneer were inevitable.

EXPLORATION RELATED RISK

Risk

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

The Group’s activities are reliant on the 

quantity and quality of the Mineral 

Resources and Ore Reserves available to it.

Exploration activities are high risk, time consuming and can be 

Operational 

unproductive. In addition, these activities often require substantial 

performance on pages 

expenditure to establish Reserves through drilling and metallurgical and 

36 to 43.

other testing, determine appropriate recovery processes to extract gold 

from the ore and construct or expand mining and processing facilities. 

Once deposits are discovered it can take several years to determine 

whether Reserves exist. During this time, the economic viability of 

production may change. As a result of these uncertainties, 

the exploration programmes in which the Group is engaged in may not 

result in the expansion or replacement of current production with new 

Reserves or mining operations.

The Group uses modern geophysical and 
geochemical exploration and surveying 
techniques. The Group employs a world class 
team of geologists with considerable regional 
expertise and experience. They are supported by 
a network of fully accredited laboratories capable 
of performing a range of assay work to high 
standards. 

The Group’s exploration budget is fixed for each 
asset at the start of each financial year 
depending upon previous results. 

High

Defined within Petropavlovsk’s substantial 
20.16Moz JORC Resource (7.95Moz JORC 
Reserve) is a 9.26Moz refractory gold Resource 
(4.07Moz refractory Ore Reserve), with under 
explored resource upside within the highly 
prospective 3,600km2 licence areas.

The completion of the POX Hub will unlock the 
9.26Moz refractory Resource which supports 
Petropavlovsk’s long term growth objectives in 
doubling the average life of mine and sustaining 
its production profile.

During 2016 the Group continued to explore the 
potential for further mine life extension and 
production expansion.

 – At Malomir, exploration work has identified 

several highly prospective satellite refractory 
targets for further exploration work, including 
Ozhidaemoe. 

 – At Pioneer, refractory targets have been 

identified south of the main Pioneer orebody 
zone. The Alexandra zone and Sosnovaya 
licence are also expected to provide further 
refractory resource upside. 

  Petropavlovsk Annual Report 2016  23

Strategic reportFinancial statementsGovernance   
   
Risks to Our Performance   continued

Table of principal risks

Operational risks continued

PROJECT RELATED RISKS – Failure to deliver various construction and development projects
The Group’s long term strategy relies on the successful commissioning of the POX Hub and the delivery of the 
underground mining project. 

Risk

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

1.  Pressure Oxidation (POX) Hub.

If the Group is unable to commission POX within the projected budget 
and timeframes this may have an adverse impact on the Group’s growth 
plans and its future profitability.

Development Projects 
on pages 44 to 47.

2.  The underground mining project.

If the Group is unable to deliver underground mining production within 
the agreed budget and timeframes this may have an adverse impact on 
the Group’s growth plans and its future profitability.

Development Projects 
on pages 44 to 47.

The Group has entered into a management 

contract with Outotec a world leader in the 

design and construction of pressure oxidation 

and flotation plants. Outotec will oversee the 

manufacture, installation and commissioning of 

the equipment and has guaranteed certain 

operating parameters.

The Group’s pilot plant in Blagoveshchensk 

during 2013-2015 confirmed the feasibility of 

POX processing for Malomir and Pioneer 

concentrates.

POX has a special procurement process with a 

separate budget and expenditure schedule, 

monitored and signed off by the CEO, COO and 

CFO based on the approved budget. 

 – During 2016 the Company renewed key 

High

contracts with Outotec. 

 – As part of the recommencing of the POX Hub 

development Outotec (alongside the Company) 

ran checks on the major equipment in situ and 

commenced work on the automation and 

control systems.

 – Tests at the pilot plant continued.

Under the refinancing agreements with VTB and 

Sberbank (see page 109), the Group is required to 

complete the construction of POX out of its free 

cash flow.

The Group employed a Russian engineering firm 

 – An experienced firm of contractors commenced 

High

to undertake a pre-feasibility study and mine 

design on underground mining. The study 

the underground mining works at Pioneer 

working closely with the Group’s in house 

concluded that underground mining should be 

underground operations team.

technically feasible and economically viable. 

The Executive Committee and the Board 

closely monitor both the POX 

and underground mining projects. 

24  Petropavlovsk Annual Report 2016    

   
   
PROJECT RELATED RISKS – Failure to deliver various construction and development projects

The Group’s long term strategy relies on the successful commissioning of the POX Hub and the delivery of the 

Operational risks continued

underground mining project. 

Risk

1.  Pressure Oxidation (POX) Hub.

If the Group is unable to commission POX within the projected budget 

Development Projects 

and timeframes this may have an adverse impact on the Group’s growth 

on pages 44 to 47.

plans and its future profitability.

2.  The underground mining project.

If the Group is unable to deliver underground mining production within 

Development Projects 

the agreed budget and timeframes this may have an adverse impact on 

on pages 44 to 47.

the Group’s growth plans and its future profitability.

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

The Group has entered into a management 
contract with Outotec a world leader in the 
design and construction of pressure oxidation 
and flotation plants. Outotec will oversee the 
manufacture, installation and commissioning of 
the equipment and has guaranteed certain 
operating parameters.

The Group’s pilot plant in Blagoveshchensk 
during 2013-2015 confirmed the feasibility of 
POX processing for Malomir and Pioneer 
concentrates.

POX has a special procurement process with a 
separate budget and expenditure schedule, 
monitored and signed off by the CEO, COO and 
CFO based on the approved budget. 

The Group employed a Russian engineering firm 
to undertake a pre-feasibility study and mine 
design on underground mining. The study 
concluded that underground mining should be 
technically feasible and economically viable. 

 – During 2016 the Company renewed key 

High

contracts with Outotec. 

 – As part of the recommencing of the POX Hub 

development Outotec (alongside the Company) 
ran checks on the major equipment in situ and 
commenced work on the automation and 
control systems.

 – Tests at the pilot plant continued.

Under the refinancing agreements with VTB and 
Sberbank (see page 109), the Group is required to 
complete the construction of POX out of its free 
cash flow.

 – An experienced firm of contractors commenced 

High

the underground mining works at Pioneer 
working closely with the Group’s in house 
underground operations team.

The Executive Committee and the Board 
closely monitor both the POX 
and underground mining projects. 

  Petropavlovsk Annual Report 2016  25

Strategic reportFinancial statementsGovernance   
   
Risks to Our Performance   continued

Table of principal risks

Financial risks

FUNDING AND LIQUIDITY RELATED RISKS

Risk

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

The Group needs ongoing access to liquidity and funding in order to 
(i) refinance its existing debt as required, (ii) support its existing 
operations and (iii) invest in new projects and exploration. There is a risk 
that the Group may be unable to obtain the necessary funds when 
required or that such funds will only be available on unfavourable terms. 
The Group may therefore be unable to develop and/or meet its 
operational or financial commitments. 

The Group’s borrowing facilities include a requirement to comply with 
certain specified covenants in relation to the level of net debt and 
interest cover. A breach of these covenants could result in a significant 
proportion of the Group’s borrowings becoming repayable immediately. 

Chief Financial Officer’s 
Statement on pages 58 
to 69.

Detailed annual budgets are approved by the 

On 20 December 2016 the Group completed the 

Board and monthly forecasts provided. 

refinancing of US$430 million of its debt with its 

High

A successful cost reduction programme was 

lending banks Sberbank and VTB.

undertaken to offset the effect of a reduction in 

the gold price. 

The approved terms include a revised maturity 

profile from May 2018 to September 2022 

The Group continues to progress its internal KPI 

(inclusive of an option to extend the 2019 maturity 

to reduce total cash costs by 50% during the 

payment to 2022 subject to certain conditions 

period 2013-2018.

being satisfied) and an effective average interest 

rate of c.8%.

The Group is currently completing the final 

documentation for the Sberbank US$100m 

commodity linked loan facility. Once this has  

been completed the Group’s entire bank debt  

of c.US$530m will have been refinanced.

The financial and operational covenants were 

renegotiated during 2016 as part of the refinancing 

of the Group’s total debt.

Lack of funding and liquidity to allow the 
Group to 

i.  Support its existing operations;

ii.  Invest in and develop its exploration and 

underground mining projects;

iii.  Complete the construction of the POX 

Hub; 

iv.  Extend the life and capacity of its 

existing mining operations; 

v.   Refinance/repay the Group’s debt as it 

falls due; and

vi.   Complete the construction of the POX 

Hub out of its free cash flow.

If the operational performance of the 
business declines significantly the 
Company may breach one or more of the 
financial and production covenants as set 
out in various financing arrangements. 

GOLD PRICE RISK

Risk

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

The Group’s operational results may be 
affected by changes in the gold price.

The Group’s financial performance is highly dependent on the price 
of gold. A sustained downward movement in the market price for gold 
may negatively affect the Group’s profitability and cash flow and 
consequently its ability to fund the construction of the POX Hub. The 
market price of gold is volatile and is affected by numerous factors 
which are beyond the Company’s control.

Chief Financial Officer’s 
Statement on pages 58 
to 69.

The Executive Committee constantly monitors 

In order to increase certainty in respect of a 

the gold price and influencing factors on a daily 

significant proportion of its cash flows, the Group 

basis and consults with the Board as 

entered into a number of gold forward contracts 

High

appropriate. 

The Group has a hedging policy and hedges a 

portion of production as the Executive 

Committee and Board deem appropriate. 

during 2016. Forward contracts to sell 

an aggregate of 134,545oz of gold matured during 

the year and resulted in US$(8.5) million net 

settlement paid by the Group. 

Forward contracts to sell an aggregate of 

50,006oz of gold at an average price of US$1,303 

per oz were outstanding as at 31 December 2016. 

During 2017 the Company has continued to hedge 

a portion of its gold production in order to protect 

itself from volatility in the price.

26  Petropavlovsk Annual Report 2016    

   
   
Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

Lack of funding and liquidity to allow the 

The Group needs ongoing access to liquidity and funding in order to 

(i) refinance its existing debt as required, (ii) support its existing 

Chief Financial Officer’s 

Statement on pages 58 

operations and (iii) invest in new projects and exploration. There is a risk 

to 69.

i.  Support its existing operations;

ii.  Invest in and develop its exploration and 

that the Group may be unable to obtain the necessary funds when 

required or that such funds will only be available on unfavourable terms. 

The Group may therefore be unable to develop and/or meet its 

underground mining projects;

operational or financial commitments. 

The Group’s borrowing facilities include a requirement to comply with 

certain specified covenants in relation to the level of net debt and 

interest cover. A breach of these covenants could result in a significant 

proportion of the Group’s borrowings becoming repayable immediately. 

Detailed annual budgets are approved by the 
Board and monthly forecasts provided. 
A successful cost reduction programme was 
undertaken to offset the effect of a reduction in 
the gold price. 

The Group continues to progress its internal KPI 
to reduce total cash costs by 50% during the 
period 2013-2018.

On 20 December 2016 the Group completed the 
refinancing of US$430 million of its debt with its 
lending banks Sberbank and VTB.

High

The approved terms include a revised maturity 
profile from May 2018 to September 2022 
(inclusive of an option to extend the 2019 maturity 
payment to 2022 subject to certain conditions 
being satisfied) and an effective average interest 
rate of c.8%.

The Group is currently completing the final 
documentation for the Sberbank US$100m 
commodity linked loan facility. Once this has  
been completed the Group’s entire bank debt  
of c.US$530m will have been refinanced.

The financial and operational covenants were 
renegotiated during 2016 as part of the refinancing 
of the Group’s total debt.

Financial risks

FUNDING AND LIQUIDITY RELATED RISKS

Risk

Group to 

iii.  Complete the construction of the POX 

Hub; 

iv.  Extend the life and capacity of its 

existing mining operations; 

v.   Refinance/repay the Group’s debt as it 

falls due; and

vi.   Complete the construction of the POX 

Hub out of its free cash flow.

If the operational performance of the 

business declines significantly the 

Company may breach one or more of the 

financial and production covenants as set 

out in various financing arrangements. 

GOLD PRICE RISK

Risk

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

The Group’s operational results may be 

affected by changes in the gold price.

The Group’s financial performance is highly dependent on the price 

of gold. A sustained downward movement in the market price for gold 

Chief Financial Officer’s 

Statement on pages 58 

may negatively affect the Group’s profitability and cash flow and 

to 69.

consequently its ability to fund the construction of the POX Hub. The 

market price of gold is volatile and is affected by numerous factors 

which are beyond the Company’s control.

The Executive Committee constantly monitors 
the gold price and influencing factors on a daily 
basis and consults with the Board as 
appropriate. 

The Group has a hedging policy and hedges a 
portion of production as the Executive 
Committee and Board deem appropriate. 

High

In order to increase certainty in respect of a 
significant proportion of its cash flows, the Group 
entered into a number of gold forward contracts 
during 2016. Forward contracts to sell 
an aggregate of 134,545oz of gold matured during 
the year and resulted in US$(8.5) million net 
settlement paid by the Group. 

Forward contracts to sell an aggregate of 
50,006oz of gold at an average price of US$1,303 
per oz were outstanding as at 31 December 2016. 

During 2017 the Company has continued to hedge 
a portion of its gold production in order to protect 
itself from volatility in the price.

  Petropavlovsk Annual Report 2016  27

Strategic reportFinancial statementsGovernance   
   
Risks to Our Performance   continued

Table of principal risks

Financial risks

FX RISK

Risk

Currency fluctuations may affect the 
Group.

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

Chief Financial Officer’s 
Statement on pages 58 
to 69.

The Group has adopted a policy of holding a 

The Group does not undertake any foreign 

minimum amount of cash and monetary assets 

currency transaction hedging although this is 

High

or liabilities in non US Dollar currencies and 

operates an internal funding structure which 

seeks to minimise foreign exchange risk 

exposure.

kept under review. 

The Russian Rouble depreciated against the 

US Dollar during 2016, with an average exchange 

rate for 2016 of 67.18 Rouble per US Dollar compared 

with 61.30 Roubles per US dollar during 2015.

The Company reports its results in US Dollars, which is the currency in 
which gold is principally traded and therefore in which most 
of the Group’s revenue is generated. Significant costs are incurred in 
and/or influenced by the local currencies in which the Group operates, 
principally Russian Roubles. The appreciation of the Russian Rouble 
against the US Dollar tends to result in an increase in the Group’s costs 
relative to its revenues, whereas the depreciation of the Russian Rouble 
against the US Dollar tends to result in lower Group costs relative to its 
revenues.

In addition, a portion of the Group corporate overhead is denominated 
in Sterling. Therefore, adverse currency movements may materially 
affect the Group’s financial condition and results of operations.

In addition, if inflation in Russia were to increase without a 
corresponding devaluation of the Russian Rouble relative to the 
US Dollar, the Group’s business, results of operations and financial 
condition may be adversely affected.

IRC Related RISKS – The Company has a 31.10% interest in IRC, a Hong Kong Listed iron ore producer

Risk

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

Risk that funding may be demanded from 
Petropavlovsk under a guarantee in favour 
of ICBC arising from:

Inability of K&S to service the interest and 
meet the repayments due on the ICBC loan 
due to insufficient funds arising from:

Petropavlovsk has provided a guarantee against a US$340 million 
project loan facility provided to K&S by ICBC to fund the construction 
of IRC’s iron ore mining operation at K&S, of which c.US$234million 
is outstanding (2015: c.US$276million). This loan is supported by 
Sinosure, the Chinese export credit agency. In the event that K&S 
was to default on its loan, Petropavlovsk may be liable to repayment of 
the outstanding loan under the terms of the guarantee and other Group 
indebtedness may become repayable under cross default provisions

IRC on page 56.

Audit Committee Report 
on pages 80-86.

The Board and the Executive Committee 

maintain close communication with 

IRC’s Executive.

IRC and the Company continue to consider 

various options available to them, both separately 

and jointly, regarding the restructuring of IRC’s 

On 31 March 2017, IRC announced that ICBC has 

High

waived the obligation of K&S to repay all loan 

principal instalments due in 2017 totalling 

US$42.5million. This amount will be spread 

equally between the five subsequent repayment 

instalments due under the project finance facility. 

debt and the potential removal of the guarantee. 

In addition K&S is successfully operating at 75% 

 – Late commissioning of K&S

 – Decrease in iron ore price

A further delay in the commissioning of K&S 
and/or a decrease in the iron ore price 
could result in a decrease in the value of the 
Company’s shareholding in IRC.

Under the terms of the Company’s banking facilities with Sberbank and 
VTB, the Company is unable to provide any funds to IRC without the 
prior consent of these lenders.

production capacity and the iron ore price has 

increased considerably during 2017, rising to 

US$100 per tonne in March 2017. Based on IRC’s 

cost optimisation analysis the estimated unit 

cash cost of K&S is c.US$34 per tonne for product 

delivered to the Chinese border.

The above factors represent a significant reduction 

in the risk that there will be a claim on the 

Company’s guarantee in the immediate future and 

hence represents a significant reduction 

in the Company’s risk profile.

The Company’s interest in IRC was valued at 

US$36.140 million as at 31 December 2016 

(2015: US$39.163 million).

28  Petropavlovsk Annual Report 2016    

   
   
Financial risks

FX RISK

Risk

Group.

Currency fluctuations may affect the 

The Company reports its results in US Dollars, which is the currency in 

which gold is principally traded and therefore in which most 

Chief Financial Officer’s 

Statement on pages 58 

of the Group’s revenue is generated. Significant costs are incurred in 

to 69.

and/or influenced by the local currencies in which the Group operates, 

principally Russian Roubles. The appreciation of the Russian Rouble 

against the US Dollar tends to result in an increase in the Group’s costs 

relative to its revenues, whereas the depreciation of the Russian Rouble 

against the US Dollar tends to result in lower Group costs relative to its 

revenues.

In addition, a portion of the Group corporate overhead is denominated 

in Sterling. Therefore, adverse currency movements may materially 

affect the Group’s financial condition and results of operations.

In addition, if inflation in Russia were to increase without a 

corresponding devaluation of the Russian Rouble relative to the 

US Dollar, the Group’s business, results of operations and financial 

condition may be adversely affected.

IRC Related RISKS – The Company has a 31.10% interest in IRC, a Hong Kong Listed iron ore producer

Risk that funding may be demanded from 

Petropavlovsk under a guarantee in favour 

of ICBC arising from:

Inability of K&S to service the interest and 

meet the repayments due on the ICBC loan 

due to insufficient funds arising from:

 – Late commissioning of K&S

 – Decrease in iron ore price

A further delay in the commissioning of K&S 

and/or a decrease in the iron ore price 

could result in a decrease in the value of the 

Company’s shareholding in IRC.

Petropavlovsk has provided a guarantee against a US$340 million 

IRC on page 56.

Audit Committee Report 

on pages 80-86.

project loan facility provided to K&S by ICBC to fund the construction 

of IRC’s iron ore mining operation at K&S, of which c.US$234million 

is outstanding (2015: c.US$276million). This loan is supported by 

Sinosure, the Chinese export credit agency. In the event that K&S 

was to default on its loan, Petropavlovsk may be liable to repayment of 

the outstanding loan under the terms of the guarantee and other Group 

indebtedness may become repayable under cross default provisions

Under the terms of the Company’s banking facilities with Sberbank and 

VTB, the Company is unable to provide any funds to IRC without the 

prior consent of these lenders.

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

The Group has adopted a policy of holding a 
minimum amount of cash and monetary assets 
or liabilities in non US Dollar currencies and 
operates an internal funding structure which 
seeks to minimise foreign exchange risk 
exposure.

The Group does not undertake any foreign 
currency transaction hedging although this is 
kept under review. 

High

The Russian Rouble depreciated against the 
US Dollar during 2016, with an average exchange 
rate for 2016 of 67.18 Rouble per US Dollar compared 
with 61.30 Roubles per US dollar during 2015.

Risk

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

The Board and the Executive Committee 
maintain close communication with 
IRC’s Executive.

IRC and the Company continue to consider 
various options available to them, both separately 
and jointly, regarding the restructuring of IRC’s 
debt and the potential removal of the guarantee. 

High

On 31 March 2017, IRC announced that ICBC has 
waived the obligation of K&S to repay all loan 
principal instalments due in 2017 totalling 
US$42.5million. This amount will be spread 
equally between the five subsequent repayment 
instalments due under the project finance facility. 

In addition K&S is successfully operating at 75% 
production capacity and the iron ore price has 
increased considerably during 2017, rising to 
US$100 per tonne in March 2017. Based on IRC’s 
cost optimisation analysis the estimated unit 
cash cost of K&S is c.US$34 per tonne for product 
delivered to the Chinese border.

The above factors represent a significant reduction 
in the risk that there will be a claim on the 
Company’s guarantee in the immediate future and 
hence represents a significant reduction 
in the Company’s risk profile.

The Company’s interest in IRC was valued at 
US$36.140 million as at 31 December 2016 
(2015: US$39.163 million).

  Petropavlovsk Annual Report 2016  29

Strategic reportFinancial statementsGovernance   
   
Risks to Our Performance   continued

Table of principal risks

Health, safety and environmental risk

Risk that our employees or those visiting our operations may be injured

Risk

Mining:

 – is subject to a number of hazards and 

risks in the workplace 

 – requires the use of hazardous 
substances including cyanide 
and other reagents.

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

The Group’s employees are one of its most valuable assets. The Group 
recognises that it has an obligation to protect the health of its employees 
and that they have the right to operate in a safe working environment. 
Certain of the Group’s operations are carried out under potentially 
hazardous conditions. Group employees may become exposed to 
health and safety risks which may lead to the occurrence of work related 
accidents and harm to the Group’s employees. These could also result 
in production delays and financial loss.

Accidental spillages of cyanide and other chemicals may result 
in damage to the environment, personnel and individuals within the local 
community.

Environmental, Safety 
and Social Report on 
pages 34 to 35.

Legal and regulatory risks

Risks that legal or regulatory issues may impact the ability of the Group to operate

Risk

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

The Group requires various licences and 
permits in order to operate.

The Group’s principal activity is the mining of precious and non-precious 
metals which require it to hold licences which permit it to explore and 
mine in particular areas in Russia. These licences are regulated by 
Russian governmental agencies and if a material licence was 
challenged or terminated, this would have a material adverse impact on 
the Group. In addition, various government regulations require the 
Group to obtain permits to implement new projects or to renew existing 
permits. 

Failure to comply with the requirements and terms of these licences may 
result in the subsequent termination of licences crucial to operations 
and cause reputational damage. Alternatively, financial or legal 
sanctions could be imposed on the Group. Failure to secure new 
licences or renew existing ones could lead to the cessation of mining at 
the Group’s operations or an inability to expand operations.

30  Petropavlovsk Annual Report 2016    

Board level oversight of health and safety issues 

The Group operates a prompt incident reporting 

occurs through the work of the Health, Safety 

system to the Executive Committee and the 

and Environmental Committee (‘HSE’) which is 

Board. There were 34 lost time accidents during 

chaired by Mr Alexander Green, Independent 

2016 with a Lost Time Injury Frequency Rate 

Non-Executive Director. 

Health and Safety management systems are 

in place across the Group to ensure that the 

(‘LTIFR’) for 2016 of 2.64 accidents per 1 million 

manhours worked compared with 36 accidents in 

2015 and a LTIFR of 2.63.

operations are managed in accordance with the 

There was one fatality during 2016 (2015: 1). This 

Medium/High

relevant health and safety regulations 

and requirements. 

The Group continually reviews and updates 

its health and safety procedures in order 

to minimise the risk of accidents and improve 

accident response, including additional 

and enhanced technical measures at all sites, 

improved first aid response and the provision of 

further occupational, health and safety training. 

Cyanide and other dangerous substances are 

kept in secure storages with limited access only 

to qualified personnel, with access closely 

monitored by security staff.

H&S targets are included in the annual bonus 

scheme for Executive Directors and the 

Executive Committee.

fatality was reported immediately to the Chairman 

of the HSE Committee. A full investigation of this 

incident was conducted by the Russian authorities 

which concluded that the Company was not at 

fault for the accident. Records confirmed that the 

individual concerned had received all relevant 

training from the Company. The HSE Committee 

discussed this matter in detail to identify whether 

any actions should be taken or further training 

provided to mitigate against any reoccurrence of a 

similar accident. Action was taken by the Group’s 

management and H&S officers to reinforce correct 

behaviour to employees.

At the request of the HSE Committee the Group 

commenced a new ‘health and safety’ campaign 

specifically aimed at preventing accidents 

involving vehicles.

There were no accidents involving cyanide or other 

dangerous substances during 2016. 

There are established processes in place to 

monitor the required and existing licences and 

permits on an on going basis and processes are 

also in place to ensure compliance with the 

requirements of the licences and permits. 

Schedules are presented to the Executive 

Committee detailing compliance with the 

Group’s licences and permits. 

Medium/High

   
   
Health, safety and environmental risk

Risk that our employees or those visiting our operations may be injured

Risk

Mining:

 – is subject to a number of hazards and 

risks in the workplace 

 – requires the use of hazardous 

substances including cyanide 

and other reagents.

The Group’s employees are one of its most valuable assets. The Group 

recognises that it has an obligation to protect the health of its employees 

Environmental, Safety 

and Social Report on 

and that they have the right to operate in a safe working environment. 

pages 34 to 35.

Certain of the Group’s operations are carried out under potentially 

hazardous conditions. Group employees may become exposed to 

health and safety risks which may lead to the occurrence of work related 

accidents and harm to the Group’s employees. These could also result 

in production delays and financial loss.

Accidental spillages of cyanide and other chemicals may result 

in damage to the environment, personnel and individuals within the local 

community.

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

Medium/High

Board level oversight of health and safety issues 
occurs through the work of the Health, Safety 
and Environmental Committee (‘HSE’) which is 
chaired by Mr Alexander Green, Independent 
Non-Executive Director. 

Health and Safety management systems are 
in place across the Group to ensure that the 
operations are managed in accordance with the 
relevant health and safety regulations 
and requirements. 

The Group continually reviews and updates 
its health and safety procedures in order 
to minimise the risk of accidents and improve 
accident response, including additional 
and enhanced technical measures at all sites, 
improved first aid response and the provision of 
further occupational, health and safety training. 

Cyanide and other dangerous substances are 
kept in secure storages with limited access only 
to qualified personnel, with access closely 
monitored by security staff.

H&S targets are included in the annual bonus 
scheme for Executive Directors and the 
Executive Committee.

The Group operates a prompt incident reporting 
system to the Executive Committee and the 
Board. There were 34 lost time accidents during 
2016 with a Lost Time Injury Frequency Rate 
(‘LTIFR’) for 2016 of 2.64 accidents per 1 million 
manhours worked compared with 36 accidents in 
2015 and a LTIFR of 2.63.

There was one fatality during 2016 (2015: 1). This 
fatality was reported immediately to the Chairman 
of the HSE Committee. A full investigation of this 
incident was conducted by the Russian authorities 
which concluded that the Company was not at 
fault for the accident. Records confirmed that the 
individual concerned had received all relevant 
training from the Company. The HSE Committee 
discussed this matter in detail to identify whether 
any actions should be taken or further training 
provided to mitigate against any reoccurrence of a 
similar accident. Action was taken by the Group’s 
management and H&S officers to reinforce correct 
behaviour to employees.

At the request of the HSE Committee the Group 
commenced a new ‘health and safety’ campaign 
specifically aimed at preventing accidents 
involving vehicles.

There were no accidents involving cyanide or other 
dangerous substances during 2016. 

Risk

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

There are established processes in place to 
monitor the required and existing licences and 
permits on an on going basis and processes are 
also in place to ensure compliance with the 
requirements of the licences and permits. 
Schedules are presented to the Executive 
Committee detailing compliance with the 
Group’s licences and permits. 

Medium/High

Legal and regulatory risks

Risks that legal or regulatory issues may impact the ability of the Group to operate

The Group requires various licences and 

The Group’s principal activity is the mining of precious and non-precious 

permits in order to operate.

metals which require it to hold licences which permit it to explore and 

mine in particular areas in Russia. These licences are regulated by 

Russian governmental agencies and if a material licence was 

challenged or terminated, this would have a material adverse impact on 

the Group. In addition, various government regulations require the 

Group to obtain permits to implement new projects or to renew existing 

permits. 

Failure to comply with the requirements and terms of these licences may 

result in the subsequent termination of licences crucial to operations 

and cause reputational damage. Alternatively, financial or legal 

sanctions could be imposed on the Group. Failure to secure new 

licences or renew existing ones could lead to the cessation of mining at 

the Group’s operations or an inability to expand operations.

  Petropavlovsk Annual Report 2016  31

Strategic reportFinancial statementsGovernance   
   
Risks to Our Performance   continued

Table of principal risks

Legal and regulatory risks continued

Risks that legal or regulatory issues may impact the ability of the Group to operate

Risk

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

The Group is subject to risks associated 
with operating in Russia. 

Actions by governments or changes in economic, political, judicial, 
administrative, taxation or other regulatory factors or foreign policy in the 
countries in which the Group operates or holds its major assets could 
have an adverse impact on the Group’s business or its future 
performance. Most of the Group’s assets and operations are based in 
Russia. 

Russian foreign investment legislation imposes restrictions on the 
acquisition by foreign investors of direct or indirect interests in strategic 
sectors of the Russian economy, including in respect of gold reserves in 
excess of a specified amount or any occurrences of platinum group 
metals. 

The Group’s Pioneer and Malomir licences have been included on the 
list of subsoil assets of federal significance, maintained by the Russian 
Government (“Strategic Assets”). The impact of this classification is that 
changes to the direct or indirect ownership of these licences may 
require obtaining clearance in accordance with the Foreign Strategic 
Investment law of the Russian Federation.

To mitigate the Russian economic and banking 

This risk cannot be influenced by the management 

risk the Group strives to use the banking services 

of the Company. However, the Group continues to 

High

of several financial institutions and not keep 

monitor changes in the political environment and 

disproportionately large sums on deposit with 

reviews changes to the relevant legislation, 

a single bank.

policies and practices.

The Group seeks to mitigate the political and 

legal risk by constant monitoring of the proposed 

and newly adopted legislation to adapt to the 

changing regulatory environment in the countries 

in which it operates and specifically in Russia. 

It also relies on the advice of external counsel in 

relation to the interpretation and implementation 

within the Group of new legislation.

The Group closely monitors its assets and the 

probability of their inclusion into the Strategic 

Assets lists published by the Russian 

Government.

The Company’s Articles of Association include a 

provision which allows the Board to impose such 

restrictions as the Directors may think necessary 

for the purpose of ensuring that no ordinary 

shares in the Company are acquired or held 

or transferred to any person in breach of Russian 

legislation, including any person having acquired 

(or who would as a result of any transfer acquire) 

ordinary shares or an interest in ordinary shares 

which, together with any other shares in which 

that person or members of their group is deemed 

to have an interest for the purposes of the 

Strategic Asset Laws, carry voting rights, 

exceeding 50 per cent. (or such lower number as 

the Board may determine in the context of the 

Strategic Asset Laws) of the total voting rights 

attributable to the issued ordinary shares without 

such acquisition having been approved, where 

such approval is required, pursuant to the 

Strategic Asset Laws.

32  Petropavlovsk Annual Report 2016    

   
Legal and regulatory risks continued

Risks that legal or regulatory issues may impact the ability of the Group to operate

The Group is subject to risks associated 

with operating in Russia. 

Actions by governments or changes in economic, political, judicial, 

administrative, taxation or other regulatory factors or foreign policy in the 

countries in which the Group operates or holds its major assets could 

have an adverse impact on the Group’s business or its future 

performance. Most of the Group’s assets and operations are based in 

Russia. 

metals. 

Russian foreign investment legislation imposes restrictions on the 

acquisition by foreign investors of direct or indirect interests in strategic 

sectors of the Russian economy, including in respect of gold reserves in 

excess of a specified amount or any occurrences of platinum group 

The Group’s Pioneer and Malomir licences have been included on the 

list of subsoil assets of federal significance, maintained by the Russian 

Government (“Strategic Assets”). The impact of this classification is that 

changes to the direct or indirect ownership of these licences may 

require obtaining clearance in accordance with the Foreign Strategic 

Investment law of the Russian Federation.

Risk

Description and potential impact

Additional information

Mitigation/comments

2016 Progress

Potential impact

Change since 2015

To mitigate the Russian economic and banking 
risk the Group strives to use the banking services 
of several financial institutions and not keep 
disproportionately large sums on deposit with 
a single bank.

This risk cannot be influenced by the management 
of the Company. However, the Group continues to 
monitor changes in the political environment and 
reviews changes to the relevant legislation, 
policies and practices.

High

The Group seeks to mitigate the political and 
legal risk by constant monitoring of the proposed 
and newly adopted legislation to adapt to the 
changing regulatory environment in the countries 
in which it operates and specifically in Russia. 
It also relies on the advice of external counsel in 
relation to the interpretation and implementation 
within the Group of new legislation.

The Group closely monitors its assets and the 
probability of their inclusion into the Strategic 
Assets lists published by the Russian 
Government.

The Company’s Articles of Association include a 
provision which allows the Board to impose such 
restrictions as the Directors may think necessary 
for the purpose of ensuring that no ordinary 
shares in the Company are acquired or held 
or transferred to any person in breach of Russian 
legislation, including any person having acquired 
(or who would as a result of any transfer acquire) 
ordinary shares or an interest in ordinary shares 
which, together with any other shares in which 
that person or members of their group is deemed 
to have an interest for the purposes of the 
Strategic Asset Laws, carry voting rights, 
exceeding 50 per cent. (or such lower number as 
the Board may determine in the context of the 
Strategic Asset Laws) of the total voting rights 
attributable to the issued ordinary shares without 
such acquisition having been approved, where 
such approval is required, pursuant to the 
Strategic Asset Laws.

  Petropavlovsk Annual Report 2016  33

Strategic reportFinancial statementsGovernance   
Environmental, Safety and Social Report 

“Our job as senior leaders within the Company is not complete until we have returned 
unharmed each and every one of our employees to their families and friends after each shift 
rotation. As such, we are committed to continual improvement in the Group’s health and 
safety record.”  Alexander Green, HSE Committee Chair

The Board is mindful of the continuing focus 
on the value of gender diversity, though it has 
not and does not intend to set a target for the 
number of female Board members it has. 
It aims to appoint the best candidate available 
for any role. Alya Samokhvalova was a Board 
member until 30 April 2015, when she 
resigned following the restructuring of the 
Board. She remains with Petropavlovsk and in 
2016 was promoted to the position of Deputy 
CEO, Strategic Development. 

Occupational health and safety (OHS) risks 
are identified, reviewed and evaluated to 
mitigate their impact. All accidents are 
recorded and reported to the Executive 
Committee and Board. A Board level Health, 
Safety and Environmental Committee meets 
regularly and one of their duties is to assess 
and evaluate OHS management systems. 
Petropavlovsk also conducts regular on site 
inspections to ensure all operations comply 
with regulations.

It is Petropavlovsk’s duty as employer to 
ensure that employees are issued with 
contracts detailing their working hours, paid 
annual leave and other guarantees, in line with 
Russian or UK legislation (as applicable). In 
Russia, the Group operates in accordance 
with the Constitution of the Russian 
Federation, which details the rights and 
freedoms of citizens.

The Group has a zero tolerance approach to 
corruption and bribery and has adopted 
policies and procedures on preventing, 
combating and dealing with bribery and 
corruption, including a Code of Conduct and 
Business Ethics (the ‘Code’). The Code, which 
has been notified to all employees, both in the 
UK and in Russia, sets out the procedures that 
employees are expected to follow. 

At the mines, shift patterns help employees  
to maintain their family commitments whilst 
ensuring operations can run throughout the 
year. Employees work to shift patterns of a 
fortnight, month, or 45 days. Once each shift 
is complete, employees have the same 
amount of time off work. Commuting is 
impractical due to the remote location of  
the mines. Employees stay in purpose built 
accommodation on site, with recreational 
facilities and modern conveniences. 

Operating Responsibly 
Petropavlovsk is committed to providing its 
employees with a safe working environment. 
The Group fully complies with Russian labour 
legislation, the most significant of which is the 
Labour Code of the Russian Federation, and 
has health and safety systems in place that 
support the Code. Petropavlovsk conducts 
regular reviews of labour protection in the 
workplace and regularly examines all internal 
policies and procedures to ensure they 
remain robust and effective. 

Given the importance of anti bribery matters 
they are considered by the Executive 
Committee, which meets frequently. 
The responsibility for actions proposed  
as appropriate is taken by the Company 
Chairman, who reports on this formally to 
the Board. 

Engaging with Communities
Petropavlovsk communicates its 
development plans to local communities and 
ensures they are actively involved in the 
process. If issues are raised, they are 
addressed through public consultation. No 
public consultations were held in 2016. The 
Group continues to monitor circumstances in 
line with its commitment to maintaining good 
relationships with local communities and 
authorities.

The Petropavlovsk Foundation was 
established in 2010 to support the Group in 
promoting development in the Russian Far 
East, with particular focus on the Amur 
region. The Foundation aims to provide local 
communities with social, economic and 
cultural opportunities, improving quality of  
life and encouraging investment in the region. 
It works closely with regional stakeholders, 
from federal groups to small businesses. 

Petropavlovsk understands the importance of 
maintaining solid relationships with its many 
stakeholders and is proud of the progress 
made since inception in 1994. The Group 
believes its approach has contributed to its 
success to date. 

In 2016, independent technical auditors 
Wardell Armstrong confirmed that 
environmental and social performance at  
the Petropavlovsk assets is managed well  
and to a high standard. All four projects are 
fully permitted and each aspect has been 
reviewed and approved by State expertise. 
Social and community management is well 
established and it is understood that there is 
almost universal support for the operations 
within the local community.

Working at Petropavlovsk
Petropavlovsk recognises the socioeconomic 
influence it has as a major employer and 
taxpayer in the Amur region. The Group 
understands that its employees are a key asset 
and invests in them accordingly, leveraging 
their expertise and providing continuous 
development. The Pokrovskiy Mining College, 
which aims to offer employment opportunities 
to graduates, was established in 2008 to 
provide future employees with specialised 
training, tailored to the needs of the Group.

The Group is proud to provide equal 
opportunities and pay in all aspects of 
employment, regardless of gender or 
background, as required by both Russian and 
UK legislation. Women have the opportunity to 
reach the highest levels of senior management 
– that the Group has a disproportionately high 
ratio of male to female employees is a reflection 
of historic trends in the mining sector. 

As at 31 December 2016, 1,857 employees 
were female, representing c.23% of the 
Group’s total workforce. 

The Board considers its senior management 
to be the Executive Committee, which is 
responsible for managing the company day to 
day. This comprises three Executive Directors 
and seven members of senior management. 
As at 31 December 2016, two of its members 
were female, representing c.29% of total 
membership.

34  Petropavlovsk Annual Report 2016    

The Foundation supports a range of causes 
that fall beneath its five areas of strategic 
investment: 

 – Future Generations (Child Development) 

 – Research and Development 

The environment is monitored throughout  
the line of each mine to identify any impact  
its activities might have on the surrounding 
ecosystem. Data is collected according to 
state approved schedules and samples 
analysed in state accredited laboratories. 

Breakdown of total number of employees 
as at 31 December 2016

1,857

Female employees
Male employees

6,364

Breakdown of members of the executive 
committee as at 31 December 2016

2

Female members
Male members

8

All Group operations hold licences with water 
usage quotas detailing where water may or 
may not be used from. Pit water is purified 
before it is discharged and local water is 
continuously monitored. The Group’s RIP 
plants use recycled water, reducing demand 
from local sources.

Waste management programmes are agreed 
with regulatory authorities in compliance with 
Russian legislation. The programmes detail 
standards and limits on what can be 
produced or disposed of. Data on waste  
is collected, logged and sent to regulatory 
authorities for review.

The Group is governed by laws designed to 
limit industrial impact on ecosystems. Land 
may only be cleared within the limits of 
licences and permits, for instance, and in 
designated areas it is forbidden to fish, hunt, 
poach or drive vehicles.

Petropavlovsk uses purification systems, anti 
dust equipment and other protective facilities 
to prevent harmful substances entering the 
atmosphere. Gas purification equipment is  
at all emission points and is monitored on a 
regular basis. Air quality monitoring includes 
carbon monoxide and dust emissions and  
is performed according to mining and 
environmental monitoring programmes, which 
are agreed in advance with federal authorities. 

The Group has modern systems in place for 
the handling of cyanide.

 – Culture

 – Quality of Life

 – Sport.

In 2016, the Foundation received funding from 
the Civic Chamber of the Russian Federation for 
a sociological research project into wellbeing in 
the Amur region. The results contributed to 
important work on demographic policy in the 
Russian Far East. Alongside this it continued to 
make significant progress with its Albazino 
archaeological project, which became a finalist 
for the national Crystal Globe award. In 2015, the 
project received funding from both the Ministry 
of Culture and the Russian Geographical 
Society, along with a certificate presented by 
Russian President Vladimir Putin, who chairs the 
Society’s Board of Trustees. 

Managing the Environment
Petropavlovsk is committed to effectively 
managing environmental issues, upholding 
the highest standards as required by Russian 
law, and operating in line with international 
best practice.

In 2016, all Group Mines adopted the 
Declarations on the Technical Regulation TR 
TS 030/2012 concerning lubricants, oils and 
speciality fluids, based on the Customs Union 
agreement (Russia, Kazakhstan, Belarus), 
and following ratification and introduction into 
Russian legislation. These declarations are 
adopted at all our sites and are aimed at 
minimizing the potential negative effects  
of such materials. Also in 2016, the Group 
prepared to renew certification for ISO:14000 
amid updated interstate ratification, 
finalisation and approval processes.

The Group requires licences and permits from 
Russian authorities for some operational 
activities (mining and exploration, construction, 
handling hazardous waste and using local water 
supplies). These may detail limits and conditions 
to help protect the environment. The Group 
must also draw up environmental impact 
assessments for mining project permits to be 
considered, in line with Russian legislation.

  Petropavlovsk Annual Report 2016  35

Strategic reportFinancial statementsGovernanceOperational Performance 

Pioneer

Acquired as greenfield licence in 2001 

Developed into one of Russia’s largest gold operations 

Produced 2.3Moz ounces of gold since 2008 

Expected +15year life of mine

Introduction 
Pioneer is one of the Group’s most prospective assets, providing near term growth potential from underground 
non-refractory exploration and development, and regional exploration (Pioneer flanks). Long term growth 
potential includes bringing forward the flotation plant (6.0Mtpa) development, currently scheduled for 2021, 
and the untapped greenfield exploration potential within its 1,375km2 total licence area. 

Operating Mine

Underground

Lime deposit

POX

Analytical Labs

Hydro Plant

Railway

Federal highway

Core assets

Blagoveschensk

Pokrovskiy POX Hub

Pioneer

2016 gold production 
141.9koz – 34% of total Group 
gold production for the year.

Key facts 

2016 Progress

2017 Targets

–  Located in the south of the Amur region, 450km from 

–  Maintained total cash costs 

–  Commence mining from 

Production as a % of total group

Blagoveshchensk, the China border trade city and regional 
business hub 

  –  Situated between the BAM and Trans-Siberian Railway, 
with the nearest station approximately 40km away 

  –  63km from the largest regional hydropower station (5GW) 

–  Hard rock non-refractory and refractory deposit 

–  Reserves and Resources 5.52Moz 

  – 44% non-refractory Mineral Resource

  – 27% of total Group Mineral Resource 

–  Open pit mining 

  –  Underground mining to commence Q2 2017 

–  6.7Mtpa RIP plant and seasonal heap leach facility on site 

–  Annual LTIFR of 3.4 per million man hours worked.

below US$650/oz 

–  Commenced development of our 

maiden underground mine at 
NE Bakhmut in Q3

–  First ore from underground 

scheduled to be mined in Q2 2017

–  Significantly increased existing 
underground Mineral Resource 
and defined first Ore Reserve at 
NE Bakhmut

–  Enhanced understanding of high 
grade underground zones and 
continuity of mineralisation 
at depth 

–  Discovery of new Katrin orebody 
within the Sosnovaya licence.

underground, ramping up to 
200ktpa throughout the year

–  Progress underground 

development into the deeper  
NE Bakhmut 3 higher grade 
main area

–  Maintain open pit mining and 

operating excellence

–  Reduce LTIFR.

36  Petropavlovsk Annual Report 2016    

 
Geology 
Gold mineralisation at Pioneer was formed 
near a contact between a multiphase 
granitoid massif and Jurassic country rocks 
as a result of hydrothermal activity associated 
with volcanism during the late Mesozoic 
Period. The mine is located on the south side 
of the Mongolo-Okhotskiy thrust line, within 
the belt of mineralisation associated with the 
collision of the Eurasian and Amur plates. 

The Pioneer deposit consists of multiple 
identified orebodies, most of which are steep 
dipping and remain open in a down dip 
direction. Pioneer orebodies comprise of high 
grade shoots and lower grade halo 
mineralisation. The high grade shoots are 
normally 1 to 8 metres in thickness with a 
strike length up to 400m. The more moderate 
grade halos are up to 200m thick with a strike 
length of up to 2km. 

Mining and Processing 
Pioneer is a multiple open pit, bulk tonnage, 
owner operator mine. The mining fleet consists 
of approximately 100 pieces of major mining 
equipment. Mining productivity and equipment 
utilisation is optimised by operating two daily 
shifts, throughout the year. 

Underground development commenced  
at NE Bakhmut in Q3 2016 by a reputable 
Russian mining contractor, with ore mining  
to commence in Q2 2017. 

The Pioneer orebodies include both non-
refractory and refractory ore. Non-refractory 
ore is processed at the 6.7Mtpa RIP plant, 
which operates throughout the year. 
Refractory ore does not respond to standard 
RIP processing methods – specifically it is not 
suitable for direct cyanidation processing. 
The Group is currently developing a 
processing plant, the POX Hub, to treat its 
significant refractory ore reserve base. 
The POX Hub is due to be completed and 
commissioned from Q4 2018, with Pioneer 
concentrate scheduled to be processed 
from 2023.

Low grade non-refractory ore (<0.5g/t) is 
processed via an onsite seasonal heap 
leach operation. 

Operational Performance 
Pioneer open pits produced 141.9koz, 
representing 34% of the Group consolidated 
annual gold production. This was a 39% 
decrease from 2015 (2015: 231.4koz). 
Ore was mined from Alexandra, Bakhmut, 
Vostochnaya and taken from stockpiles. 
Following extensive waste stripping 

Pioneer mining operations

Total material moved
Ore mined
Average grade
Gold content

Processing operations (Resin-in-pulp plant)

Total milled
Average grade
Gold content
Recovery rate
Gold recovered
Heap leach operations
Ore stacked
Average grade
Gold content
Recovery rate
Gold recovered
Total gold recovered

Units
m3 ’000
t ’000
g/t
oz. ’000

Year ended  
31 December 2016
17,360
3,266
0.95
99.4

Year ended  
31 December 2015
23,980
6,016
1.28
248.4

Units
t ’000
g/t
oz. ’000
%
oz. ’000

t ’000
g/t
oz. ’000
%
oz. ’000
oz. ’000

Year ended  
31 December 2016
6,700
0.74
159.8
85.5%
136.6

Year ended  
31 December 2015
6,582
1.25
264.5
85.0
224.7

701
0.53
12.0
44.1%
5.3
141.9

800
0.56
14.5
46.2
6.7
231.4

throughout the year, high grade ore was 
expected from the Andreevskaya East pit  
in Q4 2016. However, unusual weather 
conditions resulted in disruptions and 
ultimately deferred access to the high grade 
zone (into 2017) resulting in an average grade 
mined of 0.95g/t, 35% lower than 2015. 

Underground development has commenced, 
with stope mining scheduled to start in Q2 
2017. Including the ventilation decline, a total 
of 675m of decline development was 
completed in 2016. 

The RIP plant processed 6.7Mtpa of ore, a  
2% increase on 2015. Metallurgical recovery 
averaged 85.5%, a 1% increase on 2015.

The heap leach operation produced 5.3koz, 
a 21% decrease from 2015 (2015: 6.7koz). 

The plant performed as expected, delivering 
on all technological performance indicators. 

Total cash costs were US$631/oz, a 1% 
increase on 2015. All in sustaining costs were 
US$789/oz, a 5% increase from 2015. 

Exploration Overview
The brownfield exploration programme 
focused primarily on near mine resource 
expansion and NE Bakhmut underground 
resource to reserve conversion. Limited deep 
level surface drilling at Bakhmut, 
Promezhutochnaya and Andreevskaya 
focused on identifying potential underground 
high grade mineralisation below the 
reserve pits.’

2017 Outlook 
The 2017 Pioneer production profile is 
expected to be in line with 2016, underpinned 
by open pit operations at Alexandra, 
Yuzhnaya, Promezhutochnaya and NE 
Bakhmut 4 and 5, in addition to deferred high 
grade material from Andreevskaya East, as a 
result of the mining disruptions late in 2016. 

Operations are due to begin in 2017 at the 
maiden underground mine at NE Bakhmut, 
which is set to provide production upside. 
High grade underground mining is scheduled 
to commence in H2 2017. In addition, the 
underground exploration drilling programme 
is to begin at the deeper extensions below the 
defined resource, where deep surface drilling 
has intersected high grade mineralisation.

  Petropavlovsk Annual Report 2016  37

Strategic reportFinancial statementsGovernanceOperational Performance   continued

Albyn

 Acquired as greenfield licence in 2005

 Developed into Petropavlovsk’s largest producing mine 

Produced 749koz ounces gold since 2011

Expected +15 year life of mine

Introduction 
Albyn is currently the Company’s largest producing mine with a 100% non-refractory defined resource base. 
The highly prospective 1,100km2 licence area is largely under explored, presenting potential near term upside 
from high grade, non-refractory resources to be discovered. The main orebodies at Albyn are open in a down 
dip direction beyond of the feasible depth of open pit mining, offering longer term growth potential to establish 
resources and reserves for underground mining.

Operating Mine

Analytical Labs

Hydro Plant

Railway

Federal highway

Core assets

Blagoveschensk

2016 gold production 
180.0koz – 43% of total Group 
gold production for the year.

Albyn

Production as a % of total group

Key facts 

2016 Progress

2017 Targets

–  Located in the north east of the Amur region, 720km from 

–  Reduced total cash costs and 

–  Commence mining at 

Blagoveshchensk, the China border trade city and regional 
business hub. 2km away from town of Zlatoustovsk – a 
center of local alluvial gold mining. 

  –  BAM railway 280km away

–  Hard rock non-refractory deposit

–  Reserves and Resources 4.77Moz 

  –  100% non-refractory 

   –  24% of total Group Mineral Resource 

–  Open pit mining 

–4.7Mtpa RIP plant on site

–  Annual LTIFR of 2.6 per million man hours worked.

all-in sustaining costs by greater 
than 20%

Unglichikan to provide additional 
high grade ore for Albyn plant

–  Significantly increased Ore 
Reserves at Elginskoye, 
demonstrating sustainable 
production and extended life of 
mine potential

–  Encouraging initial results 

showing 3km strike extension 
at Yasnoye

–  Completed infill drill programme  

on the southern end of 
Unglichikan deposit in 
preparation for mining to 
commence in 2017.

–  Drill deeper targets below Albyn 

pit to model and assess 
underground potential

–  Exploration programme at 

Unglichikan and Afanasevskoye 
to further expand Albyn’s 
non-refractory reserve and 
resource base and subsequent 
life of mine

–  Sustain open pit mining and 

operating excellence. 

38  Petropavlovsk Annual Report 2016    

 
Geology 
The mine is located on the Mongolo-
Okhotskiy thrust zone, within the belt of 
mineralisation associated with the collision of 
the Eurasian and Amur plates. The 
mineralisation at Albyn comprises a series of 
gently dipping, sub parallel metasomatic 
zones, which appear to be open in a down dip 
direction. They show variable thickness and 
grade, extending for c.4.5km in strike length. 

The Albyn licence area consists of multiple 
orebodies within four key deposits: Albyn, 
Elginskoye, Unglichikan and Afanasevskoye. 
All these orebodies are open in down dip 
direction. Elginskoye, Unglichikan and 
Afanasevskoye are also open along strike. 

In addition to these four proven deposits there 
are number of known exploration targets of 
which Ulgen, Yasnoye and Leninskoe are the 
most significant. The majority of the 1,100km2 
licence area remains under explored and 
highly prospective. 

Mining and Processing
Albyn is a large (2.2km in length), open pit,  
bulk tonnage operation. The mining fleet 
consists of 101 pieces of major mining 
equipment. Mining productivity and equipment 
utilisation is optimised by operating two daily 
shifts throughout the year. 

The Albyn licence includes multiple defined 
orebodies. All are non-refractory and can be 
treated at the 4.7Mtpa RIP plant, which 
operates throughout the year. 

Operational Performance
Albyn produced 180.0koz, representing  
43% of the Group’s consolidated annual gold 
production. This was a 14% increase on 2015 
(2015: 157.6koz). Ore was mined throughout 
the year from Eastern and Northern sections 
of the pit and processed from stockpiles. 
The average annual mined grade was 
1.25 g/t, a 9% increase on 2015, due to 
reduction in dilution and mining from the 
thicker main zone. 

The RIP plant processed 4.68Mtpa of ore, a 
2% increase on 2015. Metallurgical recovery 
averaged 93.5%, a marginal improvement 
on 2015.

Albyn mining operations

Total material moved
Ore mined
Average grade
Gold content

Processing operations (Resin-in-pulp plant)

Total milled
Average grade
Gold content
Recovery rate
Gold recovered
Total gold recovered

Units
m3 ’000
t ’000
g/t
oz. ’000

Year ended  
31 December 2016
31,763
4,970
1.25
199.5

Year ended  
31 December 2015
36,722
4,906
1.15
181.5

Units
t ’000
g/t
oz. ’000
%
oz. ’000
oz. ’000

Year ended  
31 December 2016
4,675
1.28
192.5
93.5%
180.0
180.0

Year ended  
31 December 2015
4,600
1.14
168.8
93.3
157.6
157.6

2017 Outlook 
The 2017 Albyn production profile continues 
to be underpinned by open pit operations at 
Albyn, with a moderate contribution from the 
Unglichikan deposit (as a new pit). 

Based on recent successes extending mine 
life at Albyn with Elginskoye, the key focus for 
2017 is on further exploration at Unglichikan 
and Afanasevskoye, to expand the non-
refractory reserve and resource base and 
subsequent life of mine. In 2017, the Group 
plans to surrender the Kharginskoye licence 
as the decision has been made to 
concentrate exploration at better targets 
within other Albyn licences.

The plant performed as expected, delivering 
on all technological performance indicators. 

Now the Group’s largest producing mine, 
Albyn has successfully been a key target for 
cost reduction. Total cash costs of US$581/oz 
were achieved, a 22% improvement on 2015, 
with all-in sustaining costs of US$719/oz, a 
21% improvement on 2015. This was primarily 
due to higher processed grades and higher 
operational recoveries. 

Exploration Overview
The Exploration programme was successful 
in the conversion of resources to reserves at 
Elginskoye. Mining preparation drilling at 
Unglichikan resulted in an increase in 
resources. Earlier stage exploration surveying 
and trenching yielded encouraging results for 
potential resource expansion at Yasnoye, 
Ulgen, and Sergeevskaya. 

Exploration Performance 
Exploration results obtained from other 
exploration targets within the Albyn project to 
date have been promising. The main 
orebodies at Albyn are open in a down dip 
direction beyond of the feasible depth of open 
pit mining. This offers exploration potential to 
establish mineral resource and ore reserves 
for underground mining.

  Petropavlovsk Annual Report 2016  39

Strategic reportFinancial statementsGovernanceOperational Performance   continued

Malomir

Acquired as greenfield licence in 2003

Developed into Petropavlovsk’s largest asset by Reserve & Resource

Produced 542koz ounces gold since mid 2010

Expected +16 year life of mine.

Introduction 
Malomir is the Group’s largest asset by Reserves and Resources with approximately 90% of the Reserve base 
categorised as refractory ore. Completing the POX Hub, which is scheduled for the end of 2018, will unlock 
material value embedded with the existing defined asset base and extend the expected life of mine to greater 
than 16 years, with untapped resource potential within the 964km2 licence area.

Operating Mine

Underground

Lime deposit

POX

Analytical Labs

Hydro Plant

Railway

Federal highway

Core assets

Blagoveschensk

Malomir

Pokrovskiy POX Hub

2016 gold production 
56.8koz – 14% of total Group gold 
production for the year.

Key facts 

2016 Progress

2017 Targets

Production as a % of total group

–  Located in the north-east of the Amur region, 550km from 
Blagoveshchensk, the China border trade city and regional 
business hub

  –  BAM railway 130km away

–  Hard rock non-refractory and refractory deposit 

–  Reserves and Resources 7.06Moz 

  –  13% non-refractory Mineral Resource

  –  35% of total Mineral Rroup resource 

–  Open pit mining 

  –  Underground mining to commence H2 2017 

–  3.0Mtpa RIP plant on site

–  Annual LTIFR of 4.5 per million man hours worked.

–  Reduced total cash cost by 25%

–  Complete and commission the 

–  Completed underground 

feasibility study at Quartzitovoye 
and appointed underground 
contractor

–  Increased existing underground 

Mineral Resource and defined first 
Ore Reserve at Quartzitovoye

–  Enhanced understanding of high 
grade underground zones and 
continuity of mineralisation 
at depth.

3.6Mtpa (Stage 1) flotation plant, 
with production and stockpiling 
of refractory concentrate from 
early 2018 ahead of the POX Hub 
commissioning

–  Commenced underground 

development at Quartzitovoye 
– mining scheduled to start from 
H2 2017

–  Prepare underground drill 

chambers ahead of exploration 
drill programme to delineate the 
extent and continuity of the high 
grade mineralisation

–  Sustain open pit mining and 

operating excellence

–  Reduce LTIFR.

40  Petropavlovsk Annual Report 2016    

 
Geology 
The Malomir licence is situated along and 
above a major thrust zone within the 
Mongolo-Okhotskiy mineralised belt. It is 
hosted by upper Palaeozoic meta sediments, 
mainly carbonaceous shales, which are 
affected by low grade regional metamorphism 
and locally intense metasomatic alteration 
with associated hydrothermal mineralisation. 

The Malomir project includes multiple 
identified orebodies of which Malomir, 
Quartzitovoye, Ozhidaemoye and 
Magnetitovoye are the most significant. 

Mining and Processing
Malomir is an open pit operation. The mining 
fleet consists of 52 pieces of major mining 
equipment. Mining productivity and equipment 
utilisation is optimised by operating two daily 
shifts throughout the year. 

Underground development commenced at 
Quartzitovoye, with ore mining due to begin in 
H2 2017. 

The Malomir licence includes multiple 
orebodies, which contain both refractory and 
non-refractory ore. The higher grade 
non-refractory ore at Quartzitovoye and 
Magnetitovoye is processed at the 3.0Mtpa 
RIP plant, operational throughout the year. 
The refractory ore from Ozhidaemoye does 
not respond to standard RIP processing 
methods – specifically it is not suitable for 
direct cyanidation. The Group is currently 
developing a processing plant, the POX Hub, 
to treat the Group’s significant refractory 
reserve base. This includes a 5.4Mtpa 
flotation plan at Malomir, which will be 
constructed in two stages. Stage 1 (3.6Mtpa) 
is expected to be commissioned by the end of 
2017. The POX Hub is due to be completed 
and commissioning from Q4 2018. Planned 
production from refractory reserves relies on 
the completion of a flotation plant at Malomir, 
currently 90% complete and scheduled to be 
commissioned in Q4 2017. The flotation plant 
will convert the refractory reserves into higher 
grade flotation concentrate, which will be sent 
to the POX Hub for processing.

Malomir concentrate is scheduled to be 
processed from 2018.

Malomir mining operations

Total material moved
Ore mined
Average grade
Gold content

Processing operations (Resin-in-pulp plant)

Total milled
Average grade
Gold content
Recovery rate
Gold recovered
Total gold recovered

Units
m3 ’000
t ’000
g/t
oz. ’000

Year ended  
31 December 2016
8,115
1,535
1.11
54.9

Year ended  
31 December 2015
8,904
2,105
1.01
68.5

Units
t ’000
g/t
oz. ’000
%
oz. ’000
oz. ’000

Year ended  
31 December 2016
3,000
0.86
82.5
68.9%
56.8
56.8

Year ended  
31 December 2015
2,937
0.93
88.0
67.2
59.1
59.1

Deep drilling from the surface (up to 200m 
below the current pit floor) has successfully 
defined additional underground resource  
and first reserve, supporting a sustainable  
6 year production plan at Quartzitovoye. 
The orebody remains open at depth. 

2017 Outlook
The 2017 Malomir production profile is 
expected to be in line with 2016, with 
sustainable production upside from 
underground mining operations commencing 
in H2 2017. 

In Q4 2017, Malomir will begin to transition  
into the Group’s flagship asset in line with the 
scheduled completion and commissioning  
of the Stage 1 3.6Mtpa flotation plant to 
process refractory ore. From 2018, Malomir 
concentrate production and stockpiling  
will continue to ensure the POX Hub 
commissioning, scheduled for Q4 2018, 
runs smoothly.

Operational Performance 
Malomir produced 56.8koz, representing 
14% of the Group consolidated annual gold 
production. This was 4% lower than 2015 
(2015: 59.1koz). Ore was mined throughout 
the year from Quartzitovoye 2, Magnetitovoye, 
and stockpiles. The average annual mined 
grade was 1.11g/t, a 10% improvement on 
2015. This takes into account waste stripping 
at Quartzitovoye 1 throughout most of the 
year, in order to prepare access to ore 
for 2017. 

The RIP plant processed 3.0Mtpa of ore, a 
2% increase on 2015. Metallurgical recovery 
averaged 68.9%, a 3% improvement on 2015. 
The plant performed as expected in 2016, 
delivering on all technological performance 
indicators. 

Total cash costs of US$824/oz were achieved, 
a 25% improvement on 2015, with all-in 
sustaining costs of US$1004/oz, a 15% 
improvement on 2015, primarily due to 
improved operational recoveries.

Exploration Overview
Drilling confirmed high grade mineralisation 
continues at depth, with the deepest holes 
greater than 440m below the surface (245m 
below the reserve pit) intersecting potentially 
economical grades and thicknesses. 
The orebody remains open in a down dip 
direction offering potential to increase 
resources further through additional 
exploration, which will be continued from  
the underground workings. 

  Petropavlovsk Annual Report 2016  41

Strategic reportFinancial statementsGovernanceOperational Performance   continued

Pokrovskiy

Acquired by Pavel Maslovskiy, CEO in early exploration stage 

Petropavlovsk (formerly Peter Hambro Mining) was created in 1994  
to finance the project

Produced 2.01Moz ounces gold since 1999

Strategic location to the transformative POX Hub.

Introduction 
Pokrovskiy is the licence on which the Group was built. Today, as it nears the end of its mine life having 
produced 2.01Moz since 1999, the mine will transition into the POX Hub, currently under full scale production. 
The POX Hub is an integral part of the Group’s future plans and Pokrovskiy provides the ideal strategic location, 
not only due to its excellent onsite and regional infrastructure, but also its close proximity to Pioneer’s limestone 
deposit, limestone being a key ingredient for the pressure oxidation process.

Operating Mine

Underground

Lime deposit

POX

Analytical Labs

Hydro Plant

Railway

Federal highway

Core assets

Blagoveschensk

Malomir

Pokrovskiy POX Hub

Pioneer

2016 gold production 
37.6 – 9% of total Group gold  
production for the year.

Key facts 

2016 Progress

2017 Targets

–  Located in the south of the Amur region, 450km from 

–  Maintained total cash costs

–  Infrastructure adapted and 

Production as a % of total group

transitioned where appropriate 
for the POX Hub

–  Workforce utilised and 

transitioned to the POX Hub.

–  Reduction in sustaining capex  
as the mine prepares to be 
harvested from 2019

–  In line with our development 

strategy to transition Pokrovskiy 
mine into the POX Hub, there was 
no material exploration in 2016

–  Completed and implemented 

resin cleansing facility.

Blagoveshchensk, the China border trade city and regional 
business hub. 

  –  Situated between the BAM and Trans-Siberian Railway, 
with the nearest station approximately 40km away 

  –  88km from the largest regional hydropower station (5GW) 

–  Hard rock non-refractory and refractory deposit 

–  Reserves and Resources 1.39Moz 

   – 7% total Group Mineral Resource 

–  Open pit mining 

–  1.8Mtpa RIP plant and seasonal heap leach facility on site

–  Annual LTIFR of 0.5 per million man hours worked.

42  Petropavlovsk Annual Report 2016    

 
Geology 
Pokrovskiy is located on the south side  
of the Mongolo-Okhotskiy regional belt, 
approximately 40km south of Pioneer,  
which in addition to gold hosts a significant 
limestone deposit. 

Mining and Processing
Pokrovskiy is a multiple open pit operation. 

The Pokrovskiy licence includes multiple 
defined orebodies. All are non-refractory and 
can be treated at the 1.8Mtpa RIP plant, 
which operates throughout the year. 

Low grade ore (<0.5g/t) is processed via an 
onsite heap leach operations. 

Operational Performance 
Pokrovskiy produced 37.6koz (2015: 56koz) 
representing 9% of the Group’s consolidated 
annual gold production. Ore was mined from 
Pokrovka 1, Pokrovka 2, satellite deposit 
Zheltunak and from stockpiles. 

Despite the unusual weather conditions 
causing some delays to the heap leach 
operations, successful scheduling 
adjustments meant target stacking and 
production were achieved as planned. 
The heap leach operation produced 4.1koz. 

The RIP plant processed 1.79Mtpa of  
ore, unchanged from 2015. Metallurgical 
recovery at the plant averaged 90.1%,  
a 7% improvement on 2015 despite a 38% 
decrease in head grades from 1.04 to 0.65g/t. 

The plant performed as expected, delivering 
on all technological performance indicators.

Total cash costs of US$878/oz were 
achieved, a 1% increase on 2015, with all-in 
sustaining costs of US$988/oz, an 8% 
increase on 2015.

Outlook
As Pokrovskiy is coming to the end of its 
reserves, RIP production is scheduled to  
stop at the end of 2017. The heap leach  
will remain operational throughout 2018 to 
process remaining stockpiles. The Group  
is actively developing the POX Hub, which  
is scheduled to commence producing 
refractory concentrate from Q4 2018. 
Pokrovskiy will continue its life as the POX 
Hub, Petropavlovsk’s strategic processing 
centre for refractory concentrates.

Pokrovskiy mining operations

Total material moved
Ore mined
Average grade
Gold content

Processing operations (Resin-in-pulp plant)

Total milled
Average grade
Gold content
Recovery rate
Gold recovered
Heap leach operations
Ore stacked
Average grade
Gold content
Recovery rate
Gold recovered
Total gold recovered

Units
m3 ’000
t ’000
g/t
oz. ’000

Year ended  
31 December 2016
4,709 
1,027 
0.79 
26.0

Year ended  
31 December 2015
5,169
933
1.41
42.2

Units
t ’000
g/t
oz. ’000
%
oz. ’000

t ’000
g/t
oz. ’000
%
oz. ’000
oz. ’000

Year ended  
31 December 2016
1,791 
0.65 
37.1 
90.1% 
33.5 

Year ended  
31 December 2015
1,791
1.04
59.7
84.3
50.4

440 
0.45 
6.3 
64.8% 
4.1 
37.6

541
0.53
9.2
60.6
5.6
56.0

Following the successful debt restructuring in 
2016, the Group resumed development of the 
Pressure Oxidation Facility (POX Hub) at 
Pokrovskiy. Utilising and adapting existing 
infrastructure (including the 1.8Mtpa RIP 

plant) has a beneficial impact on capital costs, 
with US$90million gross value for buildings 
and equipment being incorporated directly 
into the POX Hub facility.

Other projects

Tokur is a hard rock, non-refractory gold deposit located in the north eastern 
part of the Amur region, approximately halfway between the Malomir and 
Albyn mines. Being a former Soviet era mine based in an area of intensive, 
historical alluvial mining, Tokur benefits from developed infrastructure, 
including all weather roads and power supply. This led it to become a base 
for the Group’s expansion into the area. The project’s facilities, which include 
mechanical workshops, dormitories and a canteen, are in regular use both  
by the company workers passing through and by third parties for a fee. 
The chemical and fire analysis laboratory located at Tokur is fully employed  
by the Group’s exploration division.

Tokur is at an advanced stage of development and potentially suitable for 
reopening as an open pit mine. While the deposit is not currently in commercial 
production, it contains significant JORC Mineral Resources and Ore Reserves, 
suitable for processing in a RIP plant. At this stage, the asset’s development into  
a full scale mining operation has been put on hold to minimise the Group’s capital 
expenditure in the current gold price environment. 

In line with the Group’s plan to focus on existing producing assets in the short 
term, no significant capital expenditure was allocated to this project during 2016. 
Tokur has been fully impaired (in a previous year) and the Group intends to review 
its development plans in the medium term.

  Petropavlovsk Annual Report 2016  43

Strategic reportFinancial statementsGovernanceDevelopment Projects 

44  Petropavlovsk Annual Report 2016    

FUTURE 
DEVELOPMENT

OPERATIONS

Pioneer/
Pokrovskiy Mines

Malomir
Mine

Albyn
Mine

EXPLORATION

ENGINEERING

CONSTRUCTION

NPGF Regis LLC

PHM Engineering

Kapstroi

R&D/SCIENTIFIC INSTITUTES

Irgiredmet JSC

RDC Hydrometallurgy

HIGHLY QUALIFIED TEAM

PETROPAVLOVSK PLC (POG:LN)

Underground

In 2016, following successful feasibility 
studies, it was concluded that underground 
operations at Pioneer and Malomir would be 
economically viable and provide access to 
considerably higher grade, non-refractory  
ore with which to further support sustainable 
long term production. The successful 
implementation of underground operations 
would support Petropavlovsk’s strategy by 
further simplifying cost structure and by 
maximising cash generation via improved 
access to the Group asset base. 

Pioneer – NE Bakhmut Underground 
Mine Development
2016 Progress
Appointed underground contractor for 
immediate mobilisation of personnel and 
equipment. The construction of access and 
ventilation decline portals was completed in 
H2. Development of the declines has 
progressed well throughout the period. A total 
of 675m decline had been completed. 

Successful deep level surface drilling, 
targeting high grade down dip extensions 
confirmed the continuation of mineralisation 
at depth and resulted in a maiden Ore 
Reserve of 165koz. Total Mineral Resource of 
299koz, a 300% increase from 2015, 
including a 340% increase in Indicated 
Resource category. 

2017 Priorities 
The mine plan schedules for first stope mining 
from the moderate grade Bridge area in Q2 
2017. The higher grade areas are within the 
NE Bakhmut 2 and NE Bakhmut 3 zones.  
NE Bakhmut 3 is scheduled to be accessed  
in H2 2017.  

Development and preparation of 
underground drill platforms to commence 
underground exploration drill programme to 
delineate the extent and continuity of the high 
grade mineralisation that remains open in 
multiple directions. 

Malomir – Quartzitovoye Underground 
Mine Development
2016 Progress
In Q4, appointed underground contractor for 
mobilisation of personnel and equipment in 
Q1 2017. 

Successful deep level surface drilling, 
targeting high grade down dip extensions 
confirmed the continuation of mineralisation 
at depth and resulted in a defined maiden  
Ore Reserve of 207koz @ 5.85 g/t, 
underpinning a five year life of mine 
production plan. The total Mineral Resource  
is 283koz, including a 236% increase in the 
Indicated Resource category. 

2017 Priorities
Commencement of development. The mine 
plan schedules for first stope mining in 
H2 2017. 

  Petropavlovsk Annual Report 2016  45

Strategic reportFinancial statementsGovernancePOX Hub 

Petropavlovsk’s POX Hub will be the second  
of its kind in Russia. The successful 2016 refinancing 
enabled the Company to recommence 
development works, which will be self funded 
through free cash flow. With key contracts renewed 
and key equipment assessed, solid progress  
is now being made towards commissioning.

Why POX? Over 50% of Petropavlovsk’s 
existing Reserve base consists of refractory 
ore – ore that cannot easily be processed 
via traditional cyanide based methods. The 
POX Hub will unlock this value, equating to 
c.15 years of sustainable refractory 
production.

Further upside potential exists in several 
forms. Exploration work has identified 
multiple refractory targets at Pioneer and 
Malomir, as well as mineralisation at Albyn. 
The Hub was designed so that two 
additional autoclaves could be installed in 
the future, which would increase 
processing capacity by 30% to 650ktpa. 

This could prove especially lucrative if the 
Group were able to treat refractory ore from 
third parties, given the large amount of 
undeveloped refractory mineralisation in the 
region. Petropavlovsk could also use the 
Hub to assess ore from deposits available 
for acquisition, perhaps most meaningfully 
those abandoned during the Soviet era with 
rich reserve and resource potential due to a 
lack of technology. Finally, there is the 
possibility of selling concentrate to generate 
revenue in the near term ahead of the POX 
Hub being commissioned.

Construction at Malomir (Stage 1) is 90% 
complete, and at the POX Hub is 65% complete.

46  Petropavlovsk Annual Report 2016    

Project Economics

In 2016, as part of the bank debt refinancing, the Company updated the 2010 feasibility project economics ahead of the development reboot.

–  Total outstanding POX hub pre production estimated capex – c.US$120million, inc. contingency.  

This includes total outstanding estimated capex for Malomir flotation plant – US$32million (at 31.12.16)

– Updated operating cost estimates – US$615-675/oz for Malomir/ US$785-865/oz for Pioneer.

The updated project economics account for updated operating and capital costs: 

Base case

Project NPV 
(10%)
603

Project IRR 
(%)
65

Project  
payback 
(years)
3.25

Revenue  
2018 - 2032 
(US$m)
3,965

Average production 
2018 - 2032
(koz pa)
220

(Assuming LT avg gold price US$1,200/oz, FX USD:RUR 60). The project economics are unaudited.

Refinancing 
The refinancing of the Group’s bank debt 
totalling c.US$430 million (December 2016) 
required 100% self funding of the POX Hub 
from internal cash flow generated by the 
Group’s current non refractory operations. 
This was modelled based on an average 
US$1250/oz gold price throughout the 
construction and ramp up phase. 

The Sberbank US$100million commodity 
linked loan facility remains on schedule for 
completion of final documentation effective 
Q2 2017. As at 26 April 2017, the Company 
has hedged 547koz of gold at US$1,253/oz 
over 2017-2019.

Malomir Project Parameters(1)

Malomir Flotation Plant
Ore Processed
Flotation Recovery
Sulphur Content
Concentrate Yield
Concentrate Grade

POX Hub
Concentrate Processed
Gold Recovery
Total POX Hub Recovery
Total Operating Costs (inc. Flotation)

kt
%
%
mass %
g/t

kt
%
%
US$/oz

Malomir
5,400
86%
25%
5.50%
24

300-330
93%
79%
615-675

Project economics includes production concentrate from Pioneer, which is scheduled to commence from 2023.

Key Construction Milestones

2017

2018

 – POX Hub: the oxygen plant, supporting POX Hub infrastructure and all piping, welding and assembly works are scheduled for completion
 – Malomir flotation: Stage 1 (3.6Mtpa) is scheduled for completion and commissioning.

 – Malomir: concentrate production and stockpiling will be ongoing throughout 2018 ensuring a smooth ramp up
 – POX Hub: the completion of the autoclave plant, RIP refurbishment and Hub integration are to be completed by Q3 2018 

– Scheduled to commence a staged dry and wet commissioning, one autoclave at a time.

The ramp up to commercial production is due to occur throughout 2019.

Upside Potential

Marketing Optionality

Given the scale of the POX Hub and the 
large amount of undeveloped refractory 
gold mineralisation in the Russian Far East, 
the hub opens a new dimension for the 
Group’s future growth beyond its own 
existing reserves and potential reserves.

Exploration 
At Malomir, exploration work has identified 
several highly prospective satellite refractory 
targets for further exploration work, 
including Ozhidaemoe. At Pioneer, 
refractory targets have been identified 
south of the main Pioneer orebody zone. 
Initial exploration drill results included: 
68.4m@0.65g/t, 48.1m@0.74g/t and 
30.9m@0.79g/t. The Alexandra zone and 
Sosonovaya licence are also expected to 
provide further refractory resource upside. 
There is also known refractory 
mineralisation with the Albyn licence 
holding. The Company continues to 
explore the potential for further mine life 
extension and production expansion.

Capacity 
The autoclave plant was designed and 
constructed to allow for an additional two 
autoclaves to be installed, increasing 
processing capacity by 30% to 650ktpa.

Selling Concentrate
Market analysis is being carried out to explore 
the possible economic benefit of selling 
concentrate to generate near term revenue 
stream ahead of the POX Hub commissioning.

Third Party Tolling
The POX Hub could treat third party refractory 
ore under a tolling arrangement. As part of 
running optimisation scenarios on our 
production plan, upside opportunities exist for 
increasing the concentrate grade of the feed to 
the POX Hub organically within our own assets 
or in cooperation with third party high grade ore.

Regional Licence Acquisition
The POX Hub also creates opportunities to treat 
ores from deposits available for acquisition in the 
Amur region, especially those with significant 
reserves and resources but abandoned during 
the Soviet Era due to a lack of technology.

  Petropavlovsk Annual Report 2016  47

Strategic reportFinancial statementsGovernanceReserves and Resources 

Since 2008 and in accordance with best 
industry practices, the Group has been 
reporting its Mineral Resources and Ore 
Reserves in accordance with JORC Code. 
Following the strategic disposal of the non 
core projects Visokoye, Yamal and 
Nimanskaya in 2016, all the Group’s 
remaining mining assets are located in  
the Amur Region.

Total Mineral Resource ounces (including 
Reserves) as of 31 December 2016 amounted 
to 20.16Moz, compared to 23.29Moz in 2015, 
with a total Ore Reserve of 7.95Moz 
compared to 8.41Moz the previous year. 
The decrease was mainly driven by the 
disposals of capital intensive non-core assets 
and to a lesser extent by mine depletion. 

A total of 1.22Moz of Ore Reserves were 
disposed of with Visokoye, whilst 3.55Moz of 

Mineral Resources (including Ore Reserves) 
were disposed of with the Visokoye and 
Yamal projects. Full Mineral Resource and 
Ore Reserve statements for Visokoye and 
Yamal can be found in the Petropavlovsk 
Annual Report and Accounts 2015. 

During 2016, the Group made exceptionally 
good progress developing Ore Reserves at 
Elginskoye, one of the significant satellite 
orebodies within the Albyn project area. 
Successful exploration and a feasibility study 
resulted in an increase in JORC Ore Reserves 
at Elginskoye from 0.28 to 1.24Moz (a 340% 
increase), providing a solid foundation for 
Albyn’s long term production. We also 
achieved a remarkable 76% increase in 
Mineral Resources for underground mining 
from 0.42 to 0.74Moz, and received our first 
maiden underground Ore Reserve estimate 
amounted to 0.37Moz.

This includes a new Pioneer NE Bakhmut 
underground Ore Rreserve of 0.17Moz @ 
4.46g/t, and 0.21Moz @ 5.85g/t at Malomir 
Quartzitovoe 1. The new Ore Reserve will 
support 6 year life of mine (LOM) for both 
mines with strong potential for resource, 
reserve and consequent LOM expansion. 

Overall, we successfully converted c.1.55Moz 
of Mineral Resources into Ore Reserves 
during 2016. 

Pioneer, Albyn, Malomir and Pokrovskiy 
Mineral Resource and Ore Reserve 
statements were prepared by Wardell 
Armstrong International in April 2017 in 
accordance with JORC Code (2012). 
A summary of their technical audit can  
be found on the company web site.

The tables below provide a summary and an asset by asset breakdown of Mineral Resources and Ore Reserves. 

Total Ore Reserves for open pit and underground extraction (as at 31 December 2016) 
(in accordance with JORC Code)

Total 

Non-Refractory

Refractory

Category
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable

Tonnage (kt)
32,032
229,667
261,699
22,177
95,632
117,809
9,854
134,036
143,890

Grade (g/t Au)
0.82
0.96
0.95
0.69
1.10
1.03
1.11
0.86
0.88

Gold (Moz Au)
0.84
7.11
7.95
0.49
3.39
3.88
0.35
3.72
4.07

Note: Figures may not add up due to rounding.

Total Ore Reserves for open pit extraction (as at 31 December 2016) 
(in accordance with JORC Code)

Total 

Non-Refractory

Refractory

Note: Figures may not add up due to rounding.

48  Petropavlovsk Annual Report 2016    

Category

Tonnage (kt)

Grade (g/t Au)

Gold (Moz Au)

Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable

32,032
227,415
259,446
22,177
93,379
115,557
9,854
134,036
143,890

0.82
0.92
0.91
0.69
1.01
0.95
1.11
0.86
0.88

0.84
6.74
7.58
0.49
3.02
3.51
0.35
3.72
4.07

Total Ore Reserves for underground extraction (as at 31 December 2016)
(WAI April 2017, in accordance with JORC Code 2012)

Total

Non-Refractory

Refractory

Note: Figures may not add up due to rounding.

Category
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable

Tonnage (kt)
–
2,253
2,253
–
2,253
2,253
–
–
–

Total Mineral Resource for potential open pit and underground extraction (as at 31 December 2016)
(in accordance with JORC Code)

Total

Non-Refractory

Refractory

Category
Measured
Indicated 
Sub total (M+I)
Inferred
Measured
Indicated 
Sub total (M+I)
Inferred
Measured
Indicated 
Sub total (M+I)
Inferred

Note: Mineral Resources are reported inclusive of Ore Reserves. Figures may not add up due to rounding.

Total Mineral Resource for potential open pit extraction (as at 31 December 2016) 
(in accordance with JORC Code)

Total

Non-Refractory

Refractory

Note: Mineral Resources are reported inclusive of Ore Reserves. Figures may not add up due to rounding.

Category
Measured
Indicated 
Sub total (M+I)
Inferred
Measured
Indicated 
Sub total (M+I)
Inferred
Measured
Indicated 
Sub total (M+I)
Inferred

Tonnage (kt)
51,859
418,167
470,026
257,409
33,654
207,117
240,771
115,328
18,205
211,050
229,255
142,081

Tonnage (kt)
51,859
415,393
467,252
256,155
33,654
204,343
237,997
114,074
18,205
211,050
229,255
142,081

Grade (g/t Au)
–
5.14
5.14
–
5.14
5.14
–
–
–

Grade (g/t Au)
0.94
0.89
0.90
0.80
0.91
0.96
0.95
0.96
0.99
0.82
0.84
0.67

Grade (g/t Au)
0.94
0.85
0.86
0.79
0.91
0.88
0.88
0.93
0.99
0.82
0.84
0.67

Gold (Moz Au)
–
0.37
0.37
–
0.37
0.37
–
–
–

Gold (Moz Au)
1.57
11.96
13.53
6.63
0.99
6.36
7.35
3.55
0.58
5.60
6.18
3.08

Gold (Moz Au)
1.57
11.37
12.94
6.48
0.99
5.78
6.76
3.40
0.58
5.60
6.18
3.08

  Petropavlovsk Annual Report 2016  49

Strategic reportFinancial statementsGovernanceReserves and Resources   continued

Total Mineral Resource for potential underground extraction (WAI April 2017, as at 31 December 2016) 
(in accordance with JORC Code 2012)

Total

Non-Refractory

Refractory

Category
Measured
Indicated 
Sub total (M+I)
Inferred
Measured
Indicated 
Sub total (M+I)
Inferred
Measured
Indicated 
Sub total (M+I)
Inferred

Note: Mineral Resources are reported inclusive of Ore Reserves. Figures may not add up due to rounding.

Summary of Ore Reserves by asset (as at 31 December 2016) 

Pioneer
(WAI, April 2017, in accordance with JORC Code 2012)

Total

Non-Refractory Open Pit

Non-Refractory Underground

Subtotal Non-Refractory Open Pit and Underground

Refractory Open Pit

Subtotal Non-Refractory and Refractory Open Pit 

Category
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable

Tonnage (kt)
–
2,774
2,774
1,254
–
2,774
2,774
1,254
–
–
–
–

Tonnage (kt)
15,585
86,876
102,460
14,122
30,243
44,366
–
1,154
1,154
14,122
31,398
45,520
1,462
55,478
56,940
15,585
85,721
101,306

Grade (g/t Au)
–
6.56
6.56
3.92
–
6.56
6.56
3.92
–
–
–
–

Grade (g/t Au)
0.68
0.82
0.80
0.65
0.73
0.70
–
4.46
4.46
0.65
0.86
0.80
0.87
0.80
0.80
0.68
0.77
0.76

Gold (Moz Au)
–
0.59
0.59
0.16
–
0.59
0.59
0.16
–
–
–
–

Gold (Moz Au)
0.34
2.29
2.63
0.30
0.71
1.00
–
0.17
0.17
0.30
0.87
1.17
0.04
1.42
1.46
0.34
2.13
2.46

50  Petropavlovsk Annual Report 2016    

Albyn
(WAI, April 2017, in accordance with JORC Code 2012)

Total Mineral Resources

Non-Refractory Open Pit

Refractory Open Pit

Note: All Albyn Ore Reserve is for open pit extraction.

Summary of Ore Reserves by asset (as at 31 December 2016) 

Malomir
(WAI, April 2017, in accordance with JORC Code 2012)

Total

Non-Refractory Open Pit

Non-Refractory Underground

Subtotal Non-Refractory Open Pit and Underground

Refractory Open Pit

Subtotal Non-Refractory and Refractory Open Pit 

Category
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable

Category
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable

Tonnage (kt)
4,952
52,302
57,254
4,952
52,302
57,254
–
–
–

Tonnage (kt)
8,416
86,755
95,171
24
7,100
7,124
–
1,098
1,098
24
8,198
8,222
8,392
78,557
86,949
8,416
85,657
94,073

Grade (g/t Au)
0.51
1.18
1.12
0.51
1.18
1.12
–
–
–

Grade (g/t Au)
1.15
0.97
0.98
1.16
0.83
0.83
–
5.85
5.85
1.16
1.50
1.50
1.15
0.91
0.93
1.15
0.90
0.93

Gold (Moz Au)
0.08
1.98
2.06
0.08
1.98
2.06
–
–
–

Gold (Moz Au)
0.31
2.70
3.01
0.001
0.19
0.19
–
0.21
0.21
0.001
0.40
0.40
0.31
2.30
2.61
0.31
2.49
2.80

  Petropavlovsk Annual Report 2016  51

Strategic reportFinancial statementsGovernanceReserves and Resources   continued

Pokrovskiy & Burinda 
(WAI, April 2017, in accordance with JORC Code 2012)

Total 

Non-Refractory Open Pit

Refractory Open Pit

Note: All Pokrovskiy&Burinda Ore Reserve is for open pit extraction.

Tokur
(WAI, 2010, in accordance with JORC Code 2004)

Total 

Non-Refractory Open Pit

Refractory Open Pit

Note: All Tokur Ore Reserve is for open pit extraction 

Notes on Ore Reserve statement: 

Category
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable

Category
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable
Proven
Probable
Proven+Probable

Tonnage (kt)
1,051
1,540
2,590
1,051
1,540
2,590
–
–
–

Tonnage (kt)
2,028
2,195
4,223
2,028
2,195
4,223
–
–
–

Grade (g/t Au)
0.55
0.74
0.66
0.55
0.74
0.66
–
–
–

Grade (g/t Au)
1.47
1.44
1.45
1.47
1.44
1.45
–
–
–

Gold (Moz Au)
0.02
0.04
0.06
0.02
0.04
0.06
–
–
–

Gold (Moz Au)
0.10
0.10
0.20
0.10
0.10
0.20
–
–
–

(1) Group Ore Reserves statements are prepared by WAI; Pokrovskiy, Pioneer, Malomir and Albyn Reserves are prepared in April 2017 in accordance with JORC Code 2012; Tokur Reserves are prepared in 2010 

in accordance with JORC Code 2004 

(2) Pioneer, Malomir Albyn and Pokrovskiy Ore Reserves for open pit extraction are estimated within economical pit shells using a $1,200/oz gold price assumption and applying other modifying factors based on 
projected performance of these operating mines.Tokur Reserves have been based on a $1,000/oz gold price assumption, together with the operating costs assumptions relevant at the time of the estimate. 

(3) Open Pit Reserve cut off grade for reporting varies from 0.3 to 0.5g/t Au, depending on the asset and processing method.

(4) Underground Ore Reserve estimates use mine design with decline access and trackless mining equipment; variants of open stoping with predominantly uncemented back fill are used; Ore Reserve figures 

have been adjusted for anticipated dilution and mine recovery.

(5) Underground Reserve cut off grade for reporting is 1.5g/t Au for Pioneer and 1.7g/t Au for Malomir.

(6) Figures may not add up due to rounding. 

52  Petropavlovsk Annual Report 2016    

Summary of Mineral Resources by asset (as at 31 December 2016) 

Pioneer
(WAI, April 2017, in accordance with JORC Code 2012)

Total

Non-Refractory Open Pit

Non-Refractory Underground

Sub total Non-Refractory (Open Pit and 
Underground)

Refractory Open Pit

Sub total Open Pit (Refractory and Non-Refractory)

Albyn
(WAI, April 2017, in accordance with JORC Code 2012)

Total

Non-Refractory 

Refractory 

Note: All Albyn Mineral Resources is for open pit extraction

Category
Measured
Indicated 
Measured+Indicated
Inferred
Measured
Indicated 
Measured+Indicated
Inferred
Measured
Indicated 
Measured+Indicated
Inferred
Measured
Indicated 
Measured+Indicated
Inferred
Measured
Indicated 
Measured+Indicated
Inferred
Measured
Indicated 
Measured+Indicated
Inferred

Category
Measured
Indicated 
Sub total (M+I)
Inferred
Measured
Indicated 
Sub total (M+I)
Inferred
Measured
Indicated 
Sub total (M+I)
Inferred

Tonnage (kt)
19,520
160,670
180,190
57,058
9,842
64,520
74,362
21,883
–
1,924
1,924
765
9,842
66,444
76,286
22,648
9,678
94,226
103,904
34,410
19,520
158,746
178,266
56,293

Tonnage (kt)
5,049
74,025
79,074
60,442
5,049
74,025
79,074
60,442
–
–
–
–

Grade (g/t Au)
0.68
0.75
0.74
0.66
0.58
0.63
0.62
0.66
–
5.82
5.82
4.05
0.58
0.78
0.75
0.77
0.79
0.74
0.74
0.58
0.68
0.69
0.69
0.61

Non-Refractory

Grade (g/t Au)
0.52
1.13
1.09
1.02
0.52
1.13
1.09
1.02
–
–
–
–

Gold (Moz Au)
0.43
3.89
4.32
1.20
0.18
1.30
1.48
0.46
–
0.36
0.36
0.10
0.18
1.66
1.84
0.56
0.25
2.23
2.48
0.64
0.43
3.53
3.95
1.10

Gold (Moz Au)
0.09
2.69
2.78
1.99
0.09
2.69
2.78
1.99
–
–
–
–

  Petropavlovsk Annual Report 2016  53

Strategic reportFinancial statementsGovernanceReserves and Resources   continued

Malomir
(WAI, April 2017, in accordance with JORC Code 2012)

Total

Non-Refractory Open Pit

Non-Refractory Underground

Sub total Non-Refractory (Open Pit and 
Underground)

Refractory Open Pit

Sub total Open Pit (Refractory and Non-Refractory)

Note: All Albyn Mineral Resources is for open pit extraction

Pokrovka & Burinda
(WAI, April 2017, in accordance with JORC Code 2012)

Total

Non-Refractory 

Refractory 

Note: All Albyn Mineral Resources is for open pit extraction

54  Petropavlovsk Annual Report 2016    

Category
Measured
Indicated 
Measured+Indicated
Inferred
Measured
Indicated 
Measured+Indicated
Inferred
Measured
Indicated 
Measured+Indicated
Inferred
Measured
Indicated 
Measured+Indicated
Inferred
Measured
Indicated 
Measured+Indicated
Inferred
Measured
Indicated 
Measured+Indicated
Inferred

Category
Measured
Indicated 
Measured+Indicated
Inferred
Measured
Indicated 
Measured+Indicated
Inferred
Measured
Indicated 
Measured+Indicated
Inferred

Tonnage (kt)
8,558
135,865
144,423
118,944
31
18,191
18,222
10,784
–
850
850
489
31
19,041
19,072
11,273
8,527
116,824
125,351
107,671
8,558
135,015
143,573
118,455

Tonnage (kt)
6,780
31,511
38,291
10,259
6,780
31,511
38,291
10,259
–
–
–
–

Non-Refractory

Grade (g/t Au)
1.21
0.91
0.93
0.71
1.19
0.68
0.68
0.68
–
8.23
8.23
3.72
1.20
1.02
1.02
0.81
1.21
0.90
0.92
0.70
1.21
0.87
0.89
0.70

Non-Refractory

Grade (g/t Au)
1.01
0.83
0.86
0.99
1.01
0.83
0.86
0.99
–
–
–
–

Gold (Moz Au)
0.33
3.99
4.33
2.73
0.001
0.40
0.40
0.24
–
0.23
0.23
0.06
0.001
0.62
0.63
0.29
0.33
3.37
3.70
2.44
0.33
3.77
4.10
2.68

Gold (Moz Au)
0.22
0.84
1.06
0.33
0.22
0.84
1.06
0.33
–
–
–
–

Tokur
WAI, 2010, in accordance with JORC Code 2004)

Total

Non-Refractory 

Refractory 

Note: All Tokur Mineral Resources is for open pit extraction

Notes to Mineral Resource Statement: 

(1) Mineral Resources include Ore Reserves.

Category
Measured
Indicated 
Measured+Indicated
Inferred
Measured
Indicated 
Measured+Indicated
Inferred
Measured
Indicated 
Measured+Indicated
Inferred

Tonnage (kt)
11,952
16,096
28,048
10,706
11,952
16,096
28,048
10,706
–
–
–
–

Non-Refractory

Grade (g/t Au)
1.30
1.06
1.16
1.09
1.30
1.06
1.16
1.09
–
–
–
–

Gold (Moz Au)
0.50
0.55
1.05
0.38
0.50
0.55
1.05
0.38
–
–
–
–

(2) Mineral Resources for Pokrovskiy, Pioneer, Malomir and Albyn are audited by WAI in accordance with JORC Code 2012 in April 2015 with a further review of changes in April 2016 and April 2017; Mineral 

Resources for Tokur reviewed by WAI in 2010 in accordance with JORC Code 2004.

(3) Open Pit Mineral Resources for Pokrovskiy, Pioneer, Malomir and Albyn are constrained by conceptual open pit shells at a US$1,500/oz long term gold price.; Tokur Mineral Resources have no open pit 

constraints.

(4) The cut off grade for the Mineral Resource for open pit mining varies from 0.30 to 0.4g/t depending on the type of mineralisation and proposed processing method.

(5) Minimum mining widths dependant on reconciliation have been applied to the open pit Mineral Resource.

(6) Mineral Resources for potential underground extraction were audited by WAI in accordance with JORC Code 2012 in April 2017.

(7) Cut off grade is 1.5g/t is used to report Mineral Resource for potential underground mining.

(8) Mineral Resources are not Reserves until they have demonstrated economic viability based on a feasibility or pre-feasibility study.

(9) Grade represents estimated contained metal in the ground and has not been adjusted for metallurgical recovery.

  Petropavlovsk Annual Report 2016  55

Strategic reportFinancial statementsGovernanceIRC 

IRC produces and develops industrial 
commodities. Based in the Russian Far East, 
it benefits from low production costs and 
proximity to the Chinese border, China being 
the world’s largest consumer of IRC’s main 
product, iron ore. IRC was Petropavlovsk’s 
Non Precious Metals Division before it was 
listed on the Hong Kong Stock Exchange in 
late 2010 (stock code 1029). 

The Group currently holds a 31.1% stake 
in IRC. 

IRC assets 
IRC’s key mining assets are K&S, Kuranakh 
and Garinskoye: 

 – K&S. An ongoing project at an advanced 
stage of development, which started trial 
production in 2016. The project has two 
phases and is located in the Jewish 
Autonomous Region (EAO) of the Russian 
Far East 

 – Kuranakh. An iron ore/ilmenite concentrate 
mine located in the Amur region, Russian 
Far East 

 – Garinskoye. This project is at an advanced 
stage of exploration with Probable Ore 
Reserves as well as Indicated and Inferred 
Mineral Resources. Like Kuranakh, it is 
located in the Amur region. 

IRC’s non core mining assets – those that are 
not expected to contribute substantially to 
revenue in the short to medium term, are 
Bolshoi Seym, the Garinskoye flanks and 
Kostenginskoye. 

 – Bolshoi Seym. An ilmenite deposit with 

Indicated and Inferred Mineral Resources, 
located North of Kuranakh 

 – The Garinskoye flanks. An area surrounding 
Garinskoye at an early stage of exploration 

 – Kostenginskoye. An area 18km south 
of K&S at an early stage of exploration. 

The Garinskoye Flanks and Kostenginskoye 
are yet to have JORC compliant Mineral 
Resources and Ore Reserves. 

56  Petropavlovsk Annual Report 2016    

Investment in IRC 
In January 2013, IRC entered into conditional 
agreements for a US$238 million subscription 
for new IRC Shares by General Nice 
Development Limited (‘General Nice’), a 
member of a group of companies which 
collectively is one of the largest Chinese iron 
ore importers, and Minmetals Cheerglory, a 
wholly owned subsidiary of China Minmetals 
Corporation. Liquidity constraints have 
resulted in General Nice, to date, completing 
c.80% of its planned investment. Investment 
from Minmetals Cheerglory can only occur 
once the subscription by General Nice has 
been completed. 

Although full completion of the investment 
from General Nice and Minmetals has been 
delayed, General Nice has agreed to 
commence paying interest on the outstanding 
investment amount of US$38 million from 
December 2014 onwards, although no 
interest payments have been made by 
General Nice to IRC as at 31 December 2016. 

IRC continues to be in discussions with 
General Nice, Mr Cai Sui Xin (Chairman of 
General Nice) and Minmetals Cheerglory 
about completion of General Nice’s 
subscription obligations and the settlement of 
the interest due to date and other potential 
alternative options. 

In addition, near the end of 2016, IRC 
completed the issuance of new shares to a 
new core investor, with an additional new 
member joining the Board. Tiger Capital Fund 
injected c. US$25 million into IRC for newly 
issued IRC shares, giving them a 13.22% 
shareholding, and Mr Cheng Chi Kin 
(representing Tiger Capital Fund) joined the 
Board of IRC as Non Executive Director, 
providing further diversity, expertise and 
experience to the Board.

As a result of the above, Petropavlovsk’s 
stake in IRC reduced from 35.83% to 31.10%. 
The Group remains a major shareholder. IRC 
remains an associate of Petropavlovsk and 
not a subsidiary.

Further information on the presentation of IRC may be 
found in note 27 of the Financial Statements. 

Further information may be obtained from the website 
of IRC, www.ircgroup.com.hk.

In addition to these assets, IRC also operates: 

 – Giproruda. 70% owned by IRC, based in St 

Petersburg, a technical mining and 
research consultancy 

 – SRP. A steel slag reprocessing plant located 

in North East China. It is a joint venture 
between IRC, which owns 46%, and one of 
its largest iron ore customers. 

Operational performance in 2016

K&S 
During the year, Phase One K&S commenced 
final hot commissioning and in H2 entered a 
trial production phase. Phase One K&S is 
expected to be able to produce 3.2 million 
tonnes of iron ore concentrate with a 65% iron 
(Fe) content, once completed and at full 
capacity. At the end of 2016, it had produced 
over 160,000 tonnes of iron ore concentrate.

IRC also reached an amicable settlement with 
CNEEC, of which IRC received cash 
compensation of US$4.5 million, as well as a 
smaller outstanding construction payment 
liability (US$3.9 million less). IRC reserves the 
right to claim for further penalties from the 
contractor.

Regarding the K&S loan, ICBC has agreed to 
restructure the remaining repayments under 
the Project Finance Facility. Accordingly, the 
two repayment instalments originally due in 
2017, which amounted to a total of c. US$43 
million, shall be repayable in the five 
subsequent repayment instalments. For 
details, please refer to IRC’s announcements 
dated 27 February and 21 March 2017. 

Kuranakh 
Kuranakh was moved to care and 
maintenance in the beginning of 2016 in 
response to a difficult operating environment. 
IRC considered the process to be satisfactory 
throughout 2016 with only minimal costs 
necessary to maintain security and 
equipment.

During the year, the annual sales volume  
was 219,352 tonnes for the remaining iron  
ore concentrate, and the sales volume of 
ilmenite concentrate was 60,044 tonnes. 
The segmental revenue of the mine was 
US$15.6 million. 

Garinskoye 
Garinskoye remains an attractive, low cost, 
large scale, DSO style greenfield project. IRC 
did not develop it in 2016 due to capital 
constraints, but continues to monitor market 
conditions for future opportunities. 

  Petropavlovsk Annual Report 2016  57

Strategic reportFinancial statementsGovernanceChief Financial Officer’s Statement 

For the year ended 31 December 2016

Andrey Maruta

Financial Highlights

Continuing operations

Total attributable gold production (’000oz) 

Gold sold (’000oz)

Group revenue 

Average realised gold price (US$/oz)

Average LBMA gold price afternoon fixing (US$/oz)

Total average cash costs (US$/oz) (a)

All-in sustaining costs (b)

Underlying EBITDA (c) 

Profit/(loss) for the period 

From continuing operations

From discontinued operations

Basic profit/(loss) per share 

From continuing operations

From discontinued operations 

Net cash from operating activities

From continuing operations

From discontinued operations 

(a)  Calculation of total cash costs (“TCC”) is set out in the section Hard rock mines below. 

(b) All-in sustaining costs (“AISC”) and all-in costs (“AIC”) are calculated in accordance with guidelines for reporting all-in sustaining costs and all-in costs  

published by the World Gold Council. Calculation is set out in the section All-in sustaining costs and all-in costs below. 

(c)  Reconciliation of profit/(loss) for the period and underlying EBITDA is set out in note 34 to the consolidated financial statements.

 Cash and cash equivalents 

 Loans

 Convertible bonds (e)
 Net Debt

(d) Including US$15.1 million received under investment agreement with the Russian Ministry of Far East Development.

(e)  US$100.0 million convertible bonds due on 18 March 2020 at amortised cost.

Note: Figures may not add up due to rounding.

Revenue

Revenue from hard rock mines
Revenue from other operations

58  Petropavlovsk Annual Report 2016    

2016
US$ million

2015
US$ million

416.3

399.9

540.7

1,222

1,250

660

807

200.1

31.7

31.7

–

US$0.01

US$0.01

–

37.0

37.0

–

504.1

481.9

599.9

1,178

1,160

749

874

172.8

(297.5)

(190.5)

(107.0)

(US$0.09)

(US$0.07)

(US$0.02)

103.4

111.0

(7.6)

31 December 2016
US$ million

31 December 2015
US$ million

12.6

(522.8)

(88.4)
(598.6)

28.2 (d)

(552.8)

(85.5)
(610.0)

2016  
US$ million
490.0
50.7
540.7

2015  
US$ million
568.7
31.2
599.9

2016 
oz
399,858
16,442
416,300

2015 
oz
481,884
22,216
504,100

Physical volumes of gold production and sales

Gold sold from hard rock mines
Movement in gold in circuit and doré bars
Total attributable production

Group revenue during the period was 
US$540.7 million, 10% lower than the 
US$599.9 million achieved in 2015.

Revenue from hard rock mines was 
US$490.0 million, 14% lower than the 
US$568.7 million achieved in 2015. Gold 
remains the key commodity produced and 
sold by the Group, comprising 90% of total 
revenue generated in 2016. The physical 
volume of gold sold from hard rock mines 
decreased by 17% from 481,884 ounces in 
2015 to 399,858 ounces in 2016. The average 
realised gold price increased by 4% from 
US$1,178/oz in 2015 to US$1,222/oz in 2016. 
Average realised gold price includes  
US$(21)/oz effect from hedge arrangements 
(2015: US$20/oz).

Hard rock mines sold 98,231 ounces of silver 
in 2016 at an average price of US$16/oz, 
compared to 68,075 ounces in 2015 at an 
average price of US$15/oz. 

Revenue generated as a result of third party 
work by the Group’s in house service 
companies was US$50.7 million in 2016, a 
US$19.5 million increase compared to 
US$31.2 million in 2015. This revenue is 
substantially attributable to sales generated 
by Group’s engineering and research institute, 
Irgiredmet, primarily through engineering 
services and the procurement of materials, 
consumables and equipment for third parties, 
which comprised US$44.8 million in 2016 
compared to US$28.6 million in 2015.

Cash flow hedge arrangements
In order to increase certainty in respect of a 
significant proportion of its cash flows, the 
Group has entered into a number of gold 
forward contracts. 

Forward contracts to sell an aggregate of 
134,545 ounces of gold matured during the 
year and resulted in US$(8.5) million net cash 
settlement paid by the Group (2015: US$12.6 
million contribution to cash revenue from 
forward contracts to sell an aggregate of 
178,449 ounces of gold). 

The Group constantly monitors gold price and 
hedges some portion of production as 
considered necessary. Forward contracts to 
sell an aggregate of 50,006 ounces of gold at 
an average price of US$1,303 per ounce were 
outstanding as at 31 December 2016. 

In February - March 2017, the Group entered 
into forward contracts to sell an aggregate of 
549,994 ounces of gold during the years 2017 
- 2019 at an average price of US$1,252/oz, 
thus, satisfying bank debt refinancing 
conditions. Forward contracts to sell an 
aggregate of 546,968 ounces of gold at an 
average price of US$1,253 per ounce are 
outstanding as at 26 April 2017. 

  Petropavlovsk Annual Report 2016  59

Strategic reportFinancial statementsGovernanceChief Financial Officer’s Statement   continued

For the year ended 31 December 2016

Underlying EBITDA and analysis of operating costs 

Profit/(loss) for the period from continuing operations
Add/(less):
Interest expense
Investment income
Other finance gains
Other finance losses
Foreign exchange losses
Taxation
Depreciation
Impairment of exploration and evaluation assets
Impairment of ore stockpiles
Share of results of associates (a) 
Underlying EBITDA 

2016 
US$ million
31.7

2015  
US$ million
(190.5)

61.0
(0.6)
(11.9)
1.5
5.2
(4.7)
105.3
9.2
1.2
2.4
200.1

71.5
(1.0)
(9.1)
–
12.0
48.9
129.1
37.4
17.4
57.0
172.8

(a)  Group’s share of interest expense, investment income, other finance gains and losses, foreign exchange losses, taxation, depreciation and impairment recognised by an associate (IRC)

Underlying EBITDA as contributed by business segments is set out below.

Pioneer
Pokrovskiy
Malomir
Albyn
Total Hard rock mines
Corporate and other
Underlying EBITDA 

2016  
US$ million
79.2
13.2
22.0
110.4
224.7
(24.6)
200.1

2015  
US$ million
118.6
16.1
5.7
66.5
206.9
(34.1)
172.8

60  Petropavlovsk Annual Report 2016    

Hard rock mines 
This period, hard rock mines generated 
underlying EBITDA of US$224.7 million 
compared to US$206.9 million underlying 
EBITDA in 2015.

Total cash costs for hard rock mines 
decreased from US$749/oz in 2015 to 
US$660/oz in 2016, primarily reflecting the 
effect of cost optimisation measures 
undertaken by the Group in response to the 
lower gold price environment as well as the 
positive effect of Rouble depreciation. The 
increase in the average realised gold price 
from US$1,178/oz in 2015 to US$1,222/oz in 
2016 and the improved total cash costs had 
US$53.2 million positive contribution to 
underlying EBITDA in 2016. This effect was 

offset by the decrease in physical ounces sold 
which resulted in a US$35.2 million decrease 
in underlying EBITDA.

The key components of the operating cash 
expenses are wages, electricity, diesel, 
chemical reagents and consumables, as set 
out in the table below. The key cost drivers 
affecting the operating cash expenses are 
stripping ratios, production volumes of ore 
mined and processed, grades of ore 
processed, recovery rates, cost inflation and 
fluctuations in the Rouble to US Dollar 
exchange rate.

Compared with 2015 there was no significant 
inflation of Rouble denominated costs, in 
particular, electricity costs increased by up  

to 3% in Rouble terms (decreased by up to 
6% in US Dollar terms) while the cost of diesel 
remained at the same level (decreased by up 
to 9% in US Dollar terms). The impact of 
Rouble price inflation was mitigated by the 
10% average depreciation of the Rouble 
against the US Dollar, with the average 
exchange rate for the period increasing from 
61.30 Roubles per US Dollar in 2015 to 67.18 
Roubles per US Dollar in 2016. 

Refinery and transportation costs are variable 
costs dependent on the production volume. 
Mining tax is also a variable cost dependent 
on production volume and the gold price 
realised. The mining tax rate is 6%. Since the 
second half of 2016, the Group applies two 
year mining tax concession.

Staff cost 
Materials
Fuel
Electricity
Other external services
Other operating expenses 

Movement in ore stockpiles, work in progress and bullion in process attributable to 
gold production (a)
Total operating cash expenses

(a) Excluding deferred stripping

2016 

2015

US$ million
54.7
97.4
40.3
23.3
22.1
28.2
266.0

(40.5)
225.6

%
21
37
15
9
8
10
100

US$ million
61.8
129.9
55.3
25.0
27.4
29.8
329.2

(17.8)
311.4

%
19
39
17
8
8
9
100

  Petropavlovsk Annual Report 2016  61

Strategic reportFinancial statementsGovernanceChief Financial Officer’s Statement   continued

For the year ended 31 December 2016

Hard rock mines

Pioneer  
US$ million

Pokrovskiy  
US$ million

Malomir  
US$ million

Albyn  
US$ million

2016

Total  
US$ million

2015

Total  
US$ million

Revenue
Gold 
Silver

Expenses
Operating cash expenses 
Refinery and transportation
Other taxes
Mining tax
Deferred stripping costs 
Depreciation
Impairment of exploration and evaluation assets
Impairment /(reversal of impairment)  
of ore stockpiles
Operating expenses 
Result of precious metals operations 
Add/(less):
Depreciation
Impairment of exploration and evaluation assets
Impairment/(reversal of impairment)  
of ore stockpiles
Segment EBITDA 

163.5
1.0
164.5

77.9
0.2
1.9
5.2
–
38.8
–

6.1
130.2
34.3

38.8
–

6.1
79.2

46.7
0.3
47.0

31.9
0.1
0.5
1.3
–
6.6
–

1.0
41.4
5.6

6.6
–

1.0
13.2

67.1
0.1
67.2

41.6
0.1
1.6
1.9
–
13.6
–

(5.8)
53.0
14.2

13.6
–

(5.8)
22.0

211.2
0.2
211.4

74.2
0.3
2.2
6.3
18.0
45.7
9.2

(0.1)
155.7
55.6

45.7
9.2

(0.1)
110.4

488.5
1.5
490.0

225.6
0.7
6.3
14.7
18.0
104.7
9.2

1.2
380.3
109.7

104.7
9.2

1.2
224.7

567.6
1.0
568.7

311.4
1.1
7.7
33.1
8.4
127.2
2.5

17.4
508.9
59.8

127.2
2.5

17.4
206.9

Physical volume of gold sold, oz
Cash costs
Operating cash expenses 
Refinery and transportation
Other taxes
Mining tax
Deferred stripping costs 
Operating cash costs
Deduct: co-product revenue
Total cash costs 

Average TCC/oz, US$/oz

133,605

38,151

54,760

173,342

399,858

481,884

77.9
0.2
1.9
5.2
–
85.3
(1.0)
84.3

631

31.9
0.1
0.5
1.3
–
33.8
(0.3)
33.5

878

41.6
0.1
1.6
1.9
–
45.2
(0.1)
45.1

824

74.2
0.3
2.2
6.3
18.0
101.0
(0.2)
100.8

225.6
0.7
6.3
14.7
18.0
265.3
(1.5)
263.7

311.4
1.1
7.7
33.1
8.4
361.8
(1.0)
360.7

581

660

749

62  Petropavlovsk Annual Report 2016    

 
All-in sustaining costs and all-in costs
AISC decreased from US$874/oz in 2015 to US$807/oz in 2016, reflecting the reduction in TCC as well as lower sustaining capital expenditure 
related to the existing mining operations. 

AIC decreased from US$932/oz in 2015 to US$838/oz in 2016, reflecting the decrease in AISC explained above, reversal of impairment of 
refractory ore stockpiles due to a higher gold price and decrease in exploration expenditure. 

Hard rock mines

Pioneer  
US$ million

Pokrovskiy  
US$ million

Malomir  
US$ million

Albyn  
US$ million

2016

Total  
US$ million

2015

Total  
US$ million

Physical volume of gold sold, oz

133,605

38,151

54,760

173,342

399,858

481,884

Total cash costs 

Average TCC/oz, US$/oz

Impairment /(reversal of impairment)  
of ore stockpiles
Adjusted operating costs

Central administration expenses
Capitalised stripping at end of the period
Capitalised stripping at beginning of the period
Close down and site restoration
Sustaining capital expenditure
All-in sustaining costs

All-in sustaining costs, US$/oz 

Exploration expenditure
Capital expenditure 
(Reversal of impairment)/impairment  
of ore stockpiles (a)
All-in costs

All-in costs, US$/oz 

(a)  Refractory ore stockpiles to be processed at the POX Hub. 

84.3

631

6.3
90.6

10.9
–
–
0.1
3.9
105.5

789

8.5
1.0

(0.2)
114.8

859

33.5

878

1.0
34.5

3.1
–
–
–
0.1
37.7

988

0.1
–

–
37.8

990

45.1

824

(0.0)
45.1

4.5
3.6
–
–
1.7
55.0

1,004

1.9
0.8

(5.8)
51.9

948

100.8

263.7

360.7

581

660

749

(0.1)
100.6

14.1
22.6
(18.0)
0.1
5.2
124.7

719

6.2
–

–
130.8

755

7.2
270.9

32.6
26.2
(18.0)
0.2
10.9
322.8

807

16.6
1.9

(6.0)
335.3

838

9.2
369.9

30.4
18.0
(8.4)
(1.7)
12.7
420.9

874

18.9
1.0

8.2
449.0

932

  Petropavlovsk Annual Report 2016  63

Strategic reportFinancial statementsGovernanceChief Financial Officer’s Statement   continued

For the year ended 31 December 2016

Corporate and other
The Group has corporate offices in London, 
Moscow and Blagoveschensk which together 
represent the central administration function. 
Central administration expenses increased by 
US$2.2 million from US$30.4 million in 2015 
to US$32.6 million in 2016. 

During 2016, other operations contributed 
US$(24.6) million to underlying EBITDA vs. 
US$(34.1) million in 2015. Included in result  

of corporate and other operations in 2016 is  
a US$3.6 million share in losses generated  
by IRC.

31 December 2016 , with exception of  
an individual licence impairment referred  
to below.

Impairment review
The Group undertook an impairment  
review of the tangible assets attributable to  
its gold mining projects, exploration assets 
adjacent to the existing mines and supporting 
in house service companies and concluded 
no impairment was required as at 

The forecast future cash flows are based on 
the Group’s current mining plan that assumes 
POX Hub completion in the year 2018. 
The other key assumptions which formed the 
basis of forecasting future cash flows and the 
value in use calculation are set out below:

Long term gold price
Discount rate (a)
RUB/US$ exchange rate

(a) Being the post-tax real weighted average cost of capital, equivalent to a nominal pre-tax discount rate of 10.1% (2015: 10.1%)

Year ended  
31 December 2016
US$1,200/oz
8%

Year ended  
31 December 2015
US$1,150/oz
8%
RUB60.0/US$ RUB65.0/US$

Following the decision to suspend exploration at Kharginskoye ore field, an immediate extension of the Albyn deposit, and to surrender the licence,  
a US$9.2 million impairment charges were recorded against associated exploration and evaluation costs previously capitalised within exploration 
and evaluation assets. 

As at 31 December 2016, all exploration and evaluation assets on the balance sheet related to the areas adjacent to the existing mines.

Impairment of ore stockpiles
The Group assessed the recoverability of the carrying value of ore stockpiles and recorded impairment charges/(reversals of impairment) as set 
out below: 

Year ended 31 December 2016

Year ended 31 December 2015

Pre-tax impairment 
charge/
(reversal of 
impairment)
US$ million
1.0
6.1
(5.8)
(0.1)
1.2

Post-tax 
impairment charge/
(reversal of 
impairment)
US$ million
0.8
4.9
(4.7)
(0.1)
0.9

Pre-tax impairment 
charge/
(reversal of 
impairment)
US$ million
(0.9)
11.9
6.1
0.3
17.4

Taxation
US$ million
(0.2)
(1.2)
1.2
–
(0.2)

Pokrovskiy 
Pioneer
Malomir 
Albyn

Interest income and expense 

Investment income 

The Group earned US$0.6 million interest income on its cash deposits with banks. 

Interest expense
Other

Post-tax impairment 
charge/
(reversal of 
impairment)
US$ million
(0.7)
9.6
4.9
0.2
13.9

Taxation
US$ million
0.2
(2.4)
(1.2)
(0.1)
(3.5)

2016  
US$ million
0.6

2015  
US$ million
1.0

2016  
US$ million
60.8
0.2
61.0

2015  
US$ million
71.3
0.2
71.5

Interest expense for the period was comprised of US$11.9 million effective interest on the Convertible Bonds and US$48.9 million interest on bank 
facilities (2015: US$13.6 million and US$57.7 million, respectively). There was no interest expense capitalised as part of mine development costs 
within property, plant and equipment.

64  Petropavlovsk Annual Report 2016    

Other finance gains and losses
Other finance gains for the period comprised US$11.9 million compared to US$9.1 million in 2015. Included in other finance gains is financial 
guarantee fee of US$4.5 million (2015: US$2.2 million) charged in connection with the ICBC facility and US$7.4 million (2015: US$6.4 million) fair 
value gain on revaluation of the embedded option for the bondholders to convert into the equity of the Company. The Group also recognised 
US$1.5 million loss on bank debt refinancing.

Taxation 

Tax (credit)/charge

2016  
US$ million
(4.7)

2015  
US$ million
48.9

The Group is subject to corporation tax under the the UK, Russia and Cyprus tax legislation. The average statutory tax rate for 2016 was 20% in 
the UK and 20% in Russia. 

The tax charge for the period arises primarily in relation to the Group’s gold mining operations and is represented by a current tax charge of 
US$29.8 million in 2016 (2015: US$31.8 million) and a deferred tax credit, which is a non-cash item, of US$34.5 million (2015: deferred tax charge 
of US$17.1 million). Included in the deferred tax credit in 2016 is a US$26.0 million foreign exchange effect which primarily arises because the tax 
base for a significant portion of the future taxable deductions in relation to the Group’s property, plant and equipment are denominated in Russian 
Rouble whilst the future depreciation charges associated with these assets will be based on their US Dollar carrying value.

During the period, the Group made corporation tax payments in aggregate of US$35.3 million in Russia (2015: corporation tax payments in 
aggregate of US$32.9 million in Russia). 

Profit/(loss) per share 

Profit/(loss) for the period from continuing operations attributable to equity holders of Petropavlovsk PLC
Weighted average number of Ordinary Shares
Basic profit/(loss) per ordinary share from continuing operations

2016

2015 
US$33.7 million (US$190.2 million)
3,302,148,536 2,657,332,030
(US$0.07)

US$0.01

Basic profit per share for 2016 was US$0.01 compared to US$0.07 basic loss per share for 2015. The key factor affecting the basic profit/(loss) per 
share was the increase of net profit for the period attributable to equity holders of Petropavlovsk PLC from the net loss of US$190.2 million for 2015 
to US$33.7 million net profit for 2016. 

The total number of Ordinary Shares in issue as at 31 December 2016 was 3,303,768,532 (31 December 2015: 3,300,561,697).

The Group has a number of potentially dilutive instruments which were anti-dilutive in the 2015 and 2016 and, accordingly, diluted profit/(loss) per 
share was not different from the basic profit/(loss) per share.

  Petropavlovsk Annual Report 2016  65

Strategic reportFinancial statementsGovernanceChief Financial Officer’s Statement   continued

For the year ended 31 December 2016

Financial position and cash flows

Cash and cash equivalents 
Loans
Convertible bonds (a)
Net Debt

(a)  US$100.0 million convertible bonds due on 18 March 2020 at amortised cost.

Net cash from operating activities:
  Continuing operations
  Discontinued operations

Net cash used in investing activities: 
  Continuing operations
  Discontinued operations

Net cash used in financing activities:
  Continuing operations
  Discontinued operations

(b) Including US$29.4 million cash CAPEX and US$19.2 million proceeds from disposal of subsidiaries

31 December 2016 
US$ million
12.6
(522.8)
(88.4)
(598.6)

31 December 2015 
US$ million
28.2
(552.8)
(85.5)
(610.0)

2016  
US$ million

2015  
US$ million

37.0
–
37.0

(8.7) (b)
–
(8.7) (b)

(46.8)
–
(46.8)

111.0
(7.6)
103.4

(23.2)
(43.0)
(66.2)

(110.6)
74.2
(36.4)

66  Petropavlovsk Annual Report 2016    

Key movements in cash and net debt from continuing operations

As at 1 January 2016
Net cash generated by operating activities before working capital changes
Increase in working capital
Income tax paid
Capital expenditure
Exploration expenditure
Amounts repaid under bank loans, net
Interest accrued
Interest paid 
Transaction costs paid in connection with bank loans
Bank debt refinancing
Proceeds from disposal of subsidiaries, net of cash disposed and net of liabilities settled
Funds advanced to the Group under investment agreement  
with the Russian Ministry of Far East Development
Funds transferred under investment agreement with the Russian Ministry of Far East Development
Foreign exchange
Other
As at 31 December 2016

(a)  Including US$15.1 million received under investment agreement with the Russian Ministry of Far East Development

Cash  
US$ million

28.2 (a)

Debt  
US$ million
(638.3)

Net Debt  
US$ million
(610.0)

189.3
(63.3)
(35.3)
(12.8)
(16.6)
(27.0)

(53.7)
(4.0)

19.2

30.8
(47.7)
2.8
2.7
12.6

27.0
(60.8)
53.7
5.5
1.5

0.2

(611.2)

(598.6)

The increase in working capital reflects US$25.8 million increase in trade and other receivables and US$37.7 million reduction in trade and 
other payables.

As at 31 December 2016, there were no undrawn facilities available to the continuing operations. 

Capital expenditure 
The Group invested an aggregate of US$29.4 million on its gold projects compared to US$32.6 million invested in 2015. The key areas of focus  
this year were on fulfilling existing contractual commitments in relation to the POX Hub project, exploration to support the underground mining  
at Pioneer, expansion of tailing dams at Pioneer and Albyn and ongoing exploration related to the areas adjacent to the ore bodies of the Group’s 
main mining operations. 

POX
Pokrovskiy and Pioneer (b)
Malomir
Albyn
Upgrade of in house service companies

Exploration 
expenditure  
US$ million
–
8.6
1.9
6.1
–
16.6

Development 
expenditure and 
other CAPEX(a)  
US$ million
1.9
3.7
1.6
4.9
0.6
12.8

Total  
US$ million
1.9
12.3
3.5
11.0
0.6
29.4

(a)  Including US$1.9 million of development expenditure in relation to the POX Hub which is considered to be non-sustaining capital expenditure for the purposes of calculating all-in sustaining costs and all-in costs.

(b) Including US$5.5 million of exploration expenditure in relation to the underground mining project at Pioneer to be non-sustaining capital expenditure for the purposes of calculating the all-in sustaining costs 

and all-in costs.

  Petropavlovsk Annual Report 2016  67

Strategic reportFinancial statementsGovernanceChief Financial Officer’s Statement   continued

For the year ended 31 December 2016

Foreign currency exchange differences 
The Group’s principal subsidiaries have a US Dollar functional currency. Foreign exchange differences arise on translation of monetary assets and 
liabilities denominated in foreign currencies, which for the principal subsidiaries of the Group are the Russian Rouble and GB Pounds Sterling. 

The following exchange rates to the US Dollar have been applied to translate monetary assets and liabilities denominated in foreign currencies.

GB Pounds Sterling (GBP: US$)
Russian Rouble (RUB : US$)

31 December 2016
0.81
60.66

31 December 2015
0.68
72.88

The Rouble recovered by 17% against the US Dollar during 2016, from RUB72.88 : US$1 as at 31 December 2015 to RUB60.66 : US$1 as at 
31 December 2016. The average year on year depreciation of the Rouble against the US Dollar was approximately 10%, with the average 
exchange rate for 2016 being RUB67.18 : US$1 compared to RUB61.30 : US$1 for 2015. 

As a result of the significant volatility of the Russian Rouble, the Group recognised foreign exchange losses of US$5.2 million in 2016 
(2015: US$12 million) arising primarily on Rouble denominated net monetary assets.

Refinancing of the Group’s bank debt 
In December 2016, the Group refinanced US$430 million outstanding principal of the Group’s US$530 million bank debt, including a revised 
maturity profile and renegotiation of the financial and operational covenants. 

Results of the bank debt refinancing are set out below.

December 2016
US$ million
428.2

426.7
3.0
(1.5)

ultimate responsibility for the construction of 
the power line. Upon completion, the Group 
will get access to the enhanced capacity of 
the power supply infrastructure in the region. 
Under the terms of the Investment 
Agreement, the Group has certain capital 
commitments, including further development 
of Albyn and Malomir mines.

As at 31 December 2015, the Group  
received RUB1.1billion (an equivalent to 
US$15.1 million) funds under the Investment 
Agreement. During 2016, the Group  
received further RUB2.0 billion (an equivalent 
to US$30.8 million) under the Investment 
Agreement and transferred an aggregate 
RUB3.1 billion (an equivalent to 
US$47.7 million) to DRSK. 

Carrying value of liabilities de recognised
Fair value of new liabilities recognised:
  Bank debt
  Call option over the Company’s shares
Loss on bank debt refinancing 

Cash settled call option was issued in relation 
to 3.6 per cent. of the outstanding aggregate 
ordinary share capital in the Company and is 
exercisable between December 2019 and 
March 2023 at strike price of £0.068. 

Transaction costs of US$4.9 million were 
further capitalised. 

The Group is currently completing the final 
documentation to refinance the remaining 
US$100 million bank debt. Once this has 
been completed, the Group’s entire bank 
debt of US$530 million has been refinanced. 

Disposal of subsidiaries
The Group entered into agreements to sell  
its wholly owned subsidiary LLC Ilijnskoye  
and its associate JSC Verkhnetisskaya Ore 
Mining Company for an aggregate cash 
consideration of an equivalent to US$20 
million, payable in tranches during 2016,  
out of which US$19.8 million were attributed 
to the value of Visokoe asset held by LLC 
Ilijnskoye and the remainder to JSC 
Verkhnetisskaya Ore Mining Company. 
The disposal of LLC Ilijnskoye was completed 

on 11 May 2016. The Group recognised 
US$0.5 million net loss on this disposal.

Investment agreement with the Russian 
Ministry of Far East Development

On 14 December 2015, the Group entered 
into an investment agreement with the 
Russian Ministry of Far East Development (the 
‘Investment Agreement’). The Investment 
Agreement involves provision of RUB5.5 
billion (an equivalent to c.US$91 million as at 
31 December 2016) funding towards the 
construction of the electricity power line in the 
North East of the Amur Region of Russia, 
where the Group’s Albyn and Malomir mines 
and adjacent licence areas are operated, 
during the period 2015 – 2019. The funds are 
advanced to the Group and then should be 
transferred to the joint stock company Far 
East Grid Distribution Company (‘DRSK’), 
who is to engage a contractor to build the 
relevant power supply infrastructure. The 
Group’s responsibility under the Investment 
Agreement will be to monitor the progress 
and to report to the Russian Ministry of Far 
East Development. The Group will be taking 

68  Petropavlovsk Annual Report 2016    

2017 Outlook
The Group is confident to achieve 2017 
production guidance of 460koz. The Group’s 
operating cash expenses are substantially 
Rouble denominated. The Group expects its 
total average cash costs of production in 2017 
to be c.US$700/oz at current exchange rate. 
Net debt is expected to decrease to c.
US$550 million by the end of 2017, assuming 
an average gold price of US$1,200/oz for the 
remainder of 2017.

The Strategic Report was approved by the 
Board on 26 April 2017 and signed on its 
behalf by:

Peter Hambro
Chairman

The Group has guaranteed the outstanding 
amounts IRC owes to ICBC. The outstanding 
loan principal was US$234 million as at 31 
December 2016. The assessment of whether 
there is any material uncertainty that IRC will 
be able to repay this facility as it falls due is 
another key element of the Group’s overall 
going concern assessment. IRC has agreed 
with ICBC to restructure and reschedule two 
repayment instalments under the ICBC 
Facility Agreement, which are originally due 
for payment on 20 June 2017 and 20 
December 2017, with next repayment 
instalment due on 20 June 2018. IRC also 
obtained waivers from ICBC in respect of 
obligations to maintain certain cash deposits 
with ICBC until 30 June 2018 and obligations 
to comply with certain financial covenants 
until 31 December 2017 (inclusive).

Having taken into account the 
aforementioned factors, and after making 
enquiries and considering the uncertainties 
described above, the Directors have a 
reasonable expectation that the Group will 
have adequate resources to continue in 
operational existence for the foreseeable 
future, being at least the next 12 months from 
the date of approval of the 2016 Annual 
Report and Accounts. Accordingly, they 
continue to adopt the going concern basis of 
accounting in preparing these consolidated 
financial statements. 

Going concern
The Group monitors and manages its liquidity 
risk on an ongoing basis to ensure that it has 
access to sufficient funds to meet its 
obligations. Cash forecasts are prepared 
regularly based on a number of inputs 
including, but not limited to, forecast 
commodity prices and impact of hedging 
arrangements, the Group’s mining plan, 
forecast expenditure and debt repayment 
schedules. Sensitivities are run for different 
scenarios including, but not limited to, 
changes in commodity prices, cost inflation, 
different production rates from the Group’s 
producing assets and the timing of 
expenditure on development projects. This is 
done to identify risks to liquidity and covenant 
compliance and enable management to 
develop appropriate and timely mitigation 
strategies. The Group meets its capital 
requirements through a combination of 
sources including cash generated from 
operations and external debt. 

The Group performed an assessment of the 
forecast cash flows and covenant compliance 
in relation to bank facilities for the period of 12 
months from the date of approval of the 2016 
Annual Report and Accounts. As at 31 
December 2016, the Group had sufficient 
liquidity headroom and complied with related 
financial covenants. Following the successful 
completion of the bank debt refinancing, the 
Group is also satisfied that it has sufficient 
headroom under a base case scenario for the 
period to May 2018 and expects to comply 
with related financial covenants. In the 
meantime, the Group’s projections under a 
reasonable downside scenario indicate that, 
unless mitigating actions can be taken 
including accessing deposits not currently in 
the Group’s mining plan, there will be 
insufficient liquidity and non-compliance with 
certain financial covenants under a 
reasonable downside scenario for the 
relevant period to May 2018. If a missed debt 
repayment occurs or financial covenant 
requirements are not met, this would result in 
events of default which, through cross 
defaults and cross accelerations, could cause 
all other Group’s debt arrangements to 
become repayable on demand. The Directors 
are confident that, should it be required, 
relevant mitigating actions could be 
successfully implemented.

  Petropavlovsk Annual Report 2016  69

Strategic reportFinancial statementsGovernanceBoard of Directors 

Mr Peter Hambro
Chairman

Dr Pavel Maslovskiy 
Chief Executive Officer 

Mr Andrey Maruta
Chief Financial Officer

Mr Hambro is one of the co-founders of the 
Company and has been Chairman of the 
Group since its formation in 1994. 

Experience: Mr Hambro started his career 
with his family bank and became joint 
managing Director of Smith St. Aubyn 
Holdings Ltd before joining the Mocatta 
Group, the world’s largest bullion traders,  
as Deputy Managing Director of Mocatta  
& Goldsmid Limited. 

External Appointments: Non-Executive 
Chairman of Sundeala Limited, Peter Hambro 
Limited and Tidal Transit Limited, all of which 
are family companies and he is a partner in 
Heads Farm Partnership.

Committee membership: Chairman of the 
Nomination and Executive Committees.

One of the co-founders of the Company. 
Dr Maslovskiy held directorships within  
the Group including the position of Chief 
Executive Officer from the Group’s inception 
in 1994 until December 2011, when he 
relinquished all remunerated positions 
following his appointment as a Senator-
Member of the Federation Council  
(Upper House of the Russian Parliament). 
Dr Maslovskiy retired as a Senator-Member  
in October 2014 and was re appointed as 
Chief Executive Officer, in November 2014 
having acted as Honorary President during 
2012 to November 2014. 

Experience: Prior to embarking on his 
business career, Dr Maslovskiy was a 
Professor of Metallurgy at the Moscow 
Aircraft Technology Institute.

External Appointments: None.

Committee membership: Dr Maslovskiy  
is a member of the Executive Committee.

Mr Maruta was appointed to the Board as 
Finance Director – Russia in January 2011, 
and promoted to the position of Chief 
Financial Officer in April 2012.

Experience: Mr Maruta qualified as a 
Chartered Certified Accountant at Moore 
Stephens in 2001 and joined the Group in 
2003 as Group Chief Accountant. He was 
appointed Deputy Finance Director in 2005 
and Finance Director in 2006. 

Mr Maruta is a fellow member of The 
Association of Chartered Certified 
Accountants.

External Appointments: None.

Committee membership: Mr Maruta is a 
member of the Executive Committee.

70  Petropavlovsk Annual Report 2016    

Mr Robert Jenkins 
Senior Non-Executive Director

Mr Alexander Green 
Non-Executive Director 

Mr Andrew Vickerman 
Non-Executive Director

Mr Alexander Green was appointed as a 
Non-Executive Director on 27 August 2015.

Experience: Mr Green has twenty five years  
of experience in the resources industry. 
From 2003 to 2012, he was a Marketing 
Director at BHP Biliton, a leading global 
resources company and from 2013 to 2015 
he was a Non-Executive Director of Torm A/S, 
a Danish shipping company. Mr Green has  
a wealth of experience including risk 
management, development of business 
strategy and corporate governance.

Mr Green holds a Master’s degree in  
Global History from the London School  
of Economics and Political Science and a 
Bachelor’s degree in Civil Engineering from 
the University of Salford. 

External Appointments: Mr Green is a Board 
Observer with Fluidic Analytics Limited, a 
company that builds tools for protein 
characterisation.

Committee membership: Mr Green is 
Chairman of the HSE Committee and a 
member of the Company’s Audit and 
Remuneration Committees.

Mr Andrew Vickerman was appointed as a 
Non-Executive Director on 22 October 2015. 

Experience: Mr Vickerman spent 20 years 
with Rio Tinto, one of the world’s leading 
mining companies, the last ten as a member 
of the Operations and Executive Committees 
with responsibility for global communications 
and external relations. An economist by 
background he has previously worked for The 
World Bank and other international agencies.

Mr Vickerman holds BA, MA and Ph.D 
degrees in Economics from Cambridge 
University.

External Appointments: Mr Vickerman is a 
member of the Board of Trafigura Group Pte 
Ltd., an independent commodity trading  
and logistics house, Chairman of Alva  
Group, a technology company that provides 
business intelligence and Chairman of Direct 
Nickel, an Australian business that has 
developed technology for processing nickel 
laterite deposits.

Committee membership: Mr Vickerman is 
Chairman of the Remuneration Committee 
and a member of the HSE, Audit and 
Nomination Committees.

Mr Robert Jenkins was appointed as a 
Non-Executive Director on 30 April 2015 and 
as Senior Non-Executive Director on 28 
June 2016

Experience: Mr Jenkins is a Chartered 
Accountant, having qualified with KPMG in  
the UK, and has over 20 years’ Russia related 
investment experience, including in the 
natural resources sectors. He is also a fluent 
Russian speaker. 

Mr Jenkins was Finance Director of Eurasia 
Mining, a Russia focused mining exploration 
company, admitted to the AIM market of the 
London Stock Exchange and Chief Financial 
Officer of Urals Energy, a Russia based oil 
exploration and production company, prior to 
that company’s admission to AIM.

Mr Jenkins has an MA in Modern History and 
Modern Languages from Oxford University.

External Appointments: Mr Jenkins is a 
partner in NorthStar Corporate Finance, 
which specialises in advising companies  
on Russia related as well as other European 
acquisition and financing transactions. 
He was formerly Senior Independent Director 
and Audit Committee Chairman of Ruspetro 
plc, a UK Stock Exchange listed, Russia 
focused independent oil and gas 
production company. 

Committee membership: Mr Jenkins is 
Chairman of the Company’s Audit Committee 
and a member of the Nomination Committee.

  Petropavlovsk Annual Report 2016  71

GovernanceFinancial statementsStrategic reportCorporate Governance Report 

where possible in line with best practice, 
whilst recognising the individual needs of the 
business. 

It is the Board’s intention that appointment of 
any successful candidate is made with the 
support of our major shareholders and that 
the new director, while representing the 
interest of all shareholders equally, will be fully 
independent. 

Management team and diversity
The majority of our strong and broadly based 
executive team have been with the Company 
for over 12 years, with several of them having 
been with the Company since its inception in 
1994. This longevity ensures an open and 
honest dialogue which reflects the Group’s 
collaborative culture. The expertise and wide 
range of skills of the team gives the Board 
much comfort, knowing that any issues will be 
recognised at an early stage and actions 
taken, with matters being brought to the 
attention of the full Board as appropriate.

Within our finance team Natalia Buynova, 
Group Head of Corporate Reporting has 
been with the Company since 2009, having 
originally joined on secondment from PwC. 
Natalia regularly attends Audit Committee 
meetings and presents to the Committee. 
Zhanna Kirienko, the Group’s H&S Co-
ordinator, based in Blagoveshchensk, attends 
HSE Committee meetings to update the 
Committee on actions being taken to improve 
health and safety throughout the Group and 
to report on any accidents. Zhanna’s 
promotion to this position followed her 
successful completion of an MBA in London 
which was sponsored by the Group.

These are just a few examples of the 
professional women who work within the 
Group and reflect and demonstrate our 
diversity and our commitment to the 
development of our employees.

Further details of the Executive Committee 
are provided on pages 34 and 77.

These strengths are acknowledged by the 
Senior Lenders and the resulting bank 
refinancing is arranged so as to allow the 
Company to self fund the completion of the 
Pressure Oxidation project from free 
cashflow, provided always that the macro 
economic environment is as forecast.

Board effectiveness review
Although not a requirement for the Company 
under the UK Corporate Governance Code, 
the assessment of the Petropavlovsk Board 
was facilitated externally. Further details of this 
review, which has recently been concluded, 
are provided on page 76. 

Annual General Meeting
The Annual General Meeting (AGM) is 
recognised as an opportunity for all 
shareholders to engage with the Board and  
I look forward to welcoming them to the AGM 
to be held on 20 June 2017. 

Governance at Petropavlovsk is an important 
element of our Board environment and the 
following report sets out the details of the 
Company’s approach to corporate 
governance.

Peter Hambro
Chairman 
26 April 2017

Although the mining sector is recognised as a 
male dominated environment, the Group 
recognises and encourages the development 
of women in the workplace and this is 
reflected in the high number of professional 
women in senior positions throughout the 
Group. 

For example there are several very skilled and 
experienced women in our Executive team. In 
November 2016, I was pleased to announce 
the promotion of Dr Alya Samokhvalova to 
Deputy CEO, Strategic Development and the 
appointment of Alexandra Carse to replace 
her as Head of Investor Relations. Anna-
Karolina Subczynska, a fully qualified lawyer 
in both the UK and Russia is our Group Head 
of Legal Affairs and has been with the 
Company for over 13 years whilst Anna 
Makhina is our Head of Legal in Russia. Both 
Alya and Anna-Karolina attend Board 
meetings at my request and contribute to the 
Board’s discussions. Amanda Whalley, the 
Company Secretary has been with the 
Company for 6 years.

Chairman’s introduction

Dear shareholder

I am pleased to present the Corporate 
Governance Report for the year ended 
31 December 2016, on behalf of the Board.

2016 was a transformative year for 
Petropavlovsk, having finalised a two year 
balance sheet restructuring while maintaining 
its focus on deleveraging. The refinancing of 
the Group’s bank debt, focus on the Group’s 
strategic priorities and the composition of the 
Board were the principal issues for the 
Board’s focus during the year. 

We are committed to good governance 
throughout the Company. In this introduction, 
I highlight the depth and diversity of our 
management team and the steps that we are 
taking further to strengthen our governance 
practices.

Board structure 
The Board is currently made up of both British 
and Russian nationals: 

 – Executive Directors: 

 – Dr Pavel Maslovskiy, Chief Executive 

Officer

 – Andrey Maruta, Chief Financial Officer 

 – Non-Executive Directors: 

 – Robert Jenkins, Alexander Green, and 
Andrew Vickerman, all of whom are 
independent. 

 – Chairman 

 – My role as Chairman, principally based in 
London, includes some clearly defined 
executive responsibilities that are 
separated from those of the Chief 
Executive Officer, who is principally 
based in Russia. 

There is frequent and open dialogue between 
the executives and the excellent relationship 
with the Non-Executives ensures that the full 
Board is kept informed of all strategic and 
operational issues on a timely basis.

The Board structure is currently compliant 
with the requirements of the UK Corporate 
Governance Code. However, the Board 
believes that its composition could be further 
strengthened by the appointment of an 
additional Non-Executive Director. This also 
aligns with our strategy for continual 
improvement in our corporate governance 
practices to ensure that they are robust and 

72  Petropavlovsk Annual Report 2016    

Provision B.1.1. of the Code requires that  
the Board should state its reasons for 
determining that a director is independent 
notwithstanding the existence of relationships 
or circumstances which may appear relevant 
to its determination.

Mr Robert Jenkins provided advice to the 
Company, principally to the Audit Committee 
and Non-Executive Directors, during the 
refinancing of the Group’s 4 per cent 
Convertible Bonds due 2015 which 
completed in March 2015 and prior to his 
appointment as a Director. The Board does 
not deem that this constituted a material 
business relationship with the Company. 
Accordingly, the Board considers that 
Mr Jenkins was independent at the date  
of his appointment and continues to be  
an independent director of the Company.

In accordance with the requirement of the 
Code in respect of smaller companies, the 
Board comprised of at least two independent 
directors at all times during 2016.

Corporate governance framework
The following sections of this report detail the 
work and operation of the Board and the 
corporate governance framework within 
which the Company operates, including 
further reporting required under the UK 
Corporate Governance Code, the UK Listing 
Rules and the Disclosure Guidance & 
Transparency Rules, all of which the 
Company is subject to. 

Application of the UK Corporate 
Governance Code
The UK Corporate Governance Code  
(the ‘Code’) can be viewed on the website  
of the Financial Reporting Council at  
www.frc.org.uk.

The Code sets out key corporate governance 
recommendations for companies, like 
Petropavlovsk, that have a premium listing of 
their equity shares on the main market of the 
London Stock Exchange. It consists of broad 
principles and specific provisions of good 
governance in the following areas: leadership, 
effectiveness, accountability, relations with 
shareholders and remuneration.

This corporate governance report is arranged 
around these main principles and together 
with the Audit Committee Report (on pages 
80 to 86), the Directors’ Remuneration Report 
(on pages 87 to 103) and the Nomination 
Committee Report (on page 79) sets out how 
the Company has applied the main principles 
of the Code during 2016.

The Company has complied with the 
requirements of the Code published in 
September 2014 throughout the year ended 
31 December 2016. However the following 
should be noted:

  Petropavlovsk Annual Report 2016  73

GovernanceFinancial statementsStrategic reportCorporate Governance Report   continued

Role of the board

Membership:
Mr Peter Hambro 
Dr Pavel Maslovskiy 
Mr Andrey Maruta 
Mr Robert Jenkins 
Mr Alexander Green 
Mr Andrew Vickerman

Further information:

 – The Group’s near term, medium term and 
long term strategy, set by the Board, are 
fully described in the Strategic Report on 
the inside front cover.

 – Directors’ Biographies are on pages 70 to 71. 

The Board is responsible to shareholders for the long term sustainable success of the 
Company. The Board’s role is to ensure that the Company follows this strategy and that a 
financial and operational structure is in place to enable the Group to meet its goals.

The Board has adopted a formal schedule of matters reserved for the Board’s decision a copy 
of which is available at www.petropavlovsk.net. These matters include responsibility for the 
determination and monitoring of the Company’s strategic aims, budgets, major items of capital 
expenditure and senior appointments. 

Code compliant: 
The Board comprises three Independent Non-Executive Directors

Board changes during the year

On 28 June 2016, Sir Roderic Lyne stepped down as a Non-Executive Director, after over nine 
years of valuable service with the Company, including his service as a director of Aricom plc, 
from October 2006 to April 2009. Mr Robert Jenkins, a director since April 2015, replaced Sir 
Roderic in his role as Senior Independent Director. 

Board composition and roles

Chairman: 
Mr Peter Hambro

Chief Executive Officer: 
Dr Pavel Masvlovskiy

The Chairman provides the leadership to and direction of the Board. This is necessary to 
promote the success of the Company and create value for shareholders in the long term, whilst 
ensuring that sound, effective corporate governance practices are embedded in the Group 
and in its decisions making processes.

Supported by the Chief Financial Officer and the Executive Committee, the Chief Executive 
Officer has day to day responsibility for the Group’s operations within Russia, for developing 
the Group’s objectives and strategy and for the successful achievement of objectives and 
execution of strategy, following approval by the Board. 

Code Compliant: 
The Chairman and Chief Executive Officer have clearly defined and separated responsibilities.

Chief Financial Officer: 
Mr Andrey Maruta

The Chief Financial Officer supports the Chief Executive Officer in implementing the Group’s 
strategy in addition to his specific responsibilities as Chief Financial Officer.

Senior Non-Executive Director:
Mr Robert Jenkins

The Senior Independent Director provides an independent point of contact to shareholders on 
Board matters or any matters of concern that shareholders have been unable to resolve 
through the normal channels of chairman, chief executive or other executive director or for 
which such contact is inappropriate.

Non-Executive Directors: 
Mr Robert Jenkins 
Mr Alexander Green 
Mr Andrew Vickerman

The Non-Executive Directors are responsible for bringing independent and objective analysis 
to all matters before the Board and its Committees, using their substantial and wide ranging 
experience. They bring to the Board a diverse range of business and financial expertise which 
complements the experiences of the Executive Directors. 

Code compliant:
Senior Independent Non-Executive Director
The Non-Executive Directors meet periodically with the Chairman without the Executives being present.
The Non-Executive Directors hold meetings without the Chairman or Executive Directors being present.

74  Petropavlovsk Annual Report 2016    

Effectiveness and Accountability of 
the Board

The Directors Business Experience, 
Independence and Country of Permanent 
Residence
The adjacent graphs illustrate the collective 
business experience of the Directors outside 
that acquired at Petropavlovsk as at the date 
of this report, Director Independence as 
determined by the Board, nationality and 
language skills.

Detailed knowledge of the gold mining 
industry, Russia and the Group’s operations 
are considered as being critical to the Board’s 
ability to lead the Company.

 – Approval of a new share dealing policy and 
disclosure manual to ensure compliance 
with the Market Abuse Regulations.

During the year and at the request of some of 
the Company’s major shareholders the Board 
constituted an independent committee of the 
Board comprising Andrew Vickerman as 
Chairman, Robert Jenkins and Alexander 
Green to review the proposed acquisition of 
Amur Zoloto LLC. The Independent 
Committee appointed an external financial 
adviser to review the terms of the proposed 
acquisition and to advise on whether they 
considered these to be ‘fair and reasonable.’ 
The Independent Committee met on a 
number of occasions to consider this matter.

Board activities during the year
In 2016, the Board met on five scheduled 
occasions, with 17 additional meetings held 
during the year, principally due to the bank 
refinancing, strategic issues and 
consideration of matters relating to IRC. 
Many of these additional meetings were called 
at short notice and were accommodated as 
conference calls. Further Board meetings 
were held to deal with matters of a routine  
or administrative nature. 

Board Committees
The Board is responsible for the Group’s 
system of corporate governance and is 
ultimately responsible for the Group’s 
activities, strategy, risk management and 
financial performance. The Board has 
established a number of Committees and 
provides sufficient resources to enable them 
to undertake their duties. Please see pages 
77 to 78 for further details of these 
Committees.

Board balance of Directors

Chairman (1)
Independent Non-
Executive Directors (3)
Executive Directors (2)

Directors of other 
quoted companies
Finance
Fund management/ 
banking
Diplomatic/political
Metals & mining
Business experience 
within Russia

Independent
Non-independent

Business experience

Independence

In addition to the standard agenda items, 
the Board considered the following matters 
during the year:

Directors’ induction and professional 
development, information flow and 
professional advice

Nationality

Russian
British

 – Consideration and approval of the 

refinancing of the Group’s bank debt with  
its lending banks Sberbank and VTB (the 
‘Senior Lenders’), as announced in 
December 2016

 – Evaluating and approving the proposed 

acquisition of Amur Zoloto LLC, which as 
announced on 16 December 2016 is no 
longer proceeding

 – Reviewing the proposed joint venture for  
the completion of the POX Hub with GMD 
Gold. Following agreement with the Senior 
Lenders the Group is completing the POX 
Hub from its free cashflow depending on 
the gold price

 – Reviewing the progress of the Group’s 

underground mining project

 – Monitoring the progress of the construction 
of IRC’s K&S Facility and IRC’s negotiations 
with ICBC regarding the deferral of its two 
scheduled principal repayments due in 
2017 under the ICBC Project Finance 
Facility

 – Composition of the Board in relation to a 
new Non-Executive Director appointment

Induction and Professional Development
Each Director is provided with an induction 
programme upon appointment and they are 
expected to update their skills and 
knowledge, and develop the familiarity with 
the Group’s operations needed to fulfil their 
role on both the Board and any Committees. 

The Board considers that visits to the  
Group’s gold mining operations are an 
important part of a Director’s induction and 
their understanding of the size and scale of 
the Group’s operations. Mr Jenkins visited  
the Group’s operations in the Far East Amur 
Region in October 2015, as part of his 
induction. This included a visit to the Group’s 
laboratories, the POX Hub and the pilot POX 
plant in Blagoveshchensk. Messrs Green and 
Vickerman who were appointed to the Board 
during the latter part of 2015 have not yet 
visited the mines. However, a Board visit to 
the Group’s mining operations is proposed for 
all of the Directors later in this year.

Detailed knowledge of the gold mining industry, 
Russia and the Group’s operations are 
considered as being critical to the Board’s 
ability to lead the Company.

Language skills – Russian

Native
Fluent
Basic or none

Language skills – English

Native
Fluent

  Petropavlovsk Annual Report 2016  75

GovernanceFinancial statementsStrategic reportCorporate Governance Report   continued

The Non-Executive Directors may attend 
conferences and seminars on the mining 
industry at the Company’s expense to 
enhance and update their knowledge. 
The Directors receive briefings on regulatory 
and corporate governance issues from the 
Company Secretary and the Company’s 
advisers.

Information flow
Prior to each Board meeting the Directors 
receive detailed information on operational 
and financial performance, activities of the 
Board Committees, investor relations and 
projects that are being progressed by the 
Executive management. The Board receives 
presentations and verbal updates from the 
Executive Directors and members of the 
Executive Committee at Board meetings as 
appropriate. All Directors are encouraged to 
make further enquiries and request further 
information as they feel appropriate, of the 
Executive Directors or management. All 
Directors are encouraged to participate 
actively in Board meetings which are chaired 
in an open and collaborative manner. 

All Directors have access to the services of a 
professionally qualified and experienced 
Company Secretary, who is responsible for 
information flows to the Board and its 
committees and between senior 
management and Non-Executive Directors, 
facilitating induction and assisting with 
professional development as required, 
ensuring compliance with Board procedure 
and applicable laws and regulation.

Professional advice
There is an agreed procedure for Directors to 
take independent professional advice if 
considered necessary to discharge their 
responsibilities as Directors and at the 
Company’s expense.

Investor engagement during the year
We delivered on our communication strategy 
in 2016 by:

 – Maintaining an active dialogue with our 
shareholders, with members of the 
Executive team meeting with approximately 
40 individual investor companies during 
the year

 – The Executive team attending investor 

conferences in the UK, Europe and USA, 
including London, Moscow and New York

 – Arranging conference calls for investors and 
analysts following the Company’s full year 
and half year results announcements

76  Petropavlovsk Annual Report 2016    

 – Ensuring copies of all investor presentations 

are made available on the Company’s 
website at www.petropavlovsk.net

 – Organising meetings of the Independent 
Non-Executive Directors with several of  
the Company’s major shareholders during 
the year. 

The respective chairs of the Audit, 
Remuneration and HSE Committees will be 
available, at the forthcoming AGM, to answer 
any questions relating to those committees. 
The Company Chairman will be available to 
answer any questions relating to the work of 
the Nomination Committee.

The Senior Independent Director is also 
available to discuss matters with the 
Company’s shareholders.

In addition a new Company website, 
launched in March 2017, was designed to 
strengthen our communication with our 
stakeholders. The website provides the latest 
news, details about forthcoming events for 
shareholders and analysts, and other 
information regarding the Group.

The Company aims to maintain an active and 
constructive dialogue with all of its 
shareholders as well as potential 
shareholders. The Investor Relations 
department manages the interaction with 
these audiences and ensures that full and 
comprehensive information is available to all 
shareholders. Shareholders are welcome to 
contact the Company’s Investor Relations 
department during the year with any specific 
queries regarding the Company. 

The Chairman ensures that any significant 
concerns raised by a shareholder in relation to 
the Company are communicated to the 
Board. Feedback from meetings held 
between the Executive team and institutional 
shareholders is also communicated to the 
Board.

The AGM
Individual shareholders are equally as 
important to the Company as are its 
institutional shareholders and the Board 
encourages as many shareholders as 
possible to attend the Company’s Annual 
General Meeting during which shareholders 
are given the opportunity to discuss matters 
with the Board. All resolutions at the 2016 
AGM were voted by way of a poll. This follows 
best practice and allows the Company to 
count all votes rather than just those of 
shareholders attending the meeting. As 
recommended by the Code, all resolutions 
were voted separately and the final voting 
results, which included all votes cast for, 
against and those withheld, together with all 
proxies lodged prior to the meeting, were 
released to the London Stock Exchange as 
soon as practicable after the meeting. 

Board evaluation outcome
A Board evaluation was undertaken in early 
2017 which was conducted by an external 
facilitator. This external consultant have no 
other connection with the Company. This 
review entailed a rigorous evaluation of the 
Board, its Committees and individual 
members, thus providing the Chairman with 
an objective means of assessing their 
performance. The evaluation involved online 
questionnaires, Board director interviews, 
interviews with certain members of the 
Executive Committee, a Board effectiveness 
report and improvement recommendations.

The Board evaluation has now been 
completed and the Board will be considering 
the findings in due course and will agree  
such actions as it considers necessary. 
Further detail will be included in the 2017 
Annual Report.

Annual re election of Directors
In accordance with the recommendations of 
the Code, all eligible Directors will be offering 
themselves for re election or appointment at 
the AGM on 20 June 2017. The re election of 
each of the eligible Directors has been 
reviewed by the Nomination Committee and 
the Board who are satisfied that each of the 
Directors continues to be effective and 
demonstrates commitment to the role. The 
Board recommends that shareholders vote in 
favour of the resolutions to re elect all of the 
eligible Directors of the Company and the 
reasons for this recommendation will be set 
out in the accompanying letter to the Notice of 
the Annual General Meeting.

The Board is satisfied that each of the 
Directors continues to be effective and 
demonstrates commitment to the role; and 
that re appointment is in the Company’s 
best interest. 

Board Committees
A diagram detailing the corporate governance 
framework established by the Board including 
the principal role of each Board Committee is 
shown on page 77.

The Board and its Committees (Membership as at 31 December 2016)

Board 
The Board is responsible for the Group’s system of corporate governance  
and is ultimately accountable for the Group’s activities, strategy, risk management  
(including anti-bribery matters) and financial performance.

Board Committees

Audit  
Committee

Remuneration 
Committee

Nomination 
Committee

HSE 
Committee

–  Reviews Audit Report on  
the interim review and full 
year audit

–  Reviews appropriateness of 

accounting standards

–  Oversees relationships with 

external auditors

–  Overseas external 

audit process

–  Reviews the financial risks

–  Reviews internal 

audit plans.

Membership

Robert Jenkins (Chair)

Alexander Green

Andrew Vickerman

–  Determines and agrees with 
the Board the format and 
broad policy for the 
remuneration of the 
Company Chairman, 
Executive Directors, 
members of the Executive 
Committee and the 
Company Secretary

–  Reviews the on going 
appropriateness of 
the policy

–  Ensures that the Company 

maintains contact with 
shareholders regarding the 
Company’s remuneration 
policy.

–  Reviews structure,  

size and composition  
of the Board and its 
Committees and makes 
recommendations to  
the Board as appropriate

–  Considers succession 

planning issues for Directors 
and senior executives

–  Evaluates the skills  

and experience of the Board 
before any appointment is 
recommended to/made by  
the Board.

–  Reviews the Group’s health, 
safety, environmental and 
community relations 
(“Sustainability”) strategy

–  Evaluates the effectiveness 
of the Group’s policies and 
systems for managing 
Sustainability issues  
and HSE risks

–  Assesses the performance 
of the Group with regard  
to the impact of 
Sustainability decisions and 
actions.

Membership

Membership

Peter Hambro (Chair)

Alexander Green (Chair)

Membership

Robert Jenkins

Dr Pavel Maslovskiy 

Andrew Vickerman (Chair)

Andrew Vickerman

Dr Alya Samokhvalova

Alexander Green

Dmitry Chekashkin (Alternate 
for Dr Maslovskiy)

The Report of the Audit 
Committee is on pages 80 to 86 
of this Report. 

The Report of the Remuneration 
Committee is on pages 87 to 103 
of this Report.

The Report of the 
Nomination Committee  
is on page 79 of this Report.

Please see pages 34 to 35.

The Company Secretary acts as secretary to the Audit, Remuneration, Nomination, HSE, and Executive Committees. 
All Committees are authorised to obtain legal or other professional advice as necessary and to secure the attendance of external advisers at their meeting.

Executive  
Committee

–  Responsible for the day to 

day management  
of the Company

–  Recommends strategy and 

direction to the Board

–  Acts as a conduit between 

management and the 
Board.

Committee membership  
is detailed below.

Strategic  
Committee

–  Responsible for the 

evaluation of projects from a 
strategic perspective 

–  Reviews the Group’s 

exploration assets as part of 
the Group’s full year and 
interim results procedure. 

The Strategic Committee  
is chaired by Dr Alya 
Samokhvalova, Deputy CEO 
Strategic Development

Members of the Executive Committee as at 31 December 2016:
The Chairman and Executive Directors
Mr Valery Alexseev, Group Head of Construction and Engineering
Mr Dmitry Chekashkin, Chief Operating Officer
Mr Sergey Ermolenko, General Director Management Company Petropavlovsk 
Mr Alexey Maslovskiy, Business Development Manager
Dr Alya Samokhvalova, Deputy CEO Strategic Development
Mrs Anna-Karolina Subczynska, Group Head of Legal Affairs
Mr Andrei Tarasov, Deputy General Director Management Company Petropavlovsk

  Petropavlovsk Annual Report 2016  77

GovernanceFinancial statementsStrategic reportCorporate Governance Report   continued

Meetings of the Board, Board Committees and attendance

Peter Hambro
Pavel Maslovskiy
Alexander Green 4,5
Robert Jenkins 3,4

Sir Roderic Lyne 3,4,5
Andrey Maruta
Andrew Vickerman 5

Key: C= Chairman, M= Member

Board

Audit

Remuneration

Nomination

HSE

C
M
M
M

M
M
M

5/5
5/5
5/5
5/5

3/3
5/5
5/5

–
–
M
MC

M
–
M

4
2
3/4
4/4

–
4
4/4

–
–
M
–

C
–
MC

2/2
–
2/2
–

1/1
–
2/2

 C
–
–
M

M
–
–

2/2
–
–
2/2

1/1
–
2/2

–
–
MC
M

C
–
M

5
4/5
5/5
2

3/3
1
5/5

1  Scheduled Board meetings only. Additional Board meetings were held during the year, principally relating to strategic matters including the proposed acquisition of Amur Zoloto LLC and the proposed joint 

venture arrangement with GMD Gold for the construction of the POX Hub, the refinancing and matters relating to IRC. 

2  Directors who are not members of the Audit, Remuneration and HSE Committees may attend meetings at the invitation of the Chairman of that Committee.

3  Sir Roderic Lyne retired as a Director of the Company following the conclusion of the Company’s annual general meeting on 28 June 2016. Mr Robert Jenkins was appointed as Senior Independent Director 

upon Sir Roderic’s retirement.

4   Director who the Board has determined to be independent.

5   Sir Roderic Lyne was Chairman of the Remuneration Committee and the HSE Committee until 28 June 2016, when he retired as a Director of the Company, at which time Mr Andrew Vickerman and Mr 

Alexander Green were appointed as Chair of the Remuneration Committee and the HSE Committee respectively.

78  Petropavlovsk Annual Report 2016    

Nomination Committee Report 

Letter from the Nomination Committee Chairman

Dear shareholder

I am pleased to present this report on behalf 
of the Nomination Committee.

Membership of the Committee
I continue to chair the Committee assisted  
by Mr Robert Jenkins and Mr Andrew 
Vickerman. Mr Vickerman was appointed  
to the Committee on 28 June 2016 following 
the retirement of Sir Roderic Lyne as a 
Director and as a member of the Committee. 
The Committee met on two formal occasions 
during the year, with regular contact  
between meetings. 

As detailed in my Chairman’s statement I will 
retire as Nomination Committee Chairman 
and as a member of the Committee. 
Mr Alexander Green, independent Non-
Executive Director will be appointed to the 
Committee.

Board appointment process 
During the year the Committee led the 
process to identify a suitable candidate  
to replace Sir Roderic. This involved the 
appointment of external consultants and 
discussions with some of the Company’s 
major shareholders, including at a meeting, 
to consider what level of skills and experience 
the replacement candidate should have. 
The meeting also considered whether it 
would be appropriate to appoint further 
additional directors given the stage of the 
Company’s development.

Following these discussions names of 
potential candidates for inclusion in the 
appointment process were provided by some 
of the major shareholders. The external 
consultants, who have no other connection 
with the Company, progressed the selection 
process based on the detailed brief provided 
by the Committee which specified the skills 
and experience required having taken into 
account comments expressed by our major 
shareholders. A long list of names was then 
proposed to the Committee and a number  
of candidates were interviewed during the 
year by all members of the Nomination 
Committee with a number also meeting with 
the Chief Executive Officer and the Chief 
Financial Officer.

Although suitable candidates were identified, 
the Company has not yet been successful in 
appointing Sir Roderic’s replacement for a 
number of reasons, for example due to 
conflict of interest reasons with the principal 
employer of a preferred candidate.

Whilst recognising that, with three 
independent Non-Executive Directors, the 
composition of the Board is fully compliant 
with the UK Corporate Governance Code, the 
Nomination Committee and the Board are 
somewhat disappointed that we have not yet 
found a suitable replacement for Sir Roderic. 
We continue to manage the process such 
that an appointment can be made as soon as 
possible whilst endeavouring to ensure that 
the chosen candidate will fully complement 
the Board.

Diversity statement
During our current search to date we have 
met with and considered a number of highly 
skilled and experienced woman for the above 
position. Indeed one of our preferred 
candidates was a woman. However the 
Committee’s principal goal during our current 
search for a new Non-Executive Director, is  
to appoint a candidate with the correct skills 
and experience to complement our existing 
Directors, in order that the Board has the  
right balance to take the Group forward  
into this next exciting stage of its strategy. 
The Committee believes that this is in the best 
interest of the Company and its shareholders. 
Consequently the Board has not set, and 
does not intend to set, a specific target for the 
number of female members of the Board as  
it wishes to continue to appoint the best 
candidate available to it for any particular role.

The Company values diversity and we  
have several very skilled and experienced 
women in our executive team, including 
Dr Alya Samokhvalova who was promoted  
to the position of Deputy CEO Strategic 
Development in December 2016. 
Further detail of our management team  
and its diversity are provided in the Corporate 
Governance Report on page 72 of this 
Annual Report. 

Succession planning
The Committee notes the focus of 
shareholders and the Financial Reporting 
Council on a company’s succession plans 
and the role that the Nomination Committee is 
expected to fulfil in this regard. The 
Committee has dicussed this matter to some 
extent during 2016 particularly with respect to 
the Executive Directors and it is intended that 
this will have a higher profile on the agenda 
during 2017. We look forward to reporting to 
shareholders in more detail on this matter in 
the 2017 Annual Report.

Effectiveness of the Committee
As detailed on page 76 of this Annual Report, 
the Board has recently undertaken an 
evaluation of its effectiveness and that of its 
Committees facilitated by external 
consultants. The Committee was found to be 
acting effectively and in accordance with its 
terms of reference.

Details of the other activities of the Committee 
during the year are provided below.

I will be available at the forthcoming Annual 
General Meeting to answer any questions that 
shareholders may wish to ask on the work of 
the Committee. 

Peter Hambro
Chairman,  
Nomination Committee 
26 April 2017

Additional activities during the year:

 – Evaluation of each of the eligible Directors in 
respect of their re election and subsequent 
recommendation to the Board 

 – Approval of the 2015 Nomination 

Committee Report.

The terms of reference of the Nomination 
Committee are available on the Company’s 
website at www.petropavlovsk.net

  Petropavlovsk Annual Report 2016  79

GovernanceFinancial statementsStrategic reportAudit Committee Report 

Letter from the Audit Committee Chairman

The Committee continues to assist the Board 
in its review of the Group’s internal control 
systems and oversees the reporting process 
in order to ensure that the information 
provided to shareholders in this Annual 
Report taken as a whole is ‘fair, balanced and 
understandable’ and allows assessment of 
the Company’s performance, business model 
and strategy. In addition the Committee has 
again advised the Board on the viability 
statement required under the UK Corporate 
Governance Code.

A more detailed review of the Committee’s 
work during the year is provided in this 
Report. I hope that you will find this 
informative.

Robert Jenkins
Audit Committee Chairman 
26 April 2017

Dear shareholder

I am pleased to introduce this report as  
Audit Committee Chairman.

The challenging environment continued 
throughout 2016, with further volatility in the 
gold price and exceptionally adverse weather 
conditions in the latter part of the year 
resulting in lower 2016 production than had 
originally been guided.

In addition the uncertainty regarding both the 
refinancing of the Group’s bank debt and 
IRC’s ability to reschedule its debt under the 
ICBC project finance facility resulted in an 
‘emphasis of matter’ relating to going concern 
in the Company’s 2016 Half Year accounts.

However, the Group commenced 2017  
in a stronger financial position, given the 
successful refinancing of the Group’s bank 
debt with its lenders, Sberbank and VTB (the 
‘Bank Debt Refinancing’). The extension of 
the maturity profile allows the Company to 
focus on its strategic goals and objectives. 
In addition IRC has made significant progress 
by i) securing a new investor who has injected 
US$26 million of new equity, ii) moving 
towards full production at its K&S iron ore 
processing facility and iii) obtaining waivers 
from ICBC for the two scheduled repayments 
due in 2017 under the IRC project finance 
facility. The 2017 debt repayment deferral 
obtained by IRC has reduced the risk to 
Petropavlovsk as guarantor to IRC’s debt. 
We consider this to be a significant reduction 
in our risk profile. 

These matters, which were the focus of 
considerable and regular review by the 
Committee during the year, are discussed  
in this report.

Committee membership
There has been no change in the Committee 
membership throughout the year which 
remains a fully independent body, comprising 
only of independent Non-Executive Directors. 
I have continued as Chair, assisted by 
Alexander Green and Andrew Vickerman. 
My colleagues and I continue to meet 
regularly with Timothy Biggs, from Deloitte 
LLP lead audit partner of Petropavlovsk. In 
addition, I accompanied the external audit 
team on their visit to our mining operations 
which was also attended by Venmyn Deloitte 
(“Venmyn”), technical mining experts, who 
review operational factors and contribute to 
the overall audit process. During my visits to 
the mines I have had the opportunity to hold 
discussions with local management, including 
the Group’s top geologists, to understand 
better our processes and operations. 
This has also given me a more detailed 
understanding of the issues regarding gold in 
circuit, which are explained later  
in this Report on page 84.

The Committee continues to engage 
constructively with the Executive 
management team, and the external auditor 
particularly with regards to the significant 
matters that were considered by the 
Committee, as detailed on pages 83 to 84.

During the year the Committee continued to 
devote significant time to reviewing the 
Group’s financial risks, the integrity of the 
Group’s financial reporting and the 
effectiveness of both internal and external 
audit. To develop my understanding I met 
separately with the Group Head of Internal 
Audit, who directly reports to the Committee, 
in both Moscow and London, to discuss the 
outcome of internal audit reviews and to 
develop the scope of internal audit to provide 
further assurance to the Committee on the 
effectiveness of the Group’s controls. 

80  Petropavlovsk Annual Report 2016    

Committee membership as at 26 April 2017 
and during 2016:

Mr Robert Jenkins

Mr Alexander Green

Mr Andrew Vickerman

Governance
Mr Jenkins was appointed as Audit 
Committee Chairman on 30 April 2015, and is 
considered by the Board as having the 
requisite and relevant financial experience 
due to his profession as a Chartered 
Accountant and his previous roles as Finance 
Director and Chief Financial Officer of two 
Russia focussed natural resource companies, 
including a UK AIM listed mining exploration 
company. Mr Jenkins was also the Senior 
Independent Director and Audit Committee 
Chairman of Ruspetro plc, an independent oil 
and gas production company, until its’ 
delisting from the London Stock Exchange in 
June 2016.

Messrs Vickerman and Green also have 
relevant experience within the mining sector. 
Mr Vickerman having spent almost 20 years 
with Rio Tinto, one of the world’s leading 
mining companies, the last ten as a member 
of the Operations and Executive Committee 
with responsibility for global communications 
and external relations. From 2003 to 2012, Mr 
Green was a Marketing Director at BHP 
Billiton, a leading resources company. The 
Board therefore considers that the 
Committee as a whole has competence 
relevant to the sector in which it operates.

The Company’s Chairman, the Chief 
Executive Officer, the Chief Financial Officer, 
the Internal Auditor and Group Head of 
Corporate Reporting and representatives of 
the external auditors are invited to attend all 
Committee meetings with Deloitte LLP 
attending all Committee meetings in 2016. In 
addition, the Committee Chairman meets on 
a regular basis with the Company Chairman 
and the Chief Financial Officer to discuss any 
issues and with the lead partner of the 
external auditor on a regular basis and prior to 
each Committee meeting.

Mr Timothy Biggs, the leader of Deloitte’s UK 
metals and mining sector, was appointed as 
lead audit partner in 2014. Under 
independence requirements, he is required to 
rotate as lead audit partner following the audit 
for the year ending 31 December 2018.

The Committee met on four occasions during 
the financial year to align with the Group’s 
financial reporting calendar. 

Summary of the Committee’s 
responsibilities
The Committee’s terms of reference set out 
its main responsibilities, and are available to 
view on the Company’s website. The 
Committee is responsible for:

 – The integrity of the Company’s financial 
statements and the significant reporting 
judgements contained in them

 – The appropriateness of the Company’s 
relationship with the external auditors, 
including auditor independence, fees and 
provision of non-audit services

 – The effectiveness of the external audit 

process, making recommendations to the 
Board on the appointment of the external 
auditor

 – The effectiveness of the Group’s internal 

control and financial and tax risk 
management systems 

In carrying out its responsibilities, the 
Committee has full authority to investigate all 
matters within its terms of reference. 
Accordingly, the Committee may:

 – Obtain independent professional advice in 

the satisfaction of its duties at the cost of the 
Company

 – Have direct access to the resources of the 

Group as it may reasonably require 
including the external and internal auditors. 

Activity during the year
During the year, amongst other matters, 
the Committee:

Financial statements and reports
 – Reviewed the 2015 Annual Report and 
Accounts and the six months’ Half Year 
report ended 30 June 2016 before 
recommending their adoption by the Board. 
As part of these reviews the Committee 
received reports from the external auditor, 
reviewed accounting policies, estimates 
and judgements applied by management in 
preparing the relevant statements and the 
transparency and clarity of disclosure 
contained within them

 – Considered whether the 2015 Annual 

Report and Accounts, taken as a whole, 
was fair, balanced and understandable and 
reported to the Board on its conclusion.

 – Where requested by the Board, providing 
advice on how, taking into account the 
Company’s position and principal risks, the 
Company’s prospects have been 
assessed, over what period and why the 
period is regarded as appropriate 

Bank Debt Refinancing
 – Closely monitored the Group’s financial 

position and its compliance with its financial 
covenants and monitored and reviewed the 
proposed terms of the Bank Debt 
Refinancing and negotiation thereof. 

 – Advising the Board on whether there is a 

reasonable expectation that the Company 
will be able to continue in operation and 
meet its liabilities as they fall due over the 
said period, drawing attention to any 
qualifications or assumptions as necessary. 

Risk management
 – Considered the output from the Group’s 

financial and tax review process undertaken 
to identify, evaluate and mitigate risks, 
advising the Board of changes in these risks 
as appropriate. See pages 26 to 28 of the 
Risks to Our Performance section which 
describes the Group’s principal financial 
risks during the year and actions taken to 
mitigate against them.

  Petropavlovsk Annual Report 2016  81

GovernanceFinancial statementsStrategic reportAudit Committee Report   continued

Internal audit
 – Evaluated the effectiveness and the scope 
of work to be undertaken by Group Internal 
Audit during 2016, which included audits to 
be performed at the Group’s mining 
operations and the Group’s offices in both 
Moscow and Blagoveshchensk. During the 
year the Group Head of Internal Audit 
presented his findings to the Committee 
from various assignments internal audit had 
been requested to undertake by the 
Committee. The presentation included 
details of issues identified and subsequent 
actions taken. For example the audit of fuel 
usage and storage and procedures resulted 
in improved management controls over fuel 
inventory, in particular through daily cut off 
reconciliations.

 – Audits undertaken during the year, amongst 

others, were:

 – Ongoing monitoring of working capital

 – Group’s warehouse storage facilities

 – Procurement, storage, use and 
accounting of spares and tyres 

 – Reviewed and approved the 2017 audit plan 

which will include an audit of the supply 
chain management and the testing of the 
effectiveness of internal controls over 
purchasing.

 – Reviewed management responses to audit 

reports issued during the year.

External auditor and non-audit work
 – Reviewed, considered and agreed the 

scope and methodology of the audit work 
to be undertaken by the external auditor

 – Agreed the terms of engagement for the 
audit of the 2016 financial statements.

Governance
 – Evaluated the performance of the 

Committee

 – Evaluated the independence and objectivity 

of the external auditor

To date in 2017 the Committee has reviewed, 
amongst others, the following matters in 
relation to the 2016 financial statements:

 – The going concern assumption

 – The carrying value of the Group’s mining 

assets including the POX Hub

Committee action
Given the importance of the Bank Debt 
Refinancing and IRC’s financial position the 
Committee continually monitored these 
matters and considered the appropriateness 
of the going concern assumption by receiving 
regular updates from:

 – The carrying value of the Group’s evaluation 

 – the Executive Directors on the status of 

and exploration assets 

negotiations with the principal lenders; and

 – The recoverability of gold in circuit inventory

 – IRC’s Executive Directors on the status of 

 – Accounting for the refinancing

The Committee has also advised the Board 
on:

 – Whether the 2016 Annual Report and 

Accounts taken as a whole is fair, balanced 
and understandable and the Directors’ 
statement in this respect is set out on 
page 110

 – The viability statement of the Company 

required in accordance with provision C.2.2 
of the Code.

Significant issues considered by the 
Committee during 2016

The going concern assumption
The key judgement for the Committee during 
2016 related to the appropriateness of this 
basis of accounting. During the year the 
Group’s assessment was highly sensitive to:

 – negotiations with its principal lenders, VTB 

and Sberbank, to obtain satisfactory 
modifications and temporary waivers 
regarding the existing covenants and the 
repayment schedule (the ‘Bank Debt 
Refinancing’); and

 – uncertainties in relation to IRC and its ability 
to have sufficient liquidity to facilitate a debt 
repayment of US$21.5 million in December 
2016 or to renegotiate the terms of the ICBC 
project finance facility.

negotiations with ICBC and the 
commissioning of K&S.

Conclusion
When reviewing the half yearly financial 
statements for the six months’ ended 30 June 
2016, the Committee considered the status of 
the Bank Debt Refinancing and the progress 
of IRC and noted that whilst there could be no 
guarantee that the Bank Debt Refinancing 
and IRC’s discussions would be successful 
the Directors had a reasonable expectation 
that they would be and therefore the going 
concern basis of accounting remained 
appropriate.

In December 2016, the Company refinanced 
US$430 million of its bank debt with 
Sberbank and VTB. 

Significant issues considered by the 
Committee in the context of the 2016 
financial statements:

The Committee identified the issues below as 
significant in the context of the 2016 financial 
statements. The Committee considers these 
areas to be significant taking into account the 
level of materiality and the degree of 
judgement exercised by management. The 
Committee has debated these issues in detail 
to ensure that the approaches taken were 
appropriate.

82  Petropavlovsk Annual Report 2016    

Issue

Committee action

Conclusion

Following careful review the 
Committee has a reasonable 
expectation, after taking into 
account the above mentioned 
factors, that the Group will 
have sufficient working capital 
liquidity to continue in 
operational existence for the 
foreseeable future and 
accordingly, the going concern 
basis is the appropriate basis 
of preparation for the 2016 
financial statements. The 
Committee has advised the 
Board accordingly.

The going concern assumption
(see note 2.1 to the financial statements)

The key judgement for the Committee for the 2016 
financial statements related to the appropriateness of 
the basis of accounting.

The Directors perform an assessment of the 
Company’s ability to continue as a going concern at 
the end of each reporting period. The period of the 
assessment covers at least twelve months from the 
date of signing of the financial statements. As the 
Company has guaranteed the outstanding amounts 
that IRC owes to ICBC under the Project Finance 
Facility (US$234 million as at 31 December 2016), the 
assessment of whether there is any material 
uncertainty that IRC will be able to repay this facility 
as it falls due is a key element of the Group’s overall 
going concern assessment.

Following the successful completion of the Bank 
Debt Refinancing, the Group is satisfied that it has 
sufficient headroom under a base case scenario for 
the period to May 2018 and expects to comply with 
related financial covenants. However, the Group’s 
projections under a reasonable downside scenario 
for the period to May 2018 indicate that, unless 
mitigating actions can be taken including accessing 
deposits not currently in the Group mining plan, there 
will be insufficient liquidity and non-compliance with 
certain financial covenants. In the event that a debt 
repayment is missed or financial covenant 
requirements are not met, this would result in events 
of default which, through cross defaults and cross 
accelerations, could cause all other of the Group’s 
debt arrangements to become repayable on 
demand.

In addition to the twelve month going concern 
consideration the Directors assessed the Company’s 
prospects over the longer term, specifically 
addressing a period of three years as part of the 
overall viability statement. The viability statement can 
be found in the Directors’ Report on page 109.

The Committee has addressed this matter through:

 – Reviewing a paper from management on the going 

concern assessment, challenging the key 
assumptions used for both the base case and the 
reasonable downside scenarios, in particular in 
relation to production, gold price and the Russian 
Rouble US Dollar exchange rate.

 – Considering the mitigating actions proposed by 

management in the event of a reasonable 
downside scenario. This included a report from the 
Group Chief Executive, based on recent detailed 
exploration results, on the likelihood of the Group 
being able to access identified deposits which are 
not currently in the Group’s mining plan.

 – With regards to IRC noting that:

 – two repayment instalments, originally due for 
payment on 20 June 2017 and 20 December 
2017 by IRC under the Project Finance Facility in 
an aggregate amount of US$42.5 million have 
been rescheduled evenly into five subsequent 
semi annual repayment instalments from 20 
June 2018 to 20 June 2020 inclusive. The next 
principal repayment under the Project Finance 
Facility is therefore due on 20 June 2018.

 – ICBC has agreed to grant a waiver of the 
financial covenants in the Project Finance 
Facility until 31 December 2017. 

 – IRC’s accounts for the year ended 31 December 

2016 as audited by Deloitte Hong Kong are 
unqualified.

 – In December 2016 IRC completed a US$25 
million equity fund raising from a new core 
investor. 

 – The development of K&S is advanced with full 
scale commercial production anticipated in 
H2 2017.

 – The iron ore price increased significantly during 

2016 and the beginning of 2017.

  Petropavlovsk Annual Report 2016  83

GovernanceFinancial statementsStrategic reportAudit Committee Report   continued

Issue

Committee action

Conclusion

Carrying value of mining assets 
(see note 12 to the financial statements)

The carrying value of the Group’s mining assets 
which includes the tangible assets attributable to the 
gold mining projects and the supporting in house 
service companies remains particularly sensitive to 
the forecast long term gold price, the Russian Rouble 
US Dollar exchange rate, and the forecast future 
cash flows for Pioneer and Malomir which assume 
the POX Hub’s completion. Consequently, the 
assessment of the carrying value of the Group’s 
mining assets and whether an impairment or reversal 
of impairment is necessary requires significant 
judgement.

The recoverability of gold in circuit inventory
Inventory is required to be carried at the lower of its 
cost and net realisable value. The measurement and 
valuation of gold in circuit included in inventory is 
complex and there is a risk that the total value of gold 
in circuit held on the balance sheet at 31 December 
2016 is not fully recoverable.

(Gold in circuit volume: 2016:91koz, 2015:75koz; 
monetary value: 2016: US$71 million: 2015: 
US$50 million).

The Committee has addressed this issue through:

 – Receiving reports from management outlining the 

basis for the assumptions used, including 
assumptions on gold price, the discount rate used 
for the gold mining projects and the Russian 
Rouble US Dollar exchange rate, and 
understanding and challenging these 
assumptions. The long term mine models which 
form the basis of the long term mining plan, are 
approved by the Board and, are used by 
management to perform the impairment 
assessment.

 – Reviewing the status of the construction of the POX 

Taking the above into account 
the Committee is satisfied  
with the thoroughness of the 
approach and judgements 
taken.

The Committee agreed with the 
conclusion of management that 
no impairment or reversal of the 
impairment recognised in 2013 
was required. No impairments 
or reversals of impairments 
have been recognised at 
31 December 2016. 

Taking these matters into 
account the Committee is 
satisfied with the thoroughness 
of the approach and 
judgements taken. 
Consequently the Committee 
concurs with management’s 
conclusion that the gold in 
circuit balance is recoverable.

Hub.

 – Reviewing the report prepared by Venmyn, mining 
experts, engaged by Deloitte to assist them in their 
assessment of this issue. As part of their review 
Venmyn again visited the Group’s principal mines. 

 – Discussing with the external auditor their view on 

the impairment testing procedure including the key 
assumptions used by management.

The Committee has addressed this issue through:

 – Enquiring of management the process used for 

extracting gold from the resin used in processing 
plants at Pioneer, Pokrovka and Albyn which led  
to an increase of gold in circuit volumes and 
understanding the countermeasures taken by 
management during the year to treat the resin  
and reduce gold in circuit levels. 

 – Reviewing a paper from the Chief Operating Officer 
detailing the technical reasons for this matter and 
the steps and actions taken by management to 
recover the gold including the recent 
commissioning of an acid alkali treatment 
installation for resin at Pokrovskiy mine.

 – Discussing with the external auditor the work 

undertaken by: i) Venmyn on their assessment of 
the reasonableness of the Group’s gold in circuit 
levels ii) Deloitte CIS, who attended stock counts at 
key operating locations and reconciled the gold in 
circuit levels to the production and sales data and 
iii) discussing with management the monitoring 
process for tailings in respect of any loss of gold. In 
addition the Committee noted the work performed 
by Venmyn which confirmed that the loss of gold in 
circuit to the tailings dams in immaterial.

 – A meeting by the Audit Committee Chairman 

with Venmyn.

84  Petropavlovsk Annual Report 2016    

Assurance – financial and internal 
controls and risk management
The Committee operates within the following 
assurance framework established by the 
Board. The Board has delegated authority  
to the HSE and Executive Committees in 
addition to the Audit Committee, details of 
which are as follows.

 – The Board (which receives advice from  

the Audit, HSE and Executive Committees) 
has overall responsibility for the system  
of internal control and risk management  
in the Group. The Committee reviews the 
Company’s financial and other internal 
controls. In addition, as part of the Board’s 
review of the effectiveness of the Group’s 
system of internal control the Committee is 
working with internal audit to broaden its 
remit and expand its focus on key risks  
and controls. The Committee has also 
considered and reviewed the Group’s 
financial risks and the mitigating action 
being taken to address these and has 
reported its findings to the Board. The 
system of controls is designed to manage, 
but may not eliminate, the risks of failure to 
achieve the Group’s objectives. Oversight  
is provided by the Executive Committee, 
which meets regularly to review the results 
of the Group’s operations. The Board 
considers the internal controls of the Group 
to have operated effectively throughout 
2016 and up to the date of this report

 – For IRC, Petropavlovsk operates controls 
over the inclusion of its financial data but 
places reliance upon the systems of internal 
control operating within IRC and the 
obligations upon IRC’s Board relating  
to the effectiveness of its own systems. 
IRC ceased to be a subsidiary of the 
Company and became an associate  
on 7 August 2015.

External auditor
Deloitte was appointed as auditor to the 
Company in 2009 following the Company’s 
listing on the main market. 

The Committee has evaluated the 
effectiveness of the external auditor and as 
part of this assessment, has considered:

 – Deloitte’s fulfilment of the agreed audit  

plan for the year ending 31 December 2015, 
the quality and robustness of their audit, 
identification of and response to areas of 
risk and the experience and expertise of the 
audit team, including the lead audit partner

 – Deloitte’s proposed audit fee for the 2016 

interim and year end audits and after 
consideration recommending these  
to the Board for approval

 – The non-audit fees payable to Deloitte, 

having regard to the policy on the provision 
of non-audit services

 – Deloitte’s publication entitled ‘Briefing  

on audit matters’ published in June 2016 
which explains the key concepts behind the 
Deloitte Audit methodology including audit 
objectives and materiality

 – Deloitte’s ‘2015 Audit Transparency Report’ 
in respect of the year ended 31 May 2016. 
This sets out Deloitte’s approach to ensuring 
audit quality, robust governance and ethics, 
by reference to the Professional Oversight 
Board of the Financial Reporting Council

 – The confirmation from Deloitte that they 
remain independent and objective within 
the context of applicable professional 
standards

 – The deep knowledge of the Company 

which enhances Deloitte’s ability to perform 
as external auditor and the proven stability 
that is gained from their continued 
engagement

 – In addition Committee members completed 
questionnaires to individually assess the 
performance of Deloitte the results of  
which were discussed at the March 2017 
Committee meeting.

As a result of the above actions, the 
Committee determined that Deloitte  
remains effective in its role as external auditor. 
The Committee has therefore recommended 
to the Board that Deloitte be appointed as 
external auditor for a further year and a 
resolution will be proposed to this effect  
at the 2017 Annual General Meeting.

Under the new provisions on audit tendering, 
the Committee will be required to tender the 
audit prior to 2019 but does not consider it 
necessary to undertake a tender process  
for the Group’s external auditor at the current 
time, particularly given the change of lead 
audit partner in 2014, however this will be  
kept under review. Until a decision is made  
to tender the audit the Committee will 
continue to evaluate the performance of 
Deloitte, as the Company’s external auditor 
each year. 

Non-audit services
The majority of non-audit fees paid to Deloitte 
were in respect of their work as reporting 
accountants on the proposed acquisition  
of Amur Zoloto LLC and the proposed joint 
venture with GMD Gold. As explained in this 
Annual Report neither transaction is 
proceeding. Deloitte’s appointment as 
reporting accountant on both of these 
transactions was in accordance with the 
Company’s policy on the provision of audit 
and non-audit services, a copy of which can 
be located on the Company’s website or 
obtained from the Company Secretary. 
The Committee approved the appointment 
on the basis that it was in accordance with the 
Company’s policy and that Deloitte would be 
the most appropriate firm to prepare the 
requisite working capital report within the time 
available and for a reasonable fee given their 
detailed knowledge of the Group, including 
IRC, of whom Deloitte Hong Kong is the 
external auditor. This work is typically 
performed by a company’s external auditor. 
In addition the non-audit services were 
provided by a separate team from the audit 
engagement team. Deloitte has confirmed to 
the Committee that there are no 
inconsistencies between APB Ethical 
Standards for Auditors and the Company’s 
policy for the supply of non-audit services or 
that there has been any apparent breach of 
the Company’s policy. Accordingly, in the 
opinion of the Committee, the independence 
and objectivity of Deloitte as external auditor 
to the Company, has not been impaired by 
their work in this respect.

A breakdown of audit and non-audit fees paid 
in 2016 is set out in note 7 on page 139 of this 
Annual Report.

  Petropavlovsk Annual Report 2016  85

GovernanceFinancial statementsStrategic reportAudit Committee Report   continued

Risk management
The Company has adopted a formal risk 
management framework with the Board 
having ultimate responsibility for setting  
the Group’s risk appetite and the Executive 
Committee having responsibility for on going 
risk review and management. The Committee 
retains responsibility for reviewing financial 
risks and reporting its findings and 
recommendations to the Board. The Risks  
to Our Performance section, which has been 
reviewed by the Audit Committee, summaries 
the risk management framework together with 
details of the principal risks of the Group and is 
on pages 21 to 33 of this Annual Report. 

Overview
As a result of the Committee’s work during the 
year, the Committee has concluded that it has 
acted in accordance with its terms of reference.

Some key features of the internal control 
system, not detailed above, are:

 – A defined management structure with clear 
accountabilities. There is a clear defined 
delegation of authorities, which covers all 
expenditure

 – Board approval of a detailed annual budget, 

with monthly re forecasts being made 
subsequently

 – Formal review by the Executive Committee 

of detailed management accounts including 
variance analysis against the approved 
annual budget, a copy of which is provided 
to the Board following this review

 – The Group has a detailed procurement 
policy and a centralised procurement 
function based in Moscow. The cost of the 
centralised purchases is c.75% of the 
Group’s total purchases with lower value 
orders dealt with locally in Blagoveshchensk. 
This system provides strengthening 
purchasing power and ensures strong 
controls are in place. There is appropriate 
segregation of duties throughout the Group, 
in particular separating the purchasing and 
ordering function from the processing and 
payments function. In addition there is a 
documentation and tracking process for 
purchase items for control purposes 
including to prevent theft

 – There is a special procurement process 
with a separate budget and expenditure 
schedule for the construction of the POX 
Hub. This is monitored with expenditure 
approved by the Chief Executive Officer, 
Chief Financial Officer and Chief Operating 
Officer based on the approved budget

 – There is a centrally directed treasury 

function which manages the Company’s 
cash and debt on a daily basis

 – Specific approval procedures have been 

established for approval of all related party 
transactions. A Committee of independent 
Non-Executive Directors approves all 
significant related party transactions as 
appropriate and a schedule of all of these 
transactions is presented to the Board for 
formal approval.

86  Petropavlovsk Annual Report 2016    

Directors’ Remuneration Report 

Annual statement from the Chairman  
of the Remuneration Committee (the “Committee”)

The Committee continued to align the 
implementation of its policy with the Group’s 
focus on financial discipline and its strategic 
objectives to (i) develop the underground 
mining operations and (ii) complete the 
construction of the Pressure Oxidation Hub, 
both of which are critical to the future success 
of the Company.

Remuneration highlights:
 – No salary increases were awarded to the 
Chairman or the Executive Directors for 
the year commencing 1 January 2016

 – Salary increase of c.1.3% awarded to  
the Chief Financial Officer for the year 
commencing 1 January 2017 with no salary 
increase proposed for the Chairman 
or Chief Executive Officer

 – Non-Executive Directors’ fees unchanged 

for 2017

 – Performance against targets for 2016, 

particularly relating to the satisfaction of 
specific strategic objectives, resulted in a 
bonus payable of 20% of salary; 50% of 
the bonus will be awarded in the form of 
a Deferred Bonus Award, and 50% will 
be paid in cash

 – No awards were granted under the Long 

term Incentive Plan (‘LTIP’) during 2016. The 
Committee currently proposes to grant 
awards following the publication of the 
Company’s 2017 interim results, and 
intends to consult with major shareholders 
on the proposed performance conditions

 – Best practice changes proposed to the 

Company’s Remuneration Policy:

 – Introduction of two year post-vesting 

holding period for LTIP awards from 2017 
onwards

 – Strengthening of malus and clawback 

provisions

 – Reduction of bonus payable for 

achieving target from 60% to 50%  
of maximum.

Dear shareholder

Introduction
On behalf of the Board, I am pleased to 
present the Directors’ Remuneration Report 
for the year ended 31 December 2016.

This report is divided into three parts: the Annual 
Statement, the Remuneration Policy and the 
Annual Report on Remuneration. This year 
we will be asking our shareholders to approve 
a new Remuneration Policy for Executive 
Directors at the Annual General Meeting 

(‘AGM’). The background to, and the reasons 
for, the proposed changes are set out below.

taking, and incentive opportunities that are 
fair.

Review of Remuneration policy
Our current Policy was approved by 
shareholders at the 2014 AGM, receiving 
over 98.5% support, and will expire at the 
2017 AGM. Therefore the Committee has 
conducted a review of the current Policy to 
ensure that it continues to meet our aims, 
which are principally to retain and motivate 
high calibre executives and to attract new 
talent as required, with pay outcomes linked 
to performance against our strategic 
objectives.

In particular, the Committee wishes to ensure 
that the Policy supports the Group’s strategic 
goals of progressing the underground mining 
project, and completing the construction of 
the pressure oxidation hub which will unlock 
the value embedded within the Group’s 4Moz 
reserve of refractory ore base from 2018/19, 
resulting in the deleveraging of the Company. 
To meet these strategic goals, the Company 
needs to retain its highly skilled and 
experienced Executive team.

During our review we have been mindful of 
developments in investor sentiment on 
remuneration best practice since the current 
Policy was approved and, to the extent that 
they have not already been adopted, we are 
seeking to include such changes in our 
revised Policy as we consider appropriate.

In concluding its review, the Committee 
considers that on the whole the current Policy 
is fit for purpose, well aligned with strategy, 
and reflects the market capitalisation of 
the Company whilst acknowledging the 
complexity of the Group. The proposed 2017 
Policy therefore remains broadly unchanged 
from the 2014 Policy, except for a number of 
minor amendments to reflect evolving best 
practice changes, as follows:

 – Introduction of a two year post-vesting 
holding period for awards made under 
the LTIP from 2017 onwards, to further 
strengthen the alignment between the 
Executive team and shareholders 

 – Strengthening of malus and clawback 

provisions to provide appropriate 
safeguards for shareholders

 – Reduction of the bonus payable for 

achieving target from 60% to 50% of 
maximum.

The Committee is satisfied that the revised 
Remuneration Policy will provide a structure 
that is aligned with the Group’s strategic 
objectives without encouraging undue risk 

Remuneration decisions in 2016
Annual bonus
For 2016, the annual bonus performance 
conditions were strongly linked to the Group’s 
strategic objectives and its continued focus 
on financial discipline. 60% of the bonus 
was linked to the achievement of strategic 
objectives including in relation to the progress 
of the underground mining project and the 
construction of the POX Hub, the success of 
these projects being critical to the future of the 
Group. 10% related to each of production and 
reduction in both net debt and average total 
cash costs. Given the inherent health and 
safety risks within our business, 10% of the 
bonus was based on a Lost Time Injury 
Frequency rate target, and additionally a 
health and safety underpin applied to 
bonus payout.

Based on the significant progress made on 
the underground mining project and on the 
construction of the POX Hub, the Committee 
has awarded an annual bonus of 20% of 
salary for the Executive Directors and 
members of the Executive Committee. In 
determining the bonus, the Committee has 
also taken into consideration the health and 
safety performance of the Group during the 
year. Further information is provided on page 
19 of this Annual Report.

After consultation with the Chairman, the 
Committee has determined that 50% (as 
opposed to the 25% as outlined in the 2015 
report) of the bonus payable will be awarded in 
the form of a Deferred Bonus Award, vesting 
after one year. This conserves the Group’s 
cash whilst acting as a retention tool, and 
further aligns the interests of the Executive 
team with those of our shareholders.

Other decisions
The Committee did not award any salary 
increases to the Executive Directors in 2016. 
For 2017, the Committee awarded an 
increase of 1.3% to the Chief Financial Officer; 
no increases were awarded to the Chairman 
or the Chief Executive Officer.

Implementation of the Remuneration 
Policy in 2017
In 2016, whilst recognising the significant 
achievements of the Executive team during 
the year, including the successful refinancing 
of the Group’s bank debt, the Committee 
noted the challenging external environment 
and the continuing need for financial 
stringency when making its decisions. 

  Petropavlovsk Annual Report 2016  87

GovernanceFinancial statementsStrategic reportDirectors’ Remuneration Report   continued

Therefore, as explained in the 2015 report, 
the Committee made a decision again not 
to make awards under the LTIP in 2016. 
The Committee reviewed this point in 2017, 
and is considering making awards this year 
following the publication of the Company’s 
2017 interim results, in order to improve 
shareholder alignment over the longer term, 
and to ensure the competitiveness of the 
remuneration package at a critical time for the 
Company. Prior to the granting of any such 
award the Committee intends to discuss this 
and the proposed performance conditions 
with our major shareholders.

Last year’s Annual Report on Remuneration 
received a vote in favour of 99.6% of votes 
cast at the 2016 AGM. We appreciate the 
continued support given by shareholders and 
the Committee hopes that both the decisions 
outlined in this Directors’ Remuneration 
Report and the revised Remuneration Policy 
will meet with the approval of shareholders.

I will be in attendance at the Company’s  
2017 AGM and will be pleased to discuss  
any remuneration matters with you. If you  
are unable to attend or have a query or 
comment prior to this date please email  
the Company Secretary, Amanda Whalley,  
at aw@petropavlovsk.net and we will  
be pleased to address any issues.

Andrew Vickerman
Remuneration Committee Chairman 
26 April 2017

Contents of this Report:
This report sets out details of the 
Remuneration Policy for Executive and 
Non-Executive Directors, describes the 
implementation of that Policy and discloses 
the amounts paid relating to the year ended 
31 December 2016.

The report complies with the provisions of 
the Companies Act 2006 and Schedule 8 
of The Large and Medium sized Companies 
and Groups (Accounts and Reports) 
(Amendment) Regulations 2013. The report 
has been prepared in line with the 
recommendations of the UK Corporate 
Governance Code and the requirements 
of the UKLA Listing Rules.

This revised Directors’ Remuneration Policy 
will be put to shareholders for approval in a 
binding vote at the AGM on 20 June 2017. 
If approved, the revised Policy will take effect 
from the date of the AGM. The Committee’s 
current intention is that the revised Policy will 
operate for the three year period to the AGM 
in 2020.

The Statement from the Chairman of the 
Remuneration Committee (set out on page 
87) and the Annual Report on Remuneration 
(set out on pages 96 to 103) will be subject to 
an advisory vote at the AGM.

Remuneration policy report

The Group’s Remuneration Policy is designed to provide remuneration packages to motivate and retain high calibre executives and to attract new 
talent as required. The Committee takes into account the principles of sound risk management when setting pay and takes action to ensure that 
the remuneration structure at Petropavlovsk does not encourage undue risk. The Policy is unaudited.

The table below summarises the main elements of the remuneration packages for the Executive Directors.

Remuneration element

Base salary

Purpose and link to strategy

To provide a market competitive level of guaranteed cash earnings in order to attract and retain 
high calibre Executive Directors to manage and execute the Board’s strategic plans.

Operation

The Committee reviews base salaries annually, taking into consideration any recommendation 
from the Company Chairman regarding the Executive Directors. Salary increases typically 
take effect from 1 January each year, unless there is a significant change in the responsibilities 
of the role.

Reviews take account of:

 –  The individual performance of the Executive Director, his or her experience, skills and potential;

 – The challenges intrinsic to that individual’s role;

 – Market competitiveness within the Group’s sector;

 – Salary increases across the wider employee population; and

 – The wider pay environment.

Whilst the obligation of the Company is in sterling, the Executive Directors may receive 
a proportion of their pay in Russian Roubles or US Dollars.

Maximum opportunity

There is no prescribed maximum salary.

It is generally expected that increases will be no higher than inflation, though the Committee has 
discretion to apply a higher increase in exceptional circumstances, e.g. material increase in role 
size or complexity, promotion, exceptional performance or any other factors the Committee 
considers relevant within the context of the Group’s overall policy.

88  Petropavlovsk Annual Report 2016    

Performance metrics

Not applicable, although the individual’s contribution and overall performance is one of the 
considerations in determining the level of any salary increase.

Remuneration element

Benefits

Purpose and link to strategy

To provide market competitive benefits in order to enable the Company to retain and attract high 
calibre Executive Directors to manage and execute the Board’s strategic plans.

Operation

Benefits may include (but are not limited to):

Maximum opportunity

Performance metrics

Remuneration element

Purpose and link to strategy

Operation

Maximum opportunity

Performance metrics

Remuneration element

Purpose and link to strategy

Operation

 – Private medical insurance for the individual and family;

 – Life assurance up to 4x salary, subject to underwriting; 

 – Ill health income protection; and

 – Travel insurance whilst on Company business.

The cost of these benefits to the Company is dependent upon market rates and availability of the 
respective benefits.

Not applicable.

Pension

To provide market competitive pension benefits in line with the wider workforce whilst ensuring 
no undefined liability for the Company.

All Executive Directors receive contributions from the Company into a personal pension plan or 
similar savings vehicle with the exception of Mr Hambro and Dr Maslovskiy, who do not receive 
pension benefits.

A Company contribution of up to 12.5% of salary, depending on length of service, is made to a 
personal pension arrangement with a minimum contribution from the Executive Directors of 3%. 
Cash in lieu of pension may also be made by way of a salary supplement, or a combination of 
both. These arrangements depend on the individual circumstance and residence of the 
Executive Director concerned.

Not applicable.

Annual Bonus

To ensure a focus on and provide a financial incentive for the delivery of the annual budget and 
other short term financial and strategic imperatives.

Annual performance targets are set by the Committee at the beginning of the year, with the 
bonus payable determined by the Committee after the year end, based on achievement against 
pre-determined targets.

Bonus payments, in part or in full, may be awarded in the form of Deferred Bonus Awards, 
i.e. deferred in shares which vest after one year or longer. The Committee retains the discretion 
to allow dividends (or equivalent) to accrue over the vesting period in respect of the awards 
that vest.

Malus and clawback provisions may be applied for up to a period of two years post-payment 
in exceptional circumstances, including but not limited to material misconduct, material 
misstatement of the results, a calculation error and/or poor information when calculating 
the reward outcome.

Maximum opportunity

Maximum bonus opportunity is 100% of salary.

For target level performance, the bonus earned is 50% of maximum.

  Petropavlovsk Annual Report 2016  89

GovernanceFinancial statementsStrategic reportDirectors’ Remuneration Report   continued

Performance metrics

Performance is assessed against a range of strategically important measures which may vary 
each year depending upon the annual priorities of the Group.

100% of the bonus is currently linked to the achievement of Group bonus objectives. These are 
set by the Committee and may include measures such as:

 –  Health and safety

 – Annual gold production

 – Total cash costs

 – All-in sustaining costs

 – Net debt

 – Free cashflow

 – Delivery of capital expenditure projects on time and within budget

 – Exploration success

Details of the measures applicable for the financial year under review are provided in the Annual 
Report on Remuneration.

The bonus scheme is not a contractual entitlement and the bonus is payable at the discretion 
of and subject to the approval of the Remuneration Committee. The Committee may take into 
consideration the overall relative success of the Group when adjudicating bonus payments. 
The Committee may also include a discretionary underpin in the annual bonus plan to capture 
material adverse events, e.g. material events relating to health and safety.

Remuneration element

Long term Incentive Plan (“LTIP”)

Purpose and link to strategy

Operation

Maximum opportunity

Performance metrics

90  Petropavlovsk Annual Report 2016    

To reinforce effective risk management by aligning Executive Directors’ interests with the long 
term interests of shareholders through regular awards of performance shares vesting only on 
the satisfaction of challenging long term performance conditions.

Awards of performance shares are made which are based on performance over a minimum 
of three years. Awards vest on no earlier than the third anniversary of grant subject to (i) the 
satisfaction of performance targets and (ii) continued service. There is no opportunity to retest 
the performance conditions. 

The Committee retains the discretion to allow dividends (or equivalent) to accrue over the vesting 
period in respect of the awards that vest.

A two year post-vesting holding period will apply to awards granted in 2017 and subsequent 
years. For these awards, vested shares may not be sold during the holding period except to 
cover tax liabilities.

The maximum annual award is 100% of salary. However, in exceptional circumstances, such 
as to facilitate the recruitment of an external hire, this may be exceeded to a maximum of 200% 
of salary.

Threshold performance will result in vesting of no more than 30% of the award.

The Committee will regularly review the performance conditions and targets to ensure that they are 
aligned to the Group’s strategy and that they are sufficiently challenging. The relevant metrics and 
the respective weightings may vary each year based upon the Company’s strategic priorities.

Details of the measures, weightings and performance targets used for specific LTIP grants are 
included in the Annual Report on Remuneration as relevant.

The Committee may scale back the level of vesting of an award if it considers underlying 
operational or financial performance over the performance period has been significantly worse 
than the level of vesting would otherwise indicate.

Malus and clawback provisions may be applied for up to a period of two years post-vesting 
in exceptional circumstances, including but not limited to material misconduct, material 
misstatement of the results, a calculation error and/or poor information when calculating the 
reward outcome.

Shareholding guidelines
There is no formal requirement for Executive 
Directors to own shares in the Company. 
However, Mr Hambro and Dr Maslovskiy 
as founding shareholders and having 
participated as underwriters in the rights  
issue in March 2015, have an interest, 
together with their associates, in 4.64% and 
5.81% of the voting rights over ordinary shares 
in the Company respectively. In value terms, 
the shareholding of both Mr Hambro  
and Dr Maslovskiy currently equates  
to approximately 17 and 21 times their  
annual salaries respectively.

The Committee is mindful that, given the 
significant shareholdings of Mr Hambro and 
Dr Maslovskiy, the introduction of minimum 
shareholding guidelines for Executive 
Directors will only have an impact on the  
Chief Financial Officer at this time. Given that 
there have been no LTIP awards for five years 
the Committee does not consider that the 
introduction of shareholding guidelines 
at this time would be equitable.

The Committee will continue to monitor 
market trends with respect to minimum 
shareholding guidelines for the Executive 
Directors and to keep this matter under 
review. 

The Committee reserves discretion to make 
minor changes to this Policy, which do not 
have a material advantage to Directors, to aid 
in its operation or implementation taking into 
account the interests of Shareholders but 
without the need to seek Shareholder 
approval. Any such changes will be reported 
to shareholders in the following year’s Annual 
Report on Remuneration.

Explanation of performance 
metrics chosen
Performance targets are set to be stretching 
and achievable, taking into account the 
Group’s strategic priorities and the 
environment within which the Group 
operates. In setting these performance 
targets the Committee will take into account 
a number of different reference points, which 
may include the Group’s long term mining 
plan, budgets and operational plans.

In respect of the annual bonus, strategic 
objectives are selected to ensure the delivery 
of the Company’s immediate policy objectives 
within the wider context of the Group’s long 
term strategy and corporate responsibilities. 
Other supporting annual objectives are 
selected to reflect key financial objectives of 
the Company, exploration success, delivery 
of specific investment projects and health and 
safety objectives, and to reward delivery 
against these.

The Committee retains the discretion to 
adjust the performance targets and measures 
where it considers it appropriate to do so (for 
example, to reflect changes in the structure of 
the business and to assess performance on 
a fair and consistent basis from year to year).

Remuneration Policy for other employees
A large percentage of the Group’s employees 
are based at the Group’s mines in the Amur 
Region in the Far East of Russia, whilst 
corporate, administrative and support 
staff are based at the Group’s offices in 
Blagoveshchensk, Moscow and London. 
The Board aims to ensure that employees 
are paid competitively within the region. 
Employees based at the Group’s mines 
receive base salary, shift and production 
related bonuses where applicable to their 
role, together with certain benefits.

Executive Committee members and selected 
employees in London, Moscow and 
Blagoveshchensk also participate in the 
Company’s annual bonus scheme. Executive 
Committee members and a number of senior 
employees, principally based within Russia, 
participated in the last LTIP cycle and received 
awards in 2011. It is the intention that any 
future LTIP awards will be granted to senior 
employees in order that they have the 
opportunity to share in the Group’s success, 
aligning their interest with those of the 
Executive Directors and shareholders. LTIP 
performance conditions are the same for all 
participants, while award sizes vary 
accordingly to level of seniority.

The key difference between Executive 
Directors’ and Executive Committee 
members’ remuneration and that of other 
employees is that, overall, the Remuneration 
Policy for these groups is more heavily 
weighted towards variable pay.

The Company does not have an all employee 
share ownership plan and does not consider 
that such a plan would be appropriate given 
that share ownership is not a common 
concept within Russia. The Board believes 
it more appropriate and beneficial to the 
general workforce to reward employees 
below senior employee level with bonus 
payments, based on the achievement of 
targets that are relevant to their positions 
and which they can influence.

  Petropavlovsk Annual Report 2016  91

GovernanceFinancial statementsStrategic reportDirectors’ Remuneration Report   continued

Executive Chairman (£)

Chief Executive Officer (£)

Chief Financial Officer (£)

1,965,000

1,965,000

1,179,000

1,179,000

1,255,225

655,000

655,000

775,225

455,225

Minimum

Target

Maximum

Minimum

Target

Maximum

Minimum

Target

Maximum

Salary

100%

Annual bonus 0%

LTIP

0%

55.5%

27.8%

16.7%

33.3%

33.3%

33.3%

Salary

100%

Annual bonus 0%

LTIP

0%

55.5%

27.8%

16.7%

33.3%

33.3%

33.3%

Salary

100%

Annual bonus 0%

LTIP

0%

58.7%

25.8%

15.5%

36.2%

31.9%

31.9%

Key

  LTIP  
  Annual bonus 
  Salary 

Assumptions:
Minimum = base salary, benefits 
and pension where applicable 
(i.e. fixed remuneration only) 

Target = fixed remuneration as 
above, plus annual bonus payout 
of 50% of maximum and LTIP 
threshold vesting of 30% of 
maximum award 

Maximum = fixed remuneration 
as above, plus full payout of 
annual bonus and LTIP 

When reviewing the graphs, it should be 
noted that they have been prepared on the 
Policy detailed above and ignore, for 
simplicity, the potential impact of future share 
price growth. The graphs have been prepared 
on the basis that an LTIP award will be 
granted during 2017.

Illustrations of pay for performance
Under the Company’s Policy a significant 
proportion of remuneration received by 
Executive Directors is dependent on Company 
performance. The graphs above illustrate how 
the total remuneration opportunities for the 
Executive Directors vary under three different 
performance scenarios: minimum, target and 
maximum. Potential remuneration 
opportunities are based on the proposed 
Remuneration Policy, applied to salaries as at 
1 January 2017: £655,000 for the Chairman, 
£655,000 for the Chief Executive Officer, and 
£400,000 for the Chief Financial Officer. 
The value of taxable benefits is based on the 
cost of supplying those benefits (as disclosed 
on page 97) for the year ending 31 December 
2016. The pension value for Mr Maruta is set at 
12.5% of basic salary.

92  Petropavlovsk Annual Report 2016    

 
 
Approach to recruitment and promotion
The Committee’s policy is to set pay for new 
Executive Directors within the existing 

Remuneration Policy in order to provide 
internal consistency. The Committee aims to 
ensure that the Company pays no more than 

is necessary to appoint individuals of an 
appropriate calibre.

Remuneration Element

Policy

Base salary

Benefits

Pensions

Annual bonus

Long term incentives

Salary for a new hire (or on promotion to Executive Director) would be set at a level sufficient to 
attract the best candidate available to fill the role, taking into account the Group’s position and 
strategy, market conditions and country of residence. The Committee would be prepared to set the 
salary of a new hire at a premium to those paid to the predecessor if this was necessary to attract 
and appoint a candidate with the requisite experience, seniority and calibre.

Benefits will be set in accordance with the Remuneration Policy. In addition, where necessary, 
the Committee may approve the payment of relocation expenses to facilitate recruitment. Flexibility 
is retained to pay for legal fees and other costs incurred by the individual in relation to his or her 
appointment.

A defined contribution or cash supplement up to 12.5% of salary subject to any particular 
considerations for a recruit who will be principally based outside of the UK.

The annual bonus will operate in line with the Remuneration Policy save that the Committee reserves 
the discretion to apply the maximum bonus payable of 200% of base salary for the appointment of 
an Executive Director in the first year of his or her appointment, if this is considered necessary to 
recruit the preferred candidate. Depending on the timing of the appointment and responsibilities 
of the appointee, it may be necessary to set different performance measures and targets initially.

LTIP awards will be granted in line with the Remuneration Policy. An award may (and would usually) 
be made upon appointment, subject to the Company not being prohibited from doing so. For an 
internal hire, existing awards would typically continue over their original vesting period and remain 
subject to their original terms; further awards may also be considered.

The maximum award for a new hire (or on promotion to Executive Director) is 200% of salary. 

Where an Executive Director is appointed 
through internal promotion, and the individual 
has contractual commitments made prior to 
his or her promotion to the Board, the 
Company will continue to honour these 
arrangements.

In addition, in the case of an external 
hire, the Committee may offer additional 
cash and/or share based elements 
when it considers these to be in the best 
interests of the Company (and therefore 
shareholders) to facilitate the buy out 
of value forfeit on joining the Company. 
Such payments would take account of 
remuneration relinquished when leaving a 
former employer and would reflect (as far 
as possible) the nature and time horizons 
attaching to that remuneration and the 
impact of any performance conditions. Any 
such buy out would not have a fair value 
higher than that of awards forfeited. The 
Committee will use the components of the 
Remuneration Policy when suitable but may 
also avail itself of Rule 9.4.2 of the Listing 
Rules. Shareholders will be informed of any 
such payments at the time of appointment.

  Petropavlovsk Annual Report 2016  93

GovernanceFinancial statementsStrategic reportDirectors’ Remuneration Report   continued

Executive Director service contracts
Executive Directors have service contracts 
with the Company which provide for a twelve 
month notice period, from both the Company 
and the Executive Director.

If the Company terminates the employment of 
an Executive Director with immediate effect, 
in the absence of a breach of the service 
agreement by the Director, a payment in lieu 
of notice may be made. This may include 
base salary, pension and benefits. Benefits 
may also include, but are not limited to, legal 
fees.

Executive Directors’ service contracts may be 
terminated without notice for certain events, 
such as gross misconduct. No payment or 
compensation beyond sums accrued up to 
the date of termination will be made if such an 
event occurs.

The Committee will retain discretion to 
approve new contractual arrangements with 
departing Executive Directors including 
settlement, confidentiality agreements, 
providing the provision of outplacement 
services, agreement of restrictive covenants 
and consultancy arrangements. The 

Committee will use its discretion in this 
respect sparingly and will enter into such 
arrangements only where the Committee 
believes that it is in the best interests of the 
Company and its shareholders to do so.

Dates of Executive Director service contracts 
are as follows:

Executive Director

Peter Hambro

Dr Pavel Maslovskiy

Andrey Maruta

Position 

Chairman

Chief Executive Officer

Chief Financial Officer

Effective date of contract

20 December 2001

5 November 2014

4 January 2011

Leaver and change of control provisions
The section below details how outstanding 
awards under incentive plans are treated in 
specific circumstances where the Executive 
Director’s employment has terminated or 
where there has been a change of control or 
similar transaction event. Final treatment 
remains subject to the Remuneration 
Committee’s discretion. When considering 
the use of discretion, the Committee reviews 
all potential incentive outcomes to ensure that 
any application of discretion is fair to both 
shareholders and participants.

Annual bonus 
Any annual bonus payment will be at the 
discretion of the Committee and the decision 
to award a bonus, in full or in part, will depend 
on a number of factors including the 
circumstances of the individual’s departure 
and their contribution to the Group during the 
bonus period in question. Any bonus amount 
paid will typically be pro-rated for time in 
service to termination and will, subject to 
performance, be paid at the usual time.

For good leavers (defined as death, injury, ill 
health, disability, retirement with agreement of 
the Committee, the employing company or 
business being sold out of the Group, or any 
other reason that the Committee determines 
appropriate), unvested Deferred Bonus 
Awards will vest on such date as determined 
by the Committee subject to a pro-rata 
reduction to reflect the proportion of the 
vesting period remaining. For all other leavers, 
awards will lapse.

On a change of control or similar transaction 
event, the Committee will assess the most 
appropriate treatment for the outstanding 
bonus period according to the 
circumstances. Deferred Share Awards 
will normally vest on the date of change of 
control subject to a pro-rata reduction to 
reflect the proportion of the vesting period 
remaining.

LTIP awards
For good leavers (defined as death, injury, ill 
health, disability, retirement with agreement of 
the Committee, the employing company or 
business being sold out of the Group, or any 
other reason that the Committee determines 
appropriate), unvested LTIP awards will 
vest on such date as determined by the 
Committee, subject to the achievement, 
or likely achievement, of any relevant 
performance conditions, with a pro-rata 
reduction to reflect the proportion of the 
vesting period remaining. For all other leavers, 
awards will lapse.

On a change of control or similar transaction 
event, unvested LTIP awards will typically vest 
on the date of the change of control, subject 
to the achievement or likely achievement of 
any relevant performance conditions with a 
pro-rata reduction to reflect the proportion of 
the vesting period remaining.

94  Petropavlovsk Annual Report 2016    

Remuneration Policy for Non-Executive Directors
Non-Executive Directors do not receive benefits from the Company and they are not eligible to receive pension contributions or participate in any 
bonus or incentive plan. Any reasonable expenses that they incur in the deliverance of their duties are reimbursed by the Company.

Details of the Policy on Non-Executive Director fees are set out in the table below.

Remuneration element

Fees

Purpose and link to strategy

To attract and retain high performing independent Non-Executive Directors by ensuring that 
fees are competitive and fair.

Operation

Maximum opportunity

Paid monthly in arrears and reviewed annually by the Board, after recommendation from the 
Chairman. Fee increases, if applicable are normally effective from 1 January.

There is no prescribed maximum annual increase although fees are determined by reference to 
time commitment and relevant benchmark market data. The Chairman of the Audit Committee, 
the Remuneration Committee and the Senior Independent Director may also receive an 
additional fee in recognition of the greater time commitment.

The aggregate annual fees are limited to £1.0 million under the Company’s Articles of 
Association. 

Performance metrics

Not applicable.

In recruiting a new Non-Executive Director, the Board will use the Policy as set out in the table above.

Non-Executive Directors are appointed for an initial term of three years and have formal letters of appointment setting out their duties and 
responsibilities. The appointment can be terminated by paying in lieu of the notice period with such pay being limited to the Non-Executive 
Director’s basic fees. Dates of Non-Executive Director appointment letters are as follows:

Name

Date of original appointment

Unexpired term as at 
31 December 2016

Date of appointment/last 
reappointment at AGM

Robert Jenkins

30 April 2015

Alexander Green

27 August 2015

Andrew Vickerman

22 October 2015

16 months

20 months

22 months

2016

2016

2016

Notice period

3 months

3 months 

3 months

Consideration of employment conditions 
elsewhere in the Company
The Committee may consider the level of 
salary increases that have been made to the 
Group’s employees when considering salary 
increases for the Executive Directors and 
members of the Executive Committee, whilst 
taking into consideration the diverse nature of 
the roles, responsibilities, and geographic 
locations and economies of the Group’s 
workforce. The Company does not currently 
actively consult with employees on executive 
remuneration. 

Further information on the Group’s 
employment policies are provided in the 
Environmental, Safety and Social Report  
on pages 34 and 35 of this Annual Report.

How the views of shareholders are taken 
into account
The Committee considers shareholder 
feedback and comment from corporate 
governance bodies received in relation to the 
AGM each year. The Committee will take 
these comments into consideration when 
reviewing Remuneration Policy. The 
Committee will consult with its major 
shareholders in advance of making any 
material changes to remuneration.

Policy on external directorships
Executive Directors may accept an external 
non-executive appointment with the approval 
of the Board. Any fees earned are retained by 
the executive. 

  Petropavlovsk Annual Report 2016  95

GovernanceFinancial statementsStrategic reportDirectors’ Remuneration Report   continued

Annual Report on Remuneration

The following section provides details of how the Company’s Remuneration Policy was implemented during the financial year ending 31 December 
2016, and how it will be implemented in 2017. Any information contained in this section of the report that is subject to audit is highlighted.

The Company Chairman attended parts of 
meetings in 2016 at the Committee 
Chairman’s invitation to provide advice on 
specific questions raised by the Committee. 
The Company Secretary attended each 
meeting as Secretary to the Committee. Key 
activities during the year included:

 – Review and approval of the 2015 Directors’ 

Remuneration Report

 – Review and approval of the 2015 annual 

bonus outcome

 – Review and approval of the 2016 annual 

bonus performance measures and targets

 – Review of Executive Directors’ total 
remuneration, including Executive 
Directors’ salaries for 2016

 – Review of the Company’s Remuneration 
Policy in the context of external market 
developments and best practice in 
remuneration.

External advisers
Kepler (part of the MMC group of companies), 
independent remuneration consultants 
appointed by the Committee after 
consultation with the Board, continued to act 
as the remuneration adviser to the Committee 
during the year. Kepler provides advice on 
remuneration for executives, benchmarking 
analysis, regular market and best practice 
updates, and support with drafting of the 
Directors’ Remuneration Report. In 2016, 
Kepler additionally provided support in 
reviewing the Remuneration Policy. Kepler 
is a signatory to the Code of Conduct for 
Remuneration Consultants of UK listed 
companies (which can be found at  
www.remunerationconsultantsgroup.com). 

Kepler reports directly to the Committee 
Chairman and neither Kepler nor any other 
part of the MMC group of companies 
provides any other services to the Company, 
with the exception that Marsh Ltd has been 
appointed as insurance broker for some of the 
Group’s UK and global policies and Mercer 
Marsh Benefits has been appointed as broker 
for the private medical healthcare scheme 
for the Company’s UK based employees. 
Kepler’s total fees for the provision of 
remuneration services to the Committee in 
2016 were £9,920 on the basis of time and 
materials, excluding expenses and VAT.

The Remuneration Committee
Role of the Committee
The principal role of the Committee is to 
recommend to the Board the framework and 
policy for the remuneration of the Company’s 
Chairman, the Executive Directors, any newly 
appointed Executive Director, the Company 
Secretary and members of the Executive 
Committee. In addition, and in consultation 
with the Chairman and Chief Executive Officer 
as appropriate, the Committee is responsible 
for reviewing the total individual remuneration 
package of each Executive Director 
and for reviewing annual proposals for 
the Executive Committee members. 
The Committee’s terms of reference are 
available on the Company’s website at  
www.petropavlovsk.net.

The members and activities  
of the Committee in 2016
The Committee comprises two Independent 
Non-Executive Directors, Andrew Vickerman, 
as Chairman, and Alexander Green. 
Sir Roderic Lyne retired as Chairman and as a 
member of the Committee on 28 June 2016. 
It is the intention that the additional 
Independent Non-Executive Director which 
the Company is in the process of appointing, 
will become a member of the Committee.

The Committee held two formal  
meetings during the year, with regular ongoing 
communication between Committee members 
to consider and finalise certain matters.

Shareholder voting at the 2016 AGM

The table below sets out the results of the vote on the 2015 Annual Report on Remuneration at the 2016 AGM:

For (including Chairman’s discretion)

Against

Total votes cast (excluding withheld votes but including third party discretion)

Votes withheld

Notes: 

The resolution to approve the 2015 remuneration report was passed on a poll.

A “Vote withheld” is not a vote in law and is not counted in the calculation of the votes “For” or “Against” a resolution.

Annual Report on Remuneration

Total number  
of votes
1,841,277,767
7,055,454
1,852,971,078
4,637,857

% of votes cast
99.62%
0.38%

96  Petropavlovsk Annual Report 2016    

Directors’ remuneration as a single figure (audited information) 
The table below reports the total remuneration receivable in respect of qualifying services by each Director during the financial periods ended 31 
December 2016 and 31 December 2015:

Executive Director
Peter Hambro

Pavel Maslovskiy

Andrey Maruta

Total
Total

Non-Executive Director
Robert Jenkins (c)

Alexander Green (d)

Andrew Vickerman (e)

Sir Roderic Lyne (f)

Total
Total

Year

Salary & fees

Taxable Benefit(a)

Annual Bonus(b)

Pension

Single Figure 
Remuneration 
Total £

Single Figure 
Remuneration  
Total US$

2016

2015

2016

2015

2016

2015

2016

2015

2016

2015

2016

2015

2016

2015

2016

2015

2016

2015

655,000
655,000
655,000
655,000
395,000
395,000
1,705,000
1,705,000

87,500
56,667
75,000
25,865
75,000
12,500
37,500
80,667
275,000
175,699

–
–
 –
 –
 12,958
2,133
12,958
2,133

131,000
–
131,000
–
79,000
–
341,000
–

–
–
–
–
–
–
–
–
–
–

–
–
–
–
–
–
–
–
–
–

–
–
–
–
49,375
49,375
49,375
49,375

–
–
–
–
–
–
–
–
–
–

786,000
655,000
786,000
655,000
536,333
446,508
2,108,333
1,776,508

87,500
56,667
75,000
25,865
75,000
12,500
37,500
80,667
275,000
175,699

1,065,030
1,002,150
1,065,030
1,002,150
726,731
683,158
2,856,791
2,687,408

118,562
86,700
101,625
39,574
101,625
19,125
50,813
123,420
372,625
268,819

(a)  Benefits are in respect of private medical insurance for the Director, their spouse and any children under the age of 18 years of age and pay in lieu of holiday entitlement.

(b) Value of cash bonuses and Deferred Bonus Awards awarded in respect of the corresponding performance year. For the year ended 31 December 2016, the bonus payable will be paid 50% in cash with the 

remaining 50% payable as a Deferred Bonus Award under the Company’s LTIP.

(c)  Mr Robert Jenkins was appointed as a Non-Executive Director of the Company on 30 April 2015. During 2016, Mr Jenkins received additional payments in respect of his chairmanship of the Audit Committee 

and his appointment as Senior Independent Non-Executive Director.

(d) Mr Alexander Green was appointed as a Non-Executive Director of the Company on 27 August 2015.

(e)  Mr Andrew Vickerman was appointed as a Non-Executive Director of the Company on 22 October 2015.

(f)  Sir Roderic Lyne retired as a Non-Executive Director of the Company at the conclusion of the Company’s 2016 AGM held on 28 June 2016.

(g) Rates of exchange used: 2016: £0.738:US$1, 2015: £0.65:US$1 (average exchange rate throughout the year).

  Petropavlovsk Annual Report 2016  97

GovernanceFinancial statementsStrategic report 
 
Directors’ Remuneration Report   continued

Implementation of the Remuneration Policy in 2016

Executive Directors
Salary
No salary increases were awarded to the Executive Directors during the year, recognising the low rate of inflation in the UK and the ongoing cost 
reduction programme in the lower gold price environment. 

Pension
The Group makes contributions into a personal pension scheme on behalf of Mr Andrey Maruta, Chief Financial Officer. A rate of 12.5% of base 
salary (paid partly as a pension contribution and partly as a taxable cash supplement) is payable in return for a minimum personal contribution 
of 3% on pension payments. Any cash payment is also made to Mr Maruta net of an amount equivalent to the amount of employer’s national 
insurance contributions payable on the cash payment such that the Company is not disadvantaged by making the payment in cash rather than 
as a pension payment which is not subject to employer’s national insurance. For the period ended 31 December 2016, the Group’s pension 
contribution for Mr Maruta was £49,375. Mr Hambro and Dr Maslovskiy received no payment from the Company in respect of pension 
entitlements.

Annual bonus
For 2016, the annual bonus was based 60% on strategic objectives, 10% on production, 10% on each of reduction in net debt and average 
total cash costs, and 10% on health and safety. The maximum bonus opportunity was 100% of salary, and target bonus was 60% of salary. 
The performance targets and actual achievement during the year, and the resulting bonus outcome, are set out in the table below.

Objective
Total Group production
Total Cash Costs per oz
Net Debt
Health & Safety – LTIFR
Progression of underground mining project to 
allow production in 2017, within budget
Continuing construction of the POX Hub 
in H2 2016 or entering into a Joint Venture 
arrangement for the completion of the POX Hub
Transactional
Total
Bonus earned

Pay out  
for target 
performance  
(% of max)
6%
6%
6%
6%

Stretch target
500,000oz
450,000 ounces per annum – 16.2Mtpa of RIP capacity (4 x RIP plants)Optimal extraction from accessing our full asset base. Sustainable long term refractory and non-refractory production from the POX Hub and RIP plants respectively, with ongoing resource and production growth upside from high grade underground operations and highly prospective exploration prospects within the combined 3,600km² license holding.  –3 x open pit mines  –2 x underground mines –14.5Mtpa of RIP capacity (3x RIP plants) –500ktpa POX Hub processing refractory concentrate –Malomir and Pioneer combined 11.4Mtpa flotation capacity