FY2015 Annual Report · Golden Minerals Company
Sign in to download
Loading PDF…
UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
FORM 10-K

(Mark One)

(cid:95) ANNUAL REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES 

EXCHANGE ACT OF 1934

For the fiscal year ended December 31, 2015

OR

(cid:134) TRANSITION REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES 

EXCHANGE ACT OF 1934

For the transition period from          to         

Commission file number 1-13627
GOLDEN MINERALS COMPANY
(Exact Name of Registrant as Specified in its Charter)

DELAWARE
(State of Incorporation or Organization)

350 Indiana Street, Suite 800
Golden, Colorado
(Address of principal executive offices)

26-4413382
(I.R.S. Employer Identification No.)

80401
(Zip Code)

(303) 839-5060
(Registrant’s telephone number, including area code)

Securities registered pursuant to Section 12(b) of the Act:

Title of each class
Common Stock, $0.01 par value

Name of each exchange on which registered
NYSE MKT

Securities registered pursuant to Section 12(g) of the Act: None

Indicate by check mark if the registrant is a well-known seasoned issuer, as defined in Rule 405 of the Securities Act. Yes (cid:134)

No (cid:95)

Indicate by check mark if the registrant is not required to file reports pursuant to Section 13 or Section 15(d) of the Act. Yes (cid:134)

No (cid:95)

Indicate by check mark whether the registrant (1) has filed all reports required to be filed by Section 13 or 15(d) of the 
Securities Exchange Act of 1934 during the preceding 12 months (or for such shorter period that the registrant was required to file 
such reports), and (2) has been subject to such filing requirements for the past 90 days. Yes (cid:95) No (cid:134)

Indicate by check mark whether the registrant has submitted electronically and posted on its corporate Web site, if any, every 
Interactive Data File required to be submitted and posted pursuant to Rule 405 of Regulation S-T (§ 232.405 of this chapter) during 
the preceding 12 months (or for such shorter period that the registrant was required to submit and post such files). Yes (cid:95) No (cid:134)

Indicate by check mark if disclosure of delinquent filers pursuant to Item 405 of Regulation S-K is not contained herein, and 

will not be contained, to the best of registrant’s knowledge, in definitive proxy or information statements incorporated by reference in 
Part III of this Form 10-K or any amendment to this Form 10-K. (cid:134)

Indicate by check mark whether the registrant is a large accelerated filer, an accelerated filer, a non-accelerated filer, or a 

smaller reporting company. See the definitions of “large accelerated filer,” “accelerated filer” and “smaller reporting company” in 
Rule 12b-2 of the Exchange Act.

Large accelerated filer (cid:134)

Non-accelerated filer (cid:134)
Do not check if a (smaller reporting company)

Accelerated filer (cid:134)

Smaller reporting company (cid:95)

Indicate by check mark whether the registrant is a shell company (as defined in Rule 12b-2 of the Act). Yes (cid:134) No (cid:95)

Indicate by check mark whether the registrant has filed all documents and reports required to be filed by Section 12, 13, or 15(d) 

of the Securities Exchanges Act of 1934 subsequent to the distribution of securities under a plan confirmed by a court. Yes (cid:95) No (cid:134)

The aggregate market value of the voting and non-voting common equity held by non-affiliates as of June 30, 2015 was 
approximately $13,188,091, based on the closing price of the registrant’s common stock of $0.35 per share on the NYSE MKT on 
June 30, 2015. For the purpose of this calculation, the registrant has assumed that its affiliates as of June 30, 2015 included all 
directors and officers and one shareholder that held approximately 29.1% of its outstanding common stock. The number of shares of 
common stock outstanding on February 24, 2016 was 76,690,333.

DOCUMENTS INCORPORATED BY REFERENCE

Portions of the registrant’s Definitive Proxy Statement to be filed with the Securities and Exchange Commission pursuant to 

Regulation 14A in connection with the 2016 Annual Meeting of Stockholders are incorporated by reference in Part III of this annual 
report on Form 10-K.

References to “Golden Minerals, the “Company,” “our,” “we,” or “us” mean Golden Minerals Company, its predecessors 

and consolidated subsidiaries, or any one or more of them, as the context requires. Many of the terms used in our industry are 
technical in nature. We have included a glossary of some of these terms below.

FORWARD-LOOKING STATEMENTS

Some information contained in or incorporated by reference into this annual report on Form 10-K may contain forward-

looking statements and forward-looking information (collectively, “forward-looking statements”) within the meaning of the United 
States Private Securities Litigation Reform Act of 1995 and other applicable securities laws. We use the words “anticipate,”
“continue,” “likely,” “estimate,” “expect,” “may,” “could,” “will,” “project,” “should,” “believe” and similar expressions (including 
negative and grammatical variations) to identify forward-looking statements.  These statements include statements relating to our 
plans, expectations and assumptions concerning anticipated care and maintenance costs at the Velardeña Properties (defined below), 
expectations regarding the oxide plant lease including its duration and revenues, planned exploration of certain properties in Mexico 
and other planned exploration activities and the planned costs of exploration, anticipated 2016 expenditures, expected need for 
external financing, costs related to our El Quevar project and our exploration properties, and statements concerning our financial 
condition, business strategies and business and legal risks. Although we believe the expectations and assumptions reflected in those 
forward-looking statements are reasonable, we cannot assure you that these expectations and assumptions will prove to be correct. Our 
actual results could differ materially from those expressed or implied in these forward-looking statements as a result of various factors 
described in this annual report on Form 10-K, including:

(cid:120)

(cid:120)

(cid:120)

(cid:120)

(cid:120)

(cid:120)

(cid:120)

(cid:120)

(cid:120)

(cid:120)

(cid:120)

Higher than anticipated care and maintenance costs at the Velardeña Properties in Mexico or at El Quevar in 
Argentina;

Lower revenue than anticipated from the oxide lease, which could result from delays or problems at the third party’s 
mine or at the oxide plant, permitting problems at the third party’s mine or the oxide plant, delays in constructing 
additional tailings capacity at the oxide plant, earlier than expected termination of the lease or other causes;

Whether Sentient will convert the remaining principal and interest of the Sentient Loan (defined below) into our 
common stock or whether we will be required to pay the remaining principal and interest in cash and, if the latter, 
whether we will be able to raise the capital necessary to do so on terms acceptable to us or at all;

Continued decreases or insufficient increases in silver and gold prices;

Whether we are able to raise the necessary capital required to continue our business on terms acceptable to us or at 
all, and the likely negative effect of continued low silver and gold prices or unfavorable exploration results or;

Unfavorable results from exploration at the Santa Maria, San Luis del Cordero, Rodeo or other exploration 
properties and whether we will be able to advance these or other exploration properties;

Variations in the nature, quality and quantity of any mineral deposits that are or may be located at the Velardeña 
Properties or the Company’s exploration properties, changes in interpretations of geological information, and 
unfavorable results of metallurgical and other tests;

Whether we will be able to mine and sell minerals successfully or profitably at any of our current properties at 
current or future silver and gold prices and achieve our objective of becoming a mid-tier mining company;

Potential delays in our exploration activities or other activities to advance properties towards mining resulting from 
environmental consents or permitting delays or problems, accidents, problems with contractors, disputes under 
agreements related to exploration properties, unanticipated costs and other unexpected events;

Risks related to the El Quevar project in Argentina, including whether we will be able to find a joint venture partner 
to advance the project, the feasibility and economic viability and unexpected costs of maintaining the project;

Our ability to hire or retain key management and mining personnel necessary to successfully manage and grow our 
business;

2

(cid:120)

(cid:120)

(cid:120)

Economic and political events affecting the market prices for silver, gold, zinc, lead and other minerals which may 
be found on our exploration properties;

Political and economic instability in Mexico and Argentina and other countries in which we may conduct our 
business and future actions of any of these governments with respect to nationalization of natural resources or other 
changes in mining or taxation policies; and

The factors set forth under “Risk Factors” in Item 1A of this annual report on Form 10-K.

Many of these factors are beyond our ability to control or predict. Although we believe that the expectations reflected in our 

forward-looking statements are based on reasonable assumptions, such expectations may prove to be materially incorrect due to 
known and unknown risks and uncertainties. You should not unduly rely on any of our forward-looking statements. These statements 
speak only as of the date of this annual report on Form 10-K. Except as required by law, we are not obligated to publicly release any 
revisions to these forward-looking statements to reflect future events or developments. All subsequent written and oral forward-
looking statements attributable to us and persons acting on our behalf are qualified in their entirety by the cautionary statements 
contained in this section and elsewhere in this annual report on Form 10-K.

CAUTIONARY STATEMENT REGARDING MINERALIZED MATERIAL

“Mineralized material” as used in this annual report on Form 10-K, although permissible under the United States Securities 

and Exchange Commission’s (“SEC”) Industry Guide 7, does not indicate “reserves” by SEC standards. We cannot be certain that 
any deposits at the Velardeña Properties or any part of the Yaxtché deposit at the El Quevar project will ever be confirmed or 
converted into SEC Industry Guide 7 compliant “reserves”. Investors are cautioned not to assume that all or any part of the disclosed 
mineralized material estimates will ever be confirmed or converted into reserves or that mineralized material can be economically or 
legally extracted.

CONVERSION TABLE

In this annual report on Form 10-K, figures are presented in both United States standard and metric measurements. 

Conversion rates from United States standard measurement systems to metric and metric to United States standard measurement 
systems are provided in the table below. All currency references in this annual report on Form 10-K are to United States dollars, 
unless otherwise indicated.

U.S. Unit
1 acre
1 foot
1 mile
1 ounce (troy)
1 ton

Metric Measure

Metric Unit

0.4047 hectares
0.3048 meters
1.609 kilometers
31.103 grams
0.907 tonnes

1 hectare
1 meter
1 kilometer
1 gram
1 tonne

U.S. Measure

2.47 acres
3.28 feet
0.62 miles
0.032 ounces (troy)
1.102 tons

GLOSSARY OF SELECTED MINING TERMS

“Assay” means to test ores or minerals by chemical or other methods for the purpose of determining the amount of valuable 

metals contained.

“Base Metal” means a classification of metals usually considered to be of low value and higher chemical activity when 

compared with the precious metals (gold, silver, platinum, etc.). This nonspecific term generally refers to the high-volume, low-value 
metals copper, lead, tin, and zinc.

“Breccia” means rock consisting of fragments, more or less angular, in a matrix of finer-grained material or of cementing 

material.

“Calcareous Clastic” means sedimentary rock composed of siliciclastic particles usually of conglomerate, sand, or silt-size 

and cemented by calcium carbonate in the form of calcite.

“Claim” means a mining interest giving its holder the right to prospect, explore for and exploit minerals within a defined 

area.

3

“Concentrates” means the clean product of ore or metal separated from its containing rock or earth by froth flotation or other 

methods of mineral separation.

“Concession” means a grant or lease of a tract of land made by a government or other controlling authority in return for 

stipulated services or a promise that the land will be used for a specific purpose.

“Core Drill” means a rotary type of rock drill that cuts a core of rock and is recovered in long cylindrical sections, two 

centimeters or more in diameter.

“Deposit” means an informal term for an accumulation of minerals.

“Development Stage” means a project with an established resource, not in production, engaged in the process of additional 

studies preparing for completion of a feasibility study or for commercial extraction.

“Diorite” means a grey to dark grey intermediate intrusive igneous rock composed principally of plagioclase feldspar 

(typically andesine), biotite, hornblende, and/or pyroxene.

“Doré” means gold and silver bullion that remains in a cupelling furnace after the lead has been oxidized and skimmed off.

“Epithermal Calcite-Quartz” means deposits, typically occurring in veins, of calcite-quartz from hydrothermal fluids at 

shallow depths under conditions in the lower ranges of temperature and pressure.

“Euhedral” means a well-developed degree of which mineral grains show external crystal faces (fully crystal-faced).

“Exploration Stage” means a project that is not yet in either the Development Stage or Production Stage.

“Feasibility Study” means an engineering study designed to define the technical, economic, and legal viability of a mining 

project with a high degree of reliability.

“Flotation” means the separating of finely crushed minerals from one another by causing some to float in a froth and others 

to remain in suspension in the pulp. Oils and various chemicals are used to activate, make floatable, or depress the minerals.

“Formation” means a distinct layer of sedimentary rock of similar composition.

“Fracture System” means a set or group of contemporaneous fractures related by stress.

“Grade” means the metal content of ore, usually expressed in troy ounces per ton (2,000 pounds) or in grams per ton or 

metric tonnes which contain 2,204.6 pounds or 1,000 kilograms.

“Inferred Resource” means the part of a mineral resource for which quantity and grade or quality can be estimated on the 

basis of geological evidence and limited sampling and reasonably assumed, but not verified, geological and grade continuity. The 
estimate is based on limited information and sampling gathered through appropriate techniques from locations such as outcrops, 
trenches, pits, workings and drill holes.

“Laramide Orogeny” means a period of mountain building in western North America, which started in the Late Cretaceous 

age, 70 to 80 million years ago, and ended 35 to 55 million years ago.

“Mineralization” means the concentration of metals within a body of rock.

“Mineralized Material” means a mineralized body that has been defined by appropriate drilling and/or underground 

sampling to establish continuity and support an estimate of tonnage and an average grade of the selected metals.

“Mining” means the process of extraction and beneficiation of mineral reserves or mineral deposits to produce a marketable 

metal or mineral product. Exploration continues during the mining process and, in many cases, mineral reserves or mineral deposits 
are expanded during the life of the mine activities as the exploration potential of the deposit is realized.

“Monzodiorite” means coarse-grained igneous rock consisting of essential plagioclase feldspar, orthoclase feldspar, 

hornblende and biotite, with or without pyroxene, with plagioclase being the dominant feldspar making up 6% to 90% of the total

4

feldspar and varying from oligoclase to andesine in composition. The presence of the orthoclase feldspar distinguishes this rock from a 
diorite.

“National Instrument 43-101” or “NI 43-101” means the standards of disclosure for mineral projects prescribed by the 

Canadian Securities Administrators.

“Net Smelter Return Royalty” means a defined percentage of the gross revenue from a resource extraction operation, less a 

proportionate share of transportation, insurance, and processing costs.

“Open Pit” means a mine working or excavation open to the surface.

“Ore” means material containing minerals that can be economically extracted.

“Outcrop” means that part of a geologic formation or structure that appears at the surface of the earth.

“Oxide” means mineralized rock in which some of the original minerals have been oxidized (i.e., combined with oxygen).

“Precious Metal” means any of several relatively scarce and valuable metals, such as gold, silver, and the platinum-group 

metals.

“Preliminary Economic Assessment” or “PEA” means a study, other than a pre-Feasibility or Feasibility Study, that 

includes an economic analysis of the potential viability of mineral resources.

“Probable Mineral Reserves” means mineral reserves for which quantity and grade and/or quality are computed from 

information similar to that used for Proven Mineral Reserves, but the sites for inspection, sampling and measurement are farther apart 
or are otherwise less adequately spaced. The degree of assurance, although lower than that for Proven Mineral Reserves, is high 
enough to assume continuity between points of observation.

“Production Stage” means a project that is actively engaged in the process of extraction and beneficiation of mineral 

reserves or mineral deposits to produce a marketable metal or mineral product.

“Proven Mineral Reserves” means mineral reserves for which (a) quantity is computed from dimensions revealed in 

outcrops, trenches, workings or drill holes; grade and/or quality are computed from the results of detailed sampling and (b) the sites 
for inspection, sampling and measurement are spaced so closely and the geologic character is so well defined that size, shape, depth 
and mineral content of reserves are well established.

“Reclamation” means the process of returning land to another use after mining is completed.

“Recovery” means that portion of the metal contained in the ore that is successfully extracted by processing, expressed as a 

percentage.

“Mineral Reserves” means that part of a mineral deposit that could be economically and legally extracted or produced at the 

time of mineral reserve determination.

“Sampling” means selecting a fractional part of a mineral deposit for analysis.

“Sediment” means solid fragmental material that originates from weathering of rocks and is transported or deposited by air, 
water, or ice, or that accumulates by other natural agents, such as chemical precipitation from solution or secretion by organisms, and 
that forms in layers on the earth’s surface at ordinary temperatures in a loose, unconsolidated form.

“Sedimentary” means formed by the deposition of Sediment.

“Silver Equivalent” means silver and gold only, with gold converted to silver equivalents at a 70 to 1 ratio.

“Skarn” means a coarse-grained metamorphic rock formed by the contact metamorphism of carbonate rock often containing 

garnet, pyroxene epodite and wollastonnite.

“Stock” means discordant igneous intrusion having a surface exposure of less than 40 square miles.

5

“Sulfide” means a compound of sulfur and some other element.

“Tailings Pond” means a low-lying depression used to confine tailings, the prime function of which is to allow enough time 

for heavy metals to settle out or for cyanide to be destroyed before water is discharged into the local watershed.

“Tertiary” means the first period of the Cenozoic Era (after the Cretaceous of the Mesozoic Era and before the Quaternary) 

thought to have covered the span of time between 2 to 3 million years ago and 65 million years ago.

“Vein” means a fissure, fault or crack in a rock filled by minerals that have traveled upwards from some deep source.

“Waste” means rock lacking sufficient grade and/or other characteristics of Ore.

PART I

ITEMS 1 AND 2:  BUSINESS AND PROPERTIES

Overview

We are a mining company, and we own the Velardeña and Chicago precious metals mining properties and associated oxide 

and sulfide processing plants (the “Velardeña Properties”) in the State of Durango, Mexico, the El Quevar advanced exploration 
property in the province of Salta, Argentina, and a diversified portfolio of precious metals and other mineral exploration properties 
located primarily in or near historical precious metals producing regions of Mexico. The Velardeña Properties and the El Quevar 
advanced exploration property are our only material properties. Our management team is comprised of experienced mining 
professionals with extensive expertise in mineral exploration, mine construction and development and mine operations. Our principal 
offices are located in Golden, Colorado at 350 Indiana Street, Suite 800, Golden, CO 80401, and our registered office is the 
Corporation Trust Company, 1209 Orange Street, Wilmington, DE 19801. We also maintain an office at the Velardeña Properties in 
Mexico and exploration offices in Argentina and Mexico.

Due to continuing net operating losses, we suspended mining and sulfide processing activities at our Velardeña Properties in 
November 2015 in order to conserve the asset until we are able to develop mining and processing plans that at then current prices for 
silver and gold indicate a sustainable positive operating margin (defined as revenues less costs of sales) or we are able to locate, 
acquire and develop alternative mineral sources that could be economically mined and transported to the Velardeña Properties for 
processing.

In July 2015 we entered into a leasing agreement with Minera Hecla, S.A. de C.V. (“Hecla”), a Mexican corporation and 
wholly owned subsidiary of Hecla Mining Company, which for a monthly fixed fee and a variable tonnage fee will allow Hecla to 
process its own material through our oxide plant at the Velardeña Properties for a period of up to 30 months.  Hecla began processing 
material in mid-December 2015, and we expect to receive net cash under the lease of between $4.0 and $5.0 million in 2016.

We are primarily focused on evaluating and searching for mining opportunities in North America (including Mexico) with 

high precious metal grades and low development costs with near term prospects of mining, and particularly properties within 
reasonable haulage distances of our Velardeña Properties, which may include the Santa Maria Mine located in the Parral District in 
Chihuahua State, Mexico, the Santa Rosa vein located in the San Luis del Cordero District in Durango or the Rodeo property located 
west of the Velardeña Properties in Durango. We also are focused on continuing to advance certain exploration properties located 
primarily in Mexico and on holding our El Quevar advanced exploration property in Argentina until we can find a partner to further 
advance the project. We also continue to review strategic opportunities from time to time.

No Proven or Probable Mineral Reserves/Exploration Stage Company

We are considered an exploration stage company under SEC criteria since we have not demonstrated the existence of proven 

or probable mineral reserves at our Velardeña Properties or any of our other properties. In Industry Guide 7, the SEC defines a 
“reserve” as that part of a mineral deposit which could be economically and legally extracted or produced at the time of the reserve 
determination. Proven or probable mineral reserves are those reserves for which (a) quantity is computed and (b) the sites for 
inspection, sampling, and measurement are spaced so closely that the geologic character is defined and size, shape and depth of 
mineral content can be established (proven) or the sites are farther apart or are otherwise less adequately spaced but high enough to 
assume continuity between observation points (probable). Mineral Reserves cannot be considered proven or probable unless and until 
they are supported by a feasibility study, indicating that the mineral reserves have had the requisite geologic, technical and economic 
work performed and are economically and legally extractable.

6

Prior to suspending mining and processing at the Velardeña Properties in November 2015, we had revenues from the sale of 
silver, gold, lead and zinc products from the Velardeña and Chicago mines. We have not completed a feasibility study with regard to 
all or a portion of any of our properties to date. Any mineralized material discovered or extracted by us should not be considered 
proven or probable mineral reserves. As of December 31, 2015, none of our mineralized material met the definition of proven or 
probable mineral reserves. We expect to remain an exploration stage company for the foreseeable future, even though we were 
extracting and processing mineralized material. We will not exit the exploration stage until such time, if ever, that we demonstrate the 
existence of proven or probable mineral reserves that meet the guidelines under SEC Industry Guide 7.

Company History

We were incorporated in Delaware under the Delaware General Corporation Law in March 2009, and we are the successor to 

Apex Silver Mines Limited (“Apex Silver”) for purposes of reporting under the Securities Exchange Act of 1934, as amended (the 
“Exchange Act”). From March 2009 through September 2011, we focused on the advancement of our El Quevar silver project in 
Argentina. On September 2, 2011, we completed a business combination transaction with ECU Silver Mining Inc. (“ECU”) and now 
own the Velardeña and Chicago silver, gold and base metals mines located in the Velardeña mining district in the State of Durango, 
Mexico as further described under “—Velardeña Properties”. Since the business combination with ECU, we have focused primarily 
on the further advancement and improvement of the Velardeña Properties, as well as identifying and establishing other mining 
opportunities with near term prospects.

Corporate Structure

Golden Minerals Company, headquartered in Golden, Colorado, is the operating entity through which we conduct our 

business. Following our September 2, 2011 business combination, ECU became a wholly-owned subsidiary of Golden Minerals, and 
three of ECU’s wholly-owned Mexican subsidiaries hold the assets and rights associated with the Velardeña Properties. We have a 
number of other wholly-owned subsidiaries organized throughout the world, including in Mexico, Central America, South America, 
the Caribbean and Europe. We generally hold our exploration rights and properties through subsidiaries organized in the countries in 
which our rights and properties are located.

Our Competitive Strengths and Business Strategy

Our business strategy is to establish Golden Minerals as a mid-tier precious metals mining company focused in Mexico. We 

also review strategic opportunities from time to time.

Velardeña Properties.  Due to continuing net operating losses, we suspended mining and sulfide processing activities at the 

Velardeña Properties in November 2015 in order to conserve the future value of the asset. We have placed the mine and sulfide 
processing plant on care and maintenance to enable a re-start of either the mine or the mill. Prior to shutdown, we generated payable 
metals in 2015 totaling approximately 465,000 silver equivalent ounces (equivalents calculated at 70:1 silver to gold), including 
approximately 327,000 ounces of silver and 1,975 ounces of gold. In July 2015, we leased the oxide plant to a third party, which for a 
monthly fixed fee and a variable tonnage fee will allow the third party to process its own material through the plant for up to 30 
months.

El Quevar Project.  We continue to hold our El Quevar property on care and maintenance and to reduce holding costs until 

we can find a partner to fund further exploration.

Exploration Focus.  We are focused on evaluating and searching for mining opportunities in North America (including 

Mexico) with high precious metal grades and low development costs with near term prospects of mining, and particularly properties 
within reasonable haulage distances of our Velardeña Properties, which may include the Santa Maria Mine located in the Parral 
District in Chihuahua State, the Santa Rosa vein located in the San Luis del Cordero District in Durango or the Rodeo property located 
west of the Velardeña Properties in Durango. During 2015 we mined approximately 3,000 tonnes of material from the Santa Maria 
mine from a high grade portion of a mineralized vein as bulk samples, generating approximately 113 tonnes of concentrates containing 
about 47,000 ounces of silver and 80 ounces of gold.  In November 2015, we acquired the mining rights for the Santa Rosa vein in the 
San Luis del Cordero Project.  We started a drilling program in February 2016 to test extensions of the Santa Rosa vein on strike and 
to complete infill drilling.   We also plan to drill at the Rodeo property in 2016 or early 2017 to explore for extensions of the near-
surface gold mineralization that was identified by previous exploration. During 2016 we plan to focus our exploration efforts primarily 
on the Santa Maria mine and the Santa Rosa vein, and exploration on certain other properties. We expect our expenditures for the 
exploration program in 2016 to be approximately $2.2 million.

7

Experienced Management Team.  We are led by a team of mining professionals with approximately 60 years of combined 

experience in exploration, project development, construction and operations all over the world. Our executive officers have held senior 
positions at various large mining companies including, among others, Cyprus Amax Minerals Company, INCO Limited, Meridian 
Gold Company, Barrick Gold Exploration and Noranda Exploration. Our executive team has a proven ability to manage large projects 
in challenging environments.

Velardeña Properties

Location, Access and Facilities

The Velardeña Properties are comprised of two underground mines and two processing plants within the Velardeña mining 
district, which is located in the municipality of Cuencamé, in the northeast quadrant of the State of Durango, Mexico, approximately 
65 kilometers southwest of the city of Torreón, Coahuila and approximately 140 kilometers northeast of the city of Durango, which is 
the capital of the State of Durango. The mines are reached by a seven kilometer road from the village of Velardeña which is reached 
by highway from Torreón and Durango. The Velardeña mining district is situated in a hot, semi-arid region.

Of the two underground mines comprising the Velardeña Properties, the Velardeña mine includes five different major vein 
systems including the Terneras, Roca Negra, San Mateo, Santa Juana and San Juanes systems. During 2015 we mined from the San 
Mateo, Terneras and Roca Negra vein systems as well as the Santa Juana vein system to augment grades as mining and processing 
rates ramped up.

We own a 300 tonne per day flotation sulfide mill situated near the town of Velardeña, which accounted for 100% of our 

revenue from saleable metals during 2015 and 2014. The mill includes lead, zinc and pyrite flotation circuits in which we can process 
the sulfide material to make lead, zinc and pyrite concentrates. Most of the silver and gold sold in 2014 and 2015 was contained in the 
lead concentrate. During 2015 we processed all our mined material through the sulfide plant.

We also own a conventional 550 tonne per day cyanide leach oxide mill with a Merrill-Crowe precipitation circuit and 

flotation circuit located adjacent to our Chicago mine, which we previously used to process oxide and mixed sulfide/oxide material 
from the Velardeña Properties. In July 2015, we leased the oxide plant to a third party to process its own material through the plant for 
up to 30 months. The third party began processing material at the plant in December 2015.  We continue to evaluate and search for 
other oxide and sulfide feed sources, focusing on sources within haulage distance of our sulfide and oxide mills at the Velardeña 
Properties.

Prior to shutdown, we trucked material from the Velardeña mines to the sulfide plant. In January 2012 we completed a 
tailings pond expansion at the sulfide plant, which is fully permitted and has capacity to treat tailings for approximately four additional 
years at the average processing rate of 285 tpd.   At the oxide plant, we completed the first stage of a new tailings pond during 
May 2013. Additional tailings expansion work at the oxide plant is planned for 2016 to accommodate tailings for the third party 
lessee, at the cost of the third party lessee.

Power for all of the mines and plants is provided through substations connected to the national grid. Water is provided for all 

of the mines by wells located in the valley adjacent to the Velardeña Properties. We hold title to three wells located near the sulfide 
plant and hold certificates of registration to three wells located near the oxide plant. We are licensed to pump water from all six wells 
up to a permitted amount. We are currently pumping from the three wells associated with the oxide plant which is more than sufficient 
for the third party lessee’s processing operations.

8

The following map shows the location of the Velardeña Properties.

Property History

Exploration and mining in the Velardeña district extends back to at least the late 1500s or early 1600s, with large scale 

mining beginning in 1888 with the Velardeña Mining and Smelter Company. In 1902, the mining properties were acquired by 
ASARCO, who mined the property until 1926 when the mines were closed. For the next 35 years, the mines were operated from time 
to time by small companies and local miners. The property was nationalized in 1961, and in 1968 the sulfide processing plant was 
built by the Mexican government. In 1994, William Resources acquired the concessions comprising the Velardeña Properties. In 1997, 
ECU Gold (the predecessor to ECU Silver Mining Inc.) purchased from William Resources the subsidiaries that owned the 
concessions and the oxide processing plant. The sulfide processing plant was acquired in 2004.

Title and Ownership Rights

We hold the concessions comprising the Velardeña Properties through our wholly-owned Mexican subsidiaries Minera 
William S.A. de C.V. At present, a total of 30 mineral concessions comprise the Velardeña Properties. The Velardeña Properties 
encompass approximately 895 hectares. The mineral concessions vary in size, and the concessions comprising each mineral property 
are contiguous within each of the Velardeña and Chicago properties. We are required to pay annual concession holding fees to the 
Mexican government to maintain our rights to the Velardeña mining concessions. In 2015, we made such payments totaling 
approximately $12,000 and expect to pay approximately $15,000 in 2016.  We also own the surface rights to 144 hectares that 
contains the oxide plant, tailings area and access to the Chicago mine, along with surface lands that may be required for potential plant 
expansions.

The Velardeña Properties are subject to the Mexican ejido system requiring us to contract with the local communities, or 

ejidos, surrounding our properties to obtain surface access rights needed in connection with our mining and exploration activities. We 
currently have contracts with two ejidos to secure surface rights for our Velardeña Properties with a total annual cost of approximately 
$25,000. We have a ten-year contract with the Velardeña ejido, which provides surface rights to certain roads and other infrastructure

9

at the Velardeña Properties through 2021,  and a 25-year contract with the Vista Hermosa ejido, which provides exploration access 
and access rights for roads and utilities for our Velardeña Properties until 2038.

The following Velardeña Properties exploitation concessions are identified below by name and number in the Federal 

government Public Registry of Mining.

Mine/Area
Velardeña

Chicago

Name of Exploitation
Concession

AMPL. DEL ÁGUILA MEXICANA
ÁGUILA MEXICANA
LA CUBANA
TORNASOL
SAN MATEO NUEVO
SAN MATEO
RECUERDO
SAN LUIS
LA NUEVA ESPERANZA
LA PEQUEÑA
BUEN RETIRO
UNIFICACIÓN SAN JUAN EVANGELISTA
UNIFICACIÓN VIBORILLAS
BUENAVENTURA No. 3
EL PÁJARO AZÚL
BUENAVENTURA 2
BUENAVENTURA
LOS DOS AMIGOS
VIBORILLAS NO. 2
KELLY

SANTA TERESA
SAN JUAN
LOS MUERTOS
EL GAMBUSINO
AMPLIACIÓN SAN JUAN
MUÑEQUITA
SAN AGUSTÍN
EL PISTACHÓN
LA CRUZ
EL MOGOTE FRACCION I

Concession
Number

85580
168290
168291
168292
171981
171982
171983
171984
171985
171988
172014
172737
185900
188507
188508
191305
192126
193481
211544
218681

171326
171332
171986
171987
183883
196313
210764
220407
189474
221401

We hold water concessions in wells that provide water for the Velardeña Properties. In Mexico water concessions are granted 

by the National Commission of Water (“CNA”). Currently no new water concessions are being granted by the CNA; however 
companies can acquire water concessions through purchase or lease from current concession holders. We hold title to three wells 
located near the sulfide plant and hold certificates of registration to three wells located near the oxide plant. We are licensed to pump 
water from all six wells up to a permitted amount. We are required to make annual payments to the CNA to maintain our rights to 
these wells. In 2015 we made such payments totaling approximately $25,000 and expect to pay approximately the same amount in 
2016. We are required to pay a fine to the CNA each year if we use too much water from a particular well or alternatively if we do not 
use a minimum amount of water from a particular well. During 2015 we did not incur any over usage or under usage fines.

Geology and Mineralization

The Velardeña district is located at the easternmost limit of the Sierra Madre Occidental on the boundary between the Sierra 

Madre Oriental and the Mesa Central sub-provinces. Both of these terrains are underlain by Paleozoic and possibly Precambrian 
basement rocks.

The regional geology is characterized by a thick sequence of limestone and minor calcareous clastic sediments of Cretaceous 
age, intruded by Tertiary plutons of acidic to intermediate composition. During the Laramide Orogeny, the sediments were folded into 
symmetrical anticlines and synclines that were modified into a series of asymmetrical overturned folds by a later stage of compression.

10

A series of younger Tertiary stocks have intruded the older Cretaceous limestone over a distance of approximately 15 
kilometers along a northeast to southwest trend. The various mineral deposits of the Velardeña mining district occur along the 
northeast southwest axis and are spatially associated with the intrusions and their related alteration.

An important northwest-southeast fracture system is associated with these intrusions and, in many cases, acts as the main 
focus of mineralization. The Velardeña Properties are underlain by a thick sequence of limestone that corresponds to rocks of the 
Aurora and Cuesta del Cura formations of Lower Cretaceous age.

Several types of Tertiary intrusive rocks are present in the Velardeña district. The largest of these rocks outcrops on the 

western flank of the Sierra San Lorenzo and underlies a portion of the Velardeña Properties. It is referred to as the Terneras pluton and 
forms a northeast oriented, slightly elongated body, considered to represent a diorite or monzodiorite that outcrops over a distance of 
about 2.5 kilometers. The adjacent limestone has been altered by contact metamorphism (exoskarn), and locally the intrusive has been 
metamorphosed (endoskarn).

The following is a description of the individual geological characteristics and mineralization found on each of the properties 

comprising the Velardeña and Chicago mines.

Velardeña Mine

The Santa Juana, Terneras, San Juanes and San Mateo vein deposits on the Velardeña property are hosted by Aurora 

Formation limestone, the Terneras intrusion and related skarn. The limestone is intruded by a series of multiphase diorite or 
monzodiorite stocks (Terneras intrusion) and dikes of Tertiary age that outcrop over a strike length of approximately 2.5 kilometers.

Two main vein systems are present on the Velardeña property. The first is a northwest striking system as found in the Santa 
Juana deposit, while the second is east-west trending and is present in the Santa Juana, Terneras, San Juanes and San Mateo deposits.

In the Santa Juana deposit, two main sets of vein trends are observed. The most significant is a steeply northeast dipping, 

northwest trending set that has acted as the main conduit for the mineralizing fluids in the Santa Juana deposit. This direction includes 
both linear and curved northwest vein sets.

The Terneras, San Juanes and San Mateo veins all strike east-west and dip steeply north. The most extensive of these is the 

Terneras vein, which was mined in the past over a strike length of 1,100 meters. All of these veins are observed to have extensive 
strike lengths and vertical continuity for hundreds of meters. The mineralogy of the east west system is somewhat different in that it 
contains less arsenic than the northwest Santa Juana veins.

Mineralization in the deposits located at the Velardeña mine belongs primarily to epithermal calcite quartz veins with 

associated lead, zinc, silver, gold and copper mineralization, typical of the polymetallic vein deposits of northern Mexico. The veins 
are usually thin, normally in the 0.2 meter to 0.5 meter range, but consistent along strike and down dip. Coxcomb and rhythmically 
banded textures are common.

Chicago Mine

On the Chicago property, the oldest rocks outcropping are Cretaceous limestone of the Aurora Formation which are highly 

folded. This limestone is locally metamorphosed by the intrusion of the Tertiary dioritic stocks and dykes. The general geology of the 
Chicago property is very similar to the geology of the Velardeña property. The Chicago veins strike northeast and dip steeply 
southeast. Chicago ore tends to be higher in lead and zinc than the Santa Juana ore. Vein widths at Chicago are variable and tend to be 
narrower than at the Santa Juana deposit, especially in the skarn host.

11

2014 Technical Report

During the first quarter of 2015, the engineering firm of Tetra Tech, Inc. (“Tetra Tech”) completed an estimate of mineralized 

material at the Velardeña Properties, set forth in the following table:

Silver
(Ag)
Grade
(Grams
per
tonne)

Gold
(Au)
Grade
(Grams
per
tonne)

Tonnes
(in
thousands)

Lead
(Pb)
Grade
%

Zinc (Zn)
Grade %

572
1,032

91
98

1,793

295
274

208
165

272

4.1
3.9

3.2
2.8

3.8

1.34
1.11

3.77
2.97

1.42

1.07
1.42

2.8
3.49

1.49

Mineralized Material
Mineralized Material at December 31, 

2014
Velardeña Mine

Oxide and mixed
Sulfide
Chicago Mine

Oxide and mixed
Sulfide

Total Mineralized Material at December 

31, 2014

Note: Results may not tie precisely due to rounding.

The Tetra Tech mineralized material estimate assumed a silver price of $25 per troy ounce, a gold price of $1,446 per troy 

ounce, and a cutoff grade of a net smelter return (“NSR”) of $100 per tonne.

The following table shows the commodity prices and metallurgical recoveries used to determine the cutoff grade.

Metal

Silver
Gold
Lead
Zinc

Metal Prices*

25 (oz)
1,446 (oz)
0.96 (lb)
0.91 (lb)

$
$
$
$

Sulfide
Metallurgical
Recovery
%

Oxide
Metallurgical
Recovery
%

Mixed
Metallurgical
Recovery
%

89
68
83
83

68
71
—
—

50
29
25
37

* Amounts represent three-year average prices.

The cutoff grade of $100 NSR per tonne of mineralized material was determined by adding the estimated average costs of 

mining ($53 per tonne), processing ($27 per tonne) and general and administration ($20 per tonne). The average cost estimates are the 
same for both the Velardeña and Chicago mines. The NSR value of mineralized material was determined for each type of mineralized 
material (sulfide, mixed, and oxide) by multiplying a fractional factor that represents an estimated combination of metallurgical 
recovery, treatment charges, penalties and payment terms by the unit value of each metal and then multiplying by the expected amount 
of that metal in each block of inventoried material.

The following table shows the reduction in mineralized material reported in the Tetra Tech report that resulted from 

extraction and processing of mineralized material in 2015.

12

Gold
(Au)
Grade
(Grams
per tonne)

Contained
Gold (Au)
oz.

Silver
(Ag)
Grade
(Grams
per
tonne)

Tonnes
(in thousands)

Contained
Silver (Ag)
oz.
(in thousands)

Lead
(Pb)
Grade
%

Contained
Lead (Pb)
lbs.
(in thousands)

Zinc
(Zn)
Grade %

Contained
Zinc (Zn)
lbs.
(in thousands)

572
1,032

91
98

4.1
3.9

3.2
2.8

74,780
127,741

9,362
8,822

295
274

208
165

5,425
9,101

609
520

1.34
1.11

3.77
2.97

16,898
25,254

7,563
6,417

1.07
1.42

2.80
3.49

13,493
32.307

5,617
7,540

1,793

3.8

220,406

272

15,655

1.42

56,132

1.49

58,958

—
76

—
5

81

—
—

—
—

—

572
956

91
93

—
2.6

—
1.9

2.6

—
—

—
—

—

4.1
3.9

3.2
2.8

—
6,371

—
310

6,681

—
(3,063)

—
(140)

(3,203)

74,780
118,308

9,362
8,372

—
156

—
117

154

—
—

—
—

—

295
274

208
165

—
383

—
19

401

—
(290)

—
(8)

(297)

5,425
8,429

609
493

—
0.80

—
2.00

0.87

—
—

—
—

—

1.34
1.11

3.77
2.97

—
1,343

—
220

1,564

—
(522)

—
(107)

(629)

16,898
23,389

7,563
6,089

—
1.09

—
2.82

1.20

—
—

—
—

—

1.07
1.42

2.80
3.49

—
1,839

—
311

2,150

—
(547)

—
(74)

(621)

13,493
29,921

5,617
7,155

1,712

3.8

210,522

272

14,956

1.43

53,940

1.49

56,187

Mineralized
Material
Mineralized 

Material at 
December 31, 
2014

Velardeña Mine
Oxide and mixed
Sulfide
Chicago Mine
Oxide and mixed
Sulfide

Total Mineralized 
Material at 
December 31, 
2014

2015 Extraction
Velardeña Mine
Oxide and mixed
Sulfide
Chicago Mine
Oxide and mixed
Sulfide

Total Tonnes 

Extracted in 2015

Metal loss 

adjustments 
during 2015
Velardeña Mine
Oxide and mixed
Sulfide
Chicago Mine
Oxide and mixed
Sulfide

Total Tonnes 

Extracted in 2015

Mineralized 

Material at 
December 31, 
2015

Velardeña Mine
Oxide and mixed
Sulfide
Chicago Mine
Oxide and mixed
Sulfide

Total Mineralized 
Material at 
December 31, 
2015

Note: Results may not tie precisely due to rounding. Additionally, silver ounces, zinc pounds and leads pounds are rounded to the 
nearest thousand and gold ounces are rounded to the nearest ounce and tonnes. The variance in rounding different commodities and 
units is for convenience and does not reflect any differences in the level of accuracy of the calculated mineralized material estimate.

For further detail regarding mineralized material, see “CAUTIONARY STATEMENT REGARDING MINERALIZED 

MATERIAL”.

13

Velardeña Properties 2015 Activities

In November 2015 we suspended mining and sulfide processing activities at our Velardeña Properties in order to conserve 

the asset until we are able to develop mining and processing plans that at then current prices for silver and gold indicate a sustainable 
positive operating margin (defined as revenues less costs of sales) or we are able to locate, acquire and develop alternative mineral 
sources that could be economically mined and transported to the Velardeña Properties for processing.

As a result of the shutdown of mining and sulfide processing activities at our Velardeña Properties, in the fourth quarter 

2015, we incurred approximately $1.2 million in related costs for employee severance, material and supplies inventory write downs, 
and other shutdown expenditures to place the property on care and maintenance and expect to incur approximately $0.3 million in 
quarterly holding costs for as long as mining and processing activities remain suspended.  We retained a core group of employees, 
most assigned to operate the oxide plant that is leased to a third party described below and not affected by the shutdown.  The retained 
employees also include an exploration group and an operations and administrative group to continue to advance our plans in Mexico, 
oversee corporate compliance activities, and to maintain and safeguard the longer term value of the Velardeña assets.

In July 2015 we leased our Velardeña oxide plant to a third party for an initial term of 18 months beginning July 1, 2015.  

The lease may be extended beyond the initial 18 month term for six additional months at the lessees’ option, and then for a subsequent 
six months unless we elect to use the plant to process material from our own sources.  The lease contains typical covenants and 
termination rights. The third party is responsible for all costs associated with the start-up, operation and maintenance of the oxide 
plant. The third party began making nominal monthly payments to us beginning July 1, 2015 and began processing material in mid-
December, which increased the monthly fixed fee under the lease and commenced variable charges for tonnes processed. 
Approximately 6,000 tonnes of material were processed at the leased oxide plant in December, resulting in revenues of approximately 
$130,000 in addition to fixed fees and reimbursable expenses.  Once the third party reaches its intended capacity of approximately 400 
tonnes per day, monthly payments to us, net of reimbursable costs, should total approximately $400,000 per month, including variable 
and fixed fees, or nearly $5.0 million annually.

2015 and 2014 Mining and Processing

During 2015 the processing facilities generated approximately 465,000 payable silver equivalent ounces, including 
approximately 327,000 ounces of silver and 1,975 ounces of gold, and sold approximately 494,000 silver equivalent ounces.  Silver 
equivalent ounces include silver and gold but exclude lead and zinc and are calculated at a ratio of 70 silver ounces to 1 gold ounce. 
Also, during 2015 the processing facilities generated approximately 1.1 million pounds of payable lead and 1.2 million pounds of 
payable zinc. Full year 2015 cash costs were $22.16 per payable silver ounce net of by-product credits.  “Cash costs per payable silver 
ounce, net of by-product credits” is a non-GAAP financial measure defined below in “Item 7 —Non-GAAP Financial Measures”.

Payable metals and cash costs per payable silver ounce, net of by-product credits, were negatively impacted during 2015 by 

lower average grades of plant feed of 160 grams per tonne (“gpt”) silver and 2.6 gpt gold. Mined material delivered from stopes rather 
than access drives was lower than expected, resulting in higher than expected dilution and lower than expected grades delivered to the 
plant.  During the year we used primarily shrinkage stope mining, standard mechanized cut and fill and overhand cut and fill mining 
methods. We also mined material from the Chicago mine during the third quarter to use for blending purposes to improve the lead 
content of the plant feed, which was also expected to have a positive impact on silver, gold and lead recoveries.

Mill throughput improved during 2015, with throughput of up to 370 tpd and an average rate of 252 tpd for the full year.  

Alterations to the pyrite concentrate circuit in the mill resulted in a small volume of gold bearing pyrite concentrates during the second 
half of 2015, although overall payable gold recovery was negatively impacted for the full year.

The following table shows actual silver, gold and silver equivalent payables for the fourth quarter 2014 and for 2015 until we 

suspended mining and sulfide processing in mid-November 2015.

Silver (oz)
Gold (oz)
Silver equivalent (AgEq)(oz)(3)

Note: Equivalents calculated at 70:1 silver to gold.

14

Payable Metal

2014

2015

28,746
194
42,326

326,651
1,976
464,971

The table below sets forth the mining and processing statistics of our Velardeña Properties for the last six months of 2014 and 

through mid-November of 2015.

Tonnes Milled
(includes stockpiles)

Oxide plant
Sulfide plant

Combined plant grades
(Grams per tonne)

Silver
Gold

Combined plant recovery (3) 

Silver
Gold

Contained Metals (3) 
(includes stockpiles)
Silver ounces
Gold ounces
Silver equivalent ounces (70:1)
Lead - pounds (000)
Zinc - pounds (000)

Payable Metals (3) 
(includes stockpiles)
Silver ounces
Gold ounces
Silver equivalent ounces (70:1)
Lead - pounds (000)
Zinc - pounds (000)

Products sold

Doré - kilograms
Precipitate - kilograms
Lead concentrates - tonnes
Zinc concentrates - tonnes
Pyrite concentrates - tonnes
Copper concentrates - tonnes

Payable metals in products sold

Silver ounces
Gold ounces
Silver equivalent ounces (70:1)
Lead - pounds (000)
Zinc - pounds (000)

The Year Ended December 31,

2014

2015

—
14,322
14,322

—
80,736
80,736

119
1.57

56.6%
29.0%

160
2.63

78.7%
28.9%

30,615
209
45,245
124
155

28,746
194
42,326
111
135

—
—
72
36
—
—

9,489
75
14,739
40
34

351,228
2,270
510,128
1,238
1,455

326,651
1,976
464,971
1,107
1,216

—
45
2,087
1,430
633
—

346,369
2,114
494,349
1,165
1,321

Note:   Current payable metals and recoveries include final metal settlements pertaining to sales of previously 
reported payable metals.

15

The following table shows the recovery rates for silver, gold, lead and zinc at each of our processing facilities for 2014 and 

2015.

Oxide plant recovery

Silver
Gold

Sulfide plant recovery

Silver
Gold
Lead
Zinc

2014(1)

2015

—%
—%

56.6%
29.0%
51.7%
45.6%

—%
—%

78.7%
28.9%
70.2%
57.2%

(1)  Recoveries were low in 2014 due to the buildup of in-process inventories in the sulfide plant associated with the start-up of 
processing activities in November 2014.

Product Mix

During 2015, our mining plan called for the processing of mined material to make silver and gold bearing lead, zinc and 

pyrite concentrates. In 2015 we sold from the Velardeña Properties lead, zinc and pyrite concentrates containing payable quantities of 
silver, gold, lead and zinc, selling approximately 346,000 ounces of silver and approximately 2,114 ounces of gold. Silver sales 
accounted for approximately 60% and 70% of our revenue from saleable metals during 2015 and 2014, respectively, while gold sales 
accounted for approximately 30% and 30% of our revenue from saleable metals during 2015 and 2014, respectively.

The sulfide plant at the Velardeña Properties contains a typical flotation circuit that processes material from the Velardeña 

Properties into lead, zinc and pyrite concentrate products.

Lead concentrates comprise approximately 50% to 60% of total concentrate products from the sulfide plant. The lead 
concentrates have typical assays of 30% to 35% lead, 5,000 to 6,000 grams per tonne silver, 25 to 35 grams per tonne gold, 4% to 5% 
zinc and 3% to 5% copper. After metal deductions, we are typically paid for 95% of contained lead, silver and gold. Concentrate 
treatment charges are negotiated annually and generally reflect market terms for the industry for similar products. Treatment charges 
in 2015 were approximately $245 per tonne. Additional charges are incurred for silver and gold refining, and penalties are assessed for 
certain elements, such as arsenic and antimony that exceed agreed limits.

Zinc concentrates comprise approximately 40% to 50% of total concentrate products from the sulfide plant. The zinc 

concentrates have typical assays of 50% to 55% zinc, 500 to 600 grams per tonne silver, 1 to 2 grams per tonne gold and 1% to 2% 
lead. After metal deductions, we are typically paid for approximately 80% of contained zinc and 55% of silver with lesser amounts 
payable for the contained gold. Concentrate treatment charges are negotiated annually and generally reflect market terms for the 
industry for similar products. Treatment charges in 2015 were approximately $249 per tonne. Additional charges are incurred for 
silver and gold refining, and penalties are assessed for certain elements, such as arsenic, that exceed agreed limits.

We sold a small amount of pyrite concentrates during 2015 containing on average approximately 25 gpt gold. The pyrite 
concentrates will typically contain approximately 200 - 300 gpt silver and 33% to 38% sulfur.  Concentrate treatment charges are 
renegotiated annually and generally reflect most industry key terms for similar products. Treatment charges in 2015 were 
approximately $120 per tonne with payment for approximately 70% of contained gold and no payment for silver. No additional 
charges were incurred for refining or penalties.

In 2015 we incurred approximately $1.9 million in smelting and refining charges and approximately $0.3 million in penalty 

charges, primarily for arsenic and antimony included in our lead and zinc concentrates. Treatment and penalty charges are netted 
against revenue in our consolidated statement of operations.

16

Customers

During 2015 all of our revenues from mining were attributable to the sale of products from the Velardeña Properties, 

including lead, zinc and pyrite concentrates. In 2015 we sold lead, zinc and pyrite concentrate products to three customers under 
exclusive contracts, one of which expired in March 2015, one that expired in December 2015 and one that will expire in 
February 2016. These sales contracts include terms typical for the industry, including deductions for smelting and refining charges (or 
treatment charges) and penalties for contaminates present in our products sold.

Our customer contracts, including the customer contracts that expired in March 2015 and December 2015 and the customer 

contract that will expire in February 2016 are the types that ordinarily accompany the kind of business conducted by us and our 
subsidiaries and were entered into in the ordinary course. Typically our customer contracts are not material in amount, and any 
contract that is material in amount is not a contract on which our business is substantially dependent. Most of our customer contracts 
are for a term of one year or less, and many of the contract terms are negotiable during the term of the contract. The global silver and 
gold markets are competitive with numerous refineries willing to buy concentrates on short notice. If any one of our customer 
contracts had been terminated, we had identified other customers during the bidding process as additional avenues in which to sell our 
product. We do not believe that a loss of one particular customer would have materially delayed, disrupted or reduced revenues.

Environmental Matters and Permitting

We hold environmental licenses and environmental impact assessments that allow us to run our mines, plants and tailing 

facilities at our Velardeña Properties. We are required to update our environmental licenses and environmental impact assessments for 
expansion of or modification to any of the existing two processing plants. The construction of new infrastructure beyond the current 
plant facilities also would require additional permitting, which could include environmental impact assessments and land use permits. 
We do not expect to have difficulty obtaining additional permits or environmental impact assessments.

Certain Laws Affecting Mining in Mexico

Mexico, officially the United Mexican States, is a federal constitutional republic in North America and bordered by the 

United States of America, Belize and Guatemala. Mexico is a federal democratic republic with 31 states and one federal district. Each 
state has its own constitution and its citizens elect a governor, as well as representatives, to their respective state congresses. The 
President of Mexico is the head of the executive federal government. Executive power is exercised by the President, while legislative 
power is vested in the two chambers of the Congress of the Union. The three constitutional powers are the Judiciary, the Executive 
and the Legislature which are independent of each other.

Legislation Affecting Mining

The Mining Law, originally published in 1992 and amended in 1996, 2005 and 2006, is the primary legislation governing 

mining activities in Mexico. Other significant legislation applicable to mining in Mexico includes the regulations to the Mining Law, 
the Federal Law of Waters, the Federal Labour Law, the Federal Law of Fire Arms and Explosives, the General Law on Ecological 
Balance and Environmental Protection and regulations, the Federal Law of Duties and the Federal Law on Metrology and Standards.

The Concession System

Under Mexican law, mineral deposits are property of the Mexican republic, and a mining concession, granted by the 

executive branch of the federal government, is required for the exploration, exploitation and processing of mineral deposits. Mining 
concessions may only be granted to Mexican individuals domiciled in Mexico or companies incorporated and validly existing under 
the laws of Mexico. Mexican companies that have foreign shareholders must register with the National Registry of Foreign 
Investments and renew their registration on an annual basis. Mining concessions grant rights to explore and exploit mineral deposits 
but do not grant surface rights over the land where the concession is located. Mining concession holders are required to negotiate 
surface access with the land owner or holder (e.g., agrarian communities) or, should such negotiations prove unsuccessful, file an 
application with the corresponding administrative authority (Ministry of Economy or Ministry of Agrarian-Territorial-Urban 
Development) to obtain an easement, temporary occupancy, or expropriation of the land, as the case may be. An application for a 
concession must be filed with the Mining Agency or Mining Delegation located closest to the area to which the application relates.

Mining concessions have a term of 50 years from the date on which title is recorded in the Public Registry of Mining. 
Holders of mining concessions are required to comply with various obligations, including the payment of certain mining duties based 
on the number of hectares of the concession and the number of years the concession has been in effect. Failure to pay the mining 
duties can lead to cancellation of the relevant concession. Holders of mining concessions are also obliged to carry out and prove 
assessment works in accordance with the terms and conditions set forth in the Mining Law and its regulations. The regulations to the

17

Mining Law establish minimum amounts that must be spent or invested on mining activities. A report must be filed in May of each 
year regarding the assessment works carried out during the preceding year. The mining authorities may impose a fine on the mining 
concession holder if one or more proof of assessment work reports is not timely filed.

Pursuant to amendments to the federal corporate income tax law, effective January 2014, additional duties are imposed on 

mining concession holders; see “—Taxes in Mexico”.

Environmental Legislation

Mining projects in Mexico are subject to Mexican federal, state and municipal environmental laws and regulations for the 

protection of the environment. The principal legislation applicable to mining projects in Mexico is the federal General Law of 
Ecological Balance and Environmental Protection, which is enforced by the Federal Bureau of Environmental Protection, commonly 
known as “PROFEPA”. PROFEPA is the federal entity in charge of carrying out environmental inspections and negotiating 
compliance agreements. Voluntary environmental audits, coordinated through PROFEPA, are encouraged under the federal General 
Law of Ecological Balance and Environmental Protection. PROFEPA monitors compliance with environmental legislation and 
enforces Mexican environmental laws, regulations and official standards. If warranted, PROFEPA may initiate administrative 
proceedings against companies that violate environmental laws, which proceedings may result in the temporary or permanent closure 
of non-complying facilities, the revocation of operating licenses and/or other sanctions or fines. According to the Federal Criminal 
Code, PROFEPA must inform the relevant governmental authorities of any environmental crimes that are committed by a mining 
company in Mexico.

Concession holders may submit themselves to comply with the Mexican Official Norm: NOM-120-SEMARNAT-1997, 
which provides, among other things, that mining exploration activities to be carried out within certain areas must be conducted in 
accordance with the environmental standards set forth in NOM-120-SEMARNAT-1997; otherwise, concession holders are required to 
file a preventive report or an environmental impact study prior to the commencement of the exploration, exploitation and processing 
of mineral resources. An environmental impact study may not be necessary if the concessionaire files an application with the 
environmental authorities confirming the concessionaire’s commitment to observe and comply with NOM-120-SEMARNAT-1997.

In 2014 Mexico developed an Energy sector applicable to private investment companies whereby new mining concessions 
are now subject to prior approval from the Ministry of Energy. Current mining concessions forming the Velardeña Properties are not 
subject to or affected by this approval requirement, but any new mining concessions acquired will be subject to this additional 
approval.

Taxes in Mexico

Mexico has a federal corporate income tax rate of 30%, and there are no state taxes on corporate net income. In determining 

their corporate income tax, entities are allowed to subtract from gross income various deductions permitted by law, and they are 
allowed a ten-year carry-forward of net operating losses. Pursuant to amendments to the federal tax laws effective January 1, 2014, a 
10% withholding tax is charged on dividends distributed to shareholders, regardless of the tax residence of the recipient, out of after 
tax profits. However, in the case of nonresident shareholders the limitations and tax rates provided in the treaties to avoid double 
taxation will prevail. A foreign resident company is subject to income tax if it has a permanent establishment in Mexico. In general, a 
permanent establishment is a place of business where the activities of an enterprise are totally or partially carried out and includes, 
among others, offices, branches and mining sites.

Mexico has several taxes in addition to income tax that are relevant to most business operations, including (i) the Value 

Added Tax (“VAT”); (ii) import duties; (iii) various payroll taxes; (iv) statutorily entitled employee profit sharing (“PTU”); and (v) 
mining duties and royalties. In addition, annual mining concession fees are charged by the government.

VAT in Mexico is charged upon alienation of goods, performance of independent services, grant of temporary use or 
exploitation of goods, or import of goods or services that occur within Mexico’s borders, at a rate of 16%. There is no VAT in the case 
of export of goods or services or for the sale of gold, jewelry, and gold metalwork with a minimum gold content of 80%, excluding 
retail sale to the general public. The sale of mining concessions is subject to VAT as concessions are not considered to be land. VAT 
paid by a business enterprise on its purchases and expenses may usually be credited against its liability for VAT collected from 
customers on its own sales. In addition, VAT may also be refunded, or overpayments may be used to offset tax liabilities arising from 
other federal taxes.

Import duties apply for goods and services entering the country, unless specifically exempted due to a free trade agreement or 

registered under specific programs like IMMEX, under which we are currently registered. Payroll taxes are payable in most states

18

including Durango and Coahuila, and social security, housing and pension contributions must be made to the federal government 
when paying salaries.

Employees of Mexico entities are statutorily entitled to a portion of the employer’s pre-tax profits, called PTU. The rate of 

profit sharing is currently 10% of the employer’s taxable income as defined by the Income Tax law. A taxpayer may reduce its income 
tax base by an amount equal to the PTU. Certain companies are exempt from paying PTU, which include companies in the extractive 
industry (principally the mining industry) during the period of exploration.

Under the 2014 amendments to the federal corporate income tax law, titleholders of mining concessions are required to pay 

an annual special duty of 7.5% of their mining related profits, determined by deducting from mining related revenues certain specified 
types of cash expenditures. Payment of the special duty is due at the end of March each year commencing in 2015.

Titleholders of mining concessions also are required to pay a 0.5% special mining duty, or royalty, on an annual basis, on 

revenues obtained from the sale of silver, gold and platinum. Similar to the 7.5% annual special duty, the 0.5% duty is due at the end 
of March each year commencing in 2015.

El Quevar

Location and Access

Our El Quevar silver project is located in the San Antonio de los Cobres municipality, Salta Province, in the altiplano region 

of northwestern Argentina, approximately 300 kilometers by road northwest of the city of Salta, the capital city of the province. The 
project is also accessible by a 300 kilometer dirt and gravel road from the city of Calama in northern Chile. The small village of 
Pocitos, located about 20 kilometers to the west of El Quevar, is the nearest settlement. We have established a camp approximately 10 
kilometers west of the project to house project workers. A high tension power line is located approximately 40 kilometers from the 
site, and a high pressure gas line devoted to the mining industry and subsidized by the Salta government is located within four 
kilometers of the El Quevar camp.

The El Quevar project is located near Nevado Peak with altitudes at the concessions ranging from 3,800 to 6,130 meters 

above sea level. The climate of the area is high mountain desert, with some precipitation in summer (such as snow) and little snow in 
winter.

19

The following map shows the location of the El Quevar project.

Property History

Mining activity in and around the El Quevar project dates back at least 80 years. Between 1930 and 1950, there was lead and 

silver extraction of mineralized materials from small workings in the area, but we have no mining records from that period. The first 
organized exploration activities on the property occurred during the 1970s, although no data from that period remains. Over the last 
30 years, several companies have carried out exploration activity in the area, including BHP Billiton, Industrias Peñoles, Mansfield 
Minerals and Hochschild Mining Group, consisting primarily of local sampling with some limited drilling programs.

Title and Ownership Rights

According to Argentine law, mineral resources are subject to regulation in the provinces where the resources are located. 
Each province has the authority to grant mining exploration permits and mining exploitation concession rights to applicants. The 
Federal Congress has enacted the National Mining Code and other substantive mining legislation, which is applicable throughout 
Argentina; however, each province has the authority to regulate the procedural aspects of the National Mining Code and to organize 
the enforcement authority within its own territory.

In the province of Salta, where the El Quevar project is located, all mining concessions are granted by a judge in the Salta 

Mining Court. The El Quevar project is comprised of exploitation concessions. Exploitation concessions are subject to a canon 
payment fee (maintenance fee) which is paid in advance twice a year (before June 30th and December 31st of each calendar year). 
Each time a new mining concession is granted, concession holders are exempt from the canon payment fee for a period of three years 
from the concession grant date. However, this exemption does not apply to the grant of vacant exploitation concessions; only to the 
grant of new mining concessions.

20

The El Quevar project is currently comprised of 31 mining concessions we hold directly. In total, the El Quevar project 

encompasses approximately 57,000 hectares. The area of most of our exploration activities at El Quevar is within the concessions that 
are owned by Silex Argentina S.A., our wholly-owned subsidiary.

We are required to pay a 1% net smelter return royalty on the value of all minerals extracted from the El Quevar II 

concession and a 1% net smelter return royalty on one-half of the minerals extracted from the Castor concession to the third party 
from whom we acquired these concessions.  We can purchase one half of the royalty for $1 million in the first two years of 
production.  The Yaxtché deposit is located primarily on the Castor concession. We are also required to pay a 3% royalty to the Salta 
Province based on the mine mouth value of minerals extracted from any of our concessions. To maintain all of the El Quevar 
concessions, in 2015, we paid canon payment fees to the Argentine government of approximately $74,000. In 2016 we expect to pay 
approximately $114,000. The annual amounts in 2015 and subsequent years result from the January 2015 amendment to the National 
Mining Code increasing the annual canon payment by approximately four times.

The following El Quevar mine concessions are identified below by name and file number in the Salta Province Registry of 

Mines.

Name of Mine Concession
Quevar II
Quirincolo I
Quirincolo II
Castor
Vince
Armonia
Quespejahuar
Toro I
Quevar Primera
Quevar Novena
Quevar Decimo Tercera
Quevar Tercera
Quevar Vigesimo Tercero
Quevar 10
Quevar Vigesimo Primera
Quevar Vigesimo Septima
Quevar IV
Quevar Vigesimo Cuarto
Quevar 11
Quevar Quinta
Quevar 12
Quevar Decima Quinta
Quevar Sexta
Quevar 19
Quevar Vigesimo Sexta
Quevar Vigesimo Segundo
Quevar Séptima
Quevar Veinteava
MARIANA CANTERA
Arjona
Quevar Vigesimo Quinto

Concession
File Number

17114
18036
18037
3902
1578
1542
12222
18332
19534
20215
20501
19557
21043
20219
20997
22403
19558
21044
20240
19617
20360
20445
19992
20706
22087
21042
20319
20988
15190
18080
21054

The surface rights at El Quevar are controlled by the Salta Province. There are no private properties within the concession 

area. To date, no issues involving surface rights have impacted the project. Although we have unrestricted access to our facilities, we 
have been granted easements to further protect our access rights.

Geology and Mineralization

The geology of the El Quevar project is characterized by silver-rich veins and disseminations in Tertiary volcanic rocks that 
are part of an eroded stratovolcano. Silver mineralization at El Quevar is hosted within a broad, generally east-west-trending structural

21

zone and occurs as a series of north-dipping parallel sheeted vein zones, breccias and mineralized faults situated within an envelope of 
pervasively silicified brecciated volcanic rocks. There are at least three sub-parallel structures that extend for an aggregate length of 
approximately 6.5 kilometers. Several volcanic domes (small intrusive bodies) have been identified and mineralization is also found in 
breccias associated with these domes, especially where they are intersected by the structures. The silver mineralization at the Yaxtché 
zone is of epithermal origin. The cross-cutting nature of the mineralization, the assemblage of sulfide and alteration minerals, and the 
presence of open spaces with euhedral minerals, all point to an origin at shallow to moderate depths (a few hundred meters below 
surface) from hydrothermal solutions.

2012 Technical Report

During 2012 RungePincockMinarco (“RPM”) completed an updated estimate of mineralized material at our El Quevar 
project. This SEC Industry Guide 7 estimate assumed mining of oxide material from an open pit on the east end of the Yaxtché deposit 
and sulfide material from both the open pit and an underground mine on the western portion of the Yaxtché deposit. According to the 
RPM estimate, based on results from 270 core drill holes, mineralized material in the Yaxtché zone, at a cut-off grade of 26 grams per 
tonne silver for the open pit and 100 grams per tonne silver for underground material, and using a three-year average silver price of 
$24.41 per ounce, was as follows:

Tonnes
(000s)

Average silver
grade (grams/tonne)

6,024

147.5

The RPM estimate includes a smaller tonnage of mineralized material in the possible open pit at a higher likely grade as 

compared to the technical report prepared by RPM pursuant to Canadian National Instrument 43-101 (“43-101”). In the RPM report 
pursuant to 43-101, RPM used inferred resources beneficially to the possible operation in the optimization of a resource level open pit. 
When preparing its mineralized material estimate under Industry Guide 7, RPM did not use the inferred resources calculated pursuant 
to 43-101 to beneficially optimize the pit. As such, optimization without the benefit of inferred material yielded a smaller tonnage of 
mineralized material in the possible open pit at a higher likely grade as compared to the RPM report pursuant to 43-101.

For further detail regarding mineralized material, see “CAUTIONARY STATEMENT REGARDING MINERALIZED 

MATERIAL”.

Exploration and Advancement of El Quevar

The Yaxtché deposit is the primary target currently identified at the El Quevar project. We believe that the El Quevar deposit 

may be amenable to bulk mining, which could include an open pit on the eastern and central areas of the Yaxtché deposit and bulk 
underground mining in the western area. Our work indicates that the Yaxtché deposit is at least 2 kilometers in strike length and is 
continuous laterally and to depths of more than 300 meters below surface in the main area. More recent results also support a possible 
eastward extension of the Yaxtché deposit and recognize an emerging new mineralized trend five kilometers north of the Yaxtché 
deposit. We continue to hold our El Quevar property on care and maintenance until we can find a partner to fund further exploration. 
We have completed environmental baseline studies, and a further environmental impact assessment process would be required to 
support the permits necessary for construction and mining. If the El Quevar project proceeds to development and construction, we 
would be required to obtain numerous additional permits from national, provincial and municipal authorities in Argentina.

In 2015 we spent approximately $1.1 million at our El Quevar project on holding and maintenance costs. From the inception 

of our exploration activities in 2004 through December 31, 2015 we have spent approximately $75.3 on exploration and related 
activities at El Quevar. In 2016 we expect to spend approximately $0.5 million at our El Quevar project on maintenance and holding 
costs.

Exploration Properties

In addition to El Quevar, we currently control a portfolio of approximately 10 exploration properties located primarily in 

certain traditional precious metals producing regions of Mexico. We do not consider any of our exploration properties to be material, 
including those noted below.

In 2016 we plan to focus our exploration efforts primarily on the Santa Maria Mine located in the Parral District in 
Chihuahua State, the Santa Rosa vein located in the San Luis del Cordero District in Durango State, and possibly the Rodeo property 
located west of the Velardeña Properties in Durango.  During 2016 we expect our expenditures for the exploration program to total 
approximately $2.2 million, with approximately $0.3 million in property holding costs in Mexico and approximately $0.5 million in 
administrative and general reconnaissance costs in Mexico.

22

San Luis del Cordero

We acquired the mining rights for the Santa Rosa vein in the San Luis del Cordero Project in Durango State in 

November 2015 pursuant to an exploration and exploitation agreement with a wholly-owned Mexican subsidiary of Prospero Silver 
Corp. (“Prospero”). The Santa Rosa vein is approximately two meters wide and as currently defined extends for about 400 meters on 
strike.  Silver grades as reported from previous limited drilling average between 700 and 800 gpt over a two meter width in the Santa 
Rosa vein below the historic stopes.   Records show that the Santa Rosa vein has been mined to a depth of about 100 meters.

We started a $0.5 million drilling program in February 2016 to test extensions of the Santa Rosa vein on strike and to 

complete infill drilling. Our objective is to increase the size and improve the certainty of estimates of the tonnes and grade of the 
deposit. If our exploration results are successful, we expect to issue an estimate of mineralized material and an NI 43-101 resource 
estimate and preliminary economic analysis in 2016. The preliminary results of our initial metallurgical testing of material from the 
Santa Rosa vein indicate that the material is suitable for concentration by flotation.

If the results of our exploration and metallurgical work are successful, we could mine the vein from the existing underground 

mine following completion of certain rehabilitation and access projects.  We would use primarily mining equipment from our 
shutdown Velardeña Properties and truck mined material less than 100 kilometers on paved roads to our recently idled Velardeña 
sulfide mill for processing. We may require external financing to fund capital and working capital costs associated with mining the 
Santa Rosa vein, preliminarily estimated at approximately $3 to $4 million.

Under our agreement with Prospero, we paid Prospero $140,000 on signing and are required to pay $100,000 annually until 
production begins.  We must complete a minimum of 2,000 meters of drilling within the next 18 months and commence production 
within three years. Once mining and processing begin, we would be required to pay Prospero 15% of net proceeds from the sale of 
concentrates from the property and an underlying 2% net smelter return royalty to a third party.  We would be responsible for all of 
the costs of exploration, preparation for mining, mining, processing and sales, for which we would receive a credit in the net proceeds 
calculation.

Santa Maria

In August 2014, we entered into an option agreement giving us the right to acquire for $1.2 million the Santa Maria mine, a 

privately held property comprised of a single mining claim of 18 hectares west of Hildalgo de Parral, Chihuahua State, Mexico. 
During the third quarter 2015 we mined approximately 3,000 tonnes of material from the vein as bulk samples at a total cost of about 
$250,000 and entered into a contract to process the material for metallurgical and process testing purposes at a local third-party toll 
milling facility at a cost of about $100,000. The extracted material, mined from a high grade portion of the vein, had grades of 
approximately 500 gpt silver and 0.9 gpt gold. We do not have sufficient drilling data to predict the ultimate size of this higher grade 
zone.  The 3,000 tonnes of mined material processed through the toll milling facility generated approximately 113 tonnes of 
concentrates containing approximately 47,000 ounces of silver and 80 ounces of gold.  Under an October 2015 sales agreement, we 
received proceeds for approximately 32,000 ounces of silver and 45 ounces of gold with a net payable value of about $370,000.  As 
required by the option agreement, we used a portion of the proceeds from the sale of the concentrates to pay the claim owner an 
advance royalty payment of $160,000, credited toward the $1.2 million purchase price of the property, with the remaining proceeds 
used to reimburse our costs for exploration and mining activities at Santa Maria since April 2015.

Rodeo

We acquired the Rodeo and Rodeo 2 claims comprising 1,866 hectares 80 kilometers west of the Velardeña Properties in 
Durango, Mexico where previous exploration by other companies has identified a gold-bearing epithermal system exposed at the 
surface. We plan to conduct a 2,000 meter core drilling program in 2016 or early 2017 at an estimated cost of $300,000 to $400,000.  
If our exploration efforts are successful, material from these properties could be trucked to the Velardeña oxide plant for processing 
after the third party lease has terminated.  Our cost to maintain the Rodeo properties includes advance royalty payments to La Cuesta 
International of $5,000 in 2015 and $10,000 in 2016.  La Cuesta holds a 2% net smelter return royalty on production from the claims 
up to a total payable amount of $5.0 million.  Our agreement requires a minimum program of 1,000 meters of drilling before 
May 2017.  Payments to the Mexican government to maintain the claims totaled approximately $20,000 in 2015 and are expected to 
total about $30,000 in 2016.

23

Celaya

Our Celaya properties total 6,200 hectares encompassing a strongly developed alteration system on the main Mexico Silver 

Belt trend located approximately 10 kilometers east of the Plata Latina Naranjillo discovery and 45 kilometers southeast of and on 
trend with the historic Guanajuato District. Since 2012 we have been conducting mapping and sampling exploration activities on the 
properties.  We completed during the second quarter of 2015 a 2,000 meter, three-hole drilling program, which identified epithermal 
gold and silver mineralization beneath a portion of the widespread clay-silica alteration on the claims comprising the Celaya project. 
The Company has entered into discussions with a third party regarding a potential farm-out of the project.

Zacatecas

Our 100% controlled Zacatecas silver and base metals project in Mexico is an exploration stage property that we have drilled 

in the past. Although we believe that the Zacatecas project may contain significant silver and other mineralization, we have not 
completed a mineralized material estimate or NI 43-101resource study on the property, and the property may not advance further.

The Zacatecas Mining District is located in the central part of Mexico, in the main Mexico Silver Belt. Our Zacatecas project 
surrounds the municipalities of Zacatecas, Veta Grande, Guadalupe, Pánuco, and Morelos in the state of Zacatecas, Mexico. We own 
approximately 149 concessions totaling approximately 7,900 hectares in the Zacatecas project.

To maintain all of the concessions in the Zacatecas project, we pay approximately $120,000 per year to the Mexican 
government. We are party to a finder’s fee agreement with an individual, which requires that we pay a 1% net smelter return royalty 
on any mineral production from certain of our Zacatecas claims. We also have the obligation to pay a 1% net smelter return royalty on 
the San Sabino concession, which we may buy back for $1.0 million and a 2% net smelter return royalty on the San Gil concession. 
For the San Gil concession, on the first anniversary of production, we would be required to purchase the San Gil royalty for $575,000 
and the San Gil royalty would terminate.

San Diego

We own a 50% interest in the San Diego silver exploration property, which is subject to a joint venture agreement between 
ECU and Golden Tag Resources Ltd. (“Golden Tag”), with each company holding 50% of the joint venture. The property consists of 
four concessions and the exploration activities of the joint venture are currently managed by Golden Tag. Until March 2017, Golden 
Tag has the option to earn an additional 10% interest in this joint venture by making expenditures related to further exploration 
drilling and completing an updated resource assessment.  We hold the concessions in the San Diego property through our wholly-
owned Mexican subsidiary Minera William S.A. de C.V.

The San Diego property, located in the State of Durango, Mexico, is situated approximately nine kilometers northeast of the 

Velardeña Properties and contains the La Cruz-La Rata and El Trovador mines as well as a number of other shallower shafts which 
were sunk on narrower veins such as the Cantarranas, Montanez and El Jal. The mineralization at San Diego is similar in many 
respects to that at our Velardeña Properties but contains less gold.

Farm-outs, Royalties and Other Dispositions

Exploration properties that we choose not to advance are evaluated for joint venture, sale of all or a partial interest and 

royalty potential. We currently have minority ownership interests and/or royalties in or have disposed of the following properties that 
were once part of our exploration portfolio:

(cid:120)

(cid:120)

(cid:120)

Zacatecas Royalty (Mexico).  With respect to certain concessions in a portion of our Zacatecas project in Mexico sold to 
a subsidiary of Capstone Mining Corp. in 2009, we are entitled to a net smelter return of 1.5% on the first one million 
tonnes of production, and a 3% net smelter return on production in excess of one million tonnes.  The net smelter return 
on production in excess of one million tonnes escalates by 0.5% for each $0.50 increment in copper price above $3.00 
per pound of copper. There is currently no production on these concessions.

Fortuna Royalty (Peru).  We are entitled to a net smelter return of 2.5% from a mining claim in Peru we sold to 
Compañia Minera Fortuna in August 2012. There is currently no production related to this claim.

Zacatecas Concessions (Mexico).  During the third quarter 2014 we sold 45 mining concessions totaling 770 hectares 
located in the Zacatecas District, Zacatecas State, Mexico, to Capstone Mining Group for the sum of $700,000 and 
recorded a $0.5 million gain on the sale.

24

(cid:120) Minera Silex Peru Sale (Peru).  During the third quarter 2014 we entered into an option agreement with a private party to 

sell our 1,100 hectare Peruvian Otuzco property for $450,000; the sale was completed in 2015.

Executive Officers of Golden Minerals

Name
Warren M. Rehn
Robert P. Vogels

Age

Position
61 President and Chief Executive Officer
58 Senior Vice President and Chief Financial Officer

Warren M. Rehn.  Mr. Rehn was appointed President of our company in May 2015 and appointed Chief Executive Officer 

and director in September 2015. Mr. Rehn previously served as Senior Vice President, Exploration and Chief Geologist since 
December 2012 and served as Vice President, Exploration and Chief Geologist since February 2012. From 2006 until February 2012, 
Mr. Rehn held various positions at Barrick Gold Exploration, Inc., serving most recently as Chief Exploration Geologist for the Bald 
Mountain and Ruby Hill mining units. From 2005 until 2007, Mr. Rehn was a consulting geologist for Gerson Lehman Group, which 
provides consulting services to various industries, including geology and mining. Mr. Rehn served as a Consulting Senior Geologist at 
Placer Dome Exploration, Inc. in 2004 and as an independent consulting geologist throughout the Americas from 1994 until 2003. He 
served as a Senior Geologist at Noranda Exploration, Inc. from 1988 until 1994. Mr. Rehn holds an M.S. in Geology from the 
Colorado School of Mines and a B.S. in Geological Engineering from the University of Idaho.

Robert P. Vogels.  Mr. Vogels was named Senior Vice President and Chief Financial Officer in March 2009. Mr. Vogels 

served as Controller of Apex Silver from January 2005 to March 2009 and was named Vice President in January 2006. Prior to joining 
Apex Silver, Mr. Vogels served as corporate controller for Meridian Gold Company from January 2004 until December 2004. He 
served as the controller of INCO Limited’s Goro project in New Caledonia from October 2002 to January 2004. Prior to joining 
INCO, Mr. Vogels worked from 1985 through October 2002 for Cyprus Amax Minerals Company, which was acquired in 1999 by 
Phelps Dodge Corp. During that time, he served in several capacities, including as the controller for its El Abra copper mine in Chile 
from 1997 until March 2002. Mr. Vogels began his career in public accounting as a CPA. He holds a B.Sc. in accounting and an MBA 
degree from Colorado State University.

Age

Occupation

Chairman
President and Chief Executive Officer, Company
Partner, Sierra Partners, LLC
Chief Executive Officer and Director, Geovic Mining Corporation
Corporate Director and Member, Sentient Business Council
Managing Principal, KEM Capital LLC
Principal, Marrs, Sevier & Company LLC
Chief Executive Officer and Director, The Sentient Group
Chairman, Atna Resources Ltd.

Board of Directors of Golden Minerals

Name
Jeffrey G. Clevenger
Warren M. Rehn
W. Durand Eppler (1),(3)
Michael T. Mason (3)
Ian Masterton-Hume (2)
Kevin R. Morano (2),(3)
Terry M. Palmer (1),(3)
Andrew N. Pullar
David H. Watkins (1),(2)

66
61
62
71
65
62
71
44
71

Committee Membership
(1)  Audit
(2)  Compensation
(3)  Corporate Governance and Nominating

Metals Market Overview

We are an emerging precious metals exploration company with silver and gold mining properties in Mexico and a large silver 

advanced exploration project in Argentina. Descriptions of the markets for these metals are provided below.

Silver Market

Silver has traditionally served as a medium of exchange, much like gold. Silver’s strength, malleability, ductility, thermal and 

electrical conductivity, sensitivity to light and ability to endure extreme changes in temperature combine to make it a widely used 
industrial metal. While silver continues to be used as a form of investment and a financial asset, the principal uses of silver are 
industrial, primarily in electrical and electronic components, photography, jewelry, silverware, batteries, computer chips, electrical 
contacts, and high technology printing. Silver’s anti-bacterial properties also make it valuable for use in medicine and in water 
purification. Additionally, the use of silver in the photovoltaic and solar panel industries is growing rapidly, and new uses of silver are 
being developed in connection with the use of superconductive wire and radio frequency identification devices.

25

Most silver product is obtained from mining in which silver is not the principal or primary product. The Silver Institute, an 

international silver industry association, noted that for 2014 only around 31% of output came from so-called primary silver mines, 
where silver is the main source of revenue.

The following table sets forth for the periods indicated on the London Fix high and low silver fixes in U.S. dollars per troy 

ounce. On February 24, 2016, the closing price of silver was $15.32 per troy ounce.

Year
2009
2010
2011
2012
2013
2014
2015
2016*

*

Through February 24, 2016.

Gold Market

Silver

High

Low

$
$
$
$
$
$
$
$

19.18
30.70
48.70
37.23
32.23
22.05
18.23
15.65

$
$
$
$
$
$
$
$

10.51
15.14
26.16
26.67
18.61
15.28
13.71
13.58

Gold has two main categories of use: fabrication and investment. Fabricated gold has a variety of end uses, including jewelry, 
electronics, dentistry, industrial and decorative uses, medals, medallions and official coins. Gold investors buy gold bullion, official 
coins and jewelry. The supply of gold consists of a combination of production from mining and the draw-down of existing stocks of 
gold held by governments, financial institutions, industrial organizations and private individuals.

The following table sets forth for the periods indicated on the London Fix PM high and low gold fixes in U.S. dollars per troy ounce. 
On February 24, 2016, the closing price of gold was $1,250.75 per troy ounce.

Year
2009
2010
2011
2012
2013
2014
2015
2016*

Gold

High

Low

1,212.50
1,420.00
1,895.00
1,791.75
1,693.75
1,385.00
1,295.75
1,250.75

$
$
$
$
$
$
$
$

810.00
1,058.00
1,319.00
1,540.00
1,192.00
1,142.00
1,049.40
1,077.00

$
$
$
$
$
$
$
$

* Through February 24, 2016.

Employees

We currently have approximately 165 employees, including six in Golden, approximately 129 in Torreón, Mexico or at the 
Velardeña Properties (including approximately 71 assigned to the oxide plant which is leased to a third party), three in Argentina in 
connection with the El Quevar project, and approximately 27 in various foreign exploration offices.

Competition

There is aggressive competition within the mining industry for the acquisition of a limited number of mineral resource 

opportunities, and many of the mining companies with which we compete have greater financial and technical resources than we do. 
Accordingly, these competitors may be able to spend greater amounts on acquisitions of mineral properties of merit, as well as on 
exploration and advancement of their mineral properties. We also compete with other mining companies for the acquisition and 
retention of skilled mining engineers, mine and processing plant operators and mechanics, geologists, geophysicists and other 
experienced technical personnel. Our competitive position depends upon our ability to successfully and economically advance new

26

and existing silver and gold properties. Failure to achieve and maintain a competitive position could adversely impact our ability to 
obtain the financing necessary for us to advance our mineral properties.

Available Information

We make available, free of charge through our website at www.goldenminerals.com, our annual report on Form 10-K, 

quarterly reports on Form 10-Q, current reports on Form 8-K, and amendments to those reports filed or furnished pursuant to 
Section 13(a) or 15(d) of the Exchange Act, as soon as reasonably practicable after such material is electronically filed with or 
furnished to the SEC. Information on our website is not incorporated into this annual report on Form 10-K and is not a part of this 
report.  Additionally, the public may read and copy any materials we file with the SEC at the SEC’s Public Reference Room at 100 F 
Street, NE, Washington, DC 20549. The SEC also maintains an Internet site that contains reports, proxy and information statements, 
and other information regarding issuers that file electronically with the SEC at http://www.sec.gov.

ITEM 1A:  RISK FACTORS

Investors in Golden Minerals should consider carefully, in addition to the other information contained in, or incorporated by 

reference into, this annual report on Form 10-K, the following risk factors:

We have historically incurred operating losses and operating cash flow deficits and we expect to incur operating losses and 
operating cash flow deficits through 2016; our potential profitability in the foreseeable future would depend on our ability to 
identify, acquire and mine properties to generate sufficient revenues to fund our continuing activities.

We have a history of operating losses and we expect that we will continue to incur operating losses unless and until such time 
as our Velardeña Properties, our El Quevar project, or another of our exploration properties, which may include the Santa Maria Mine, 
the San Luis del Cordero project, or the Rodeo property, generates sufficient revenue to fund our continuing business activities. In the 
fourth quarter 2015 we shut down the mines at our Velardeña Properties due to our inability to establish profitability with current 
mining methods at current prices, and borrowed $5.0 million from an investment fund managed by The Sentient Group, our largest 
stockholder, to fund cash deficits.  Although we have leased the oxide plant at the Velardeña Properties to a subsidiary of Hecla 
Mining Company, the cash that we expect will be generated from that lease will be insufficient to fund all of our continuing business 
activities as currently conducted.   In addition, the oxide plant lease may terminate sooner or produce less revenue than we anticipate if 
Hecla experiences mining problems or delays at its nearby mine, if there are disputes between Hecla and us, or for other reasons.  
There is no assurance that we will develop additional sources of revenue.

In addition, the potential profitability of mining and processing at any of our properties would be based on a number of 

assumptions. For example, profitability would depend on metal prices, costs of materials and supplies, costs at the mines and 
processing plants and the amounts and timing of expenditures, including expenditures to maintain our El Quevar project and to 
continue exploration at other exploration properties, and potential strategic acquisitions or other transactions, in addition to other 
factors, many of which are and will be beyond our control. We cannot be certain we will be able to generate sufficient revenue from 
any source to achieve profitability and eliminate operating cash flow deficits, or to cease to require additional funding.

We will require additional external financing to fund our continuing business activities in the future.

As of December 31, 2015, we had approximately $4.1 million in cash and cash equivalents. If Sentient converts the 
remaining $1.1 million Sentient Loan plus accrued interest into shares of our common stock, and assuming we receive approximately 
$4.8 million from the oxide plant lease in 2016, we expect that our current cash and cash equivalent balance would be depleted to 
approximately $0.5 million by the end of 2016.  If Sentient does not convert the remaining $1.1 million Sentient Loan plus accrued 
interest into shares of our common stock, we will require external funding to repay the loan.  In addition, the oxide plant lease may 
terminate sooner or produce less revenue than we anticipate if Hecla experiences mining problems or delays at its nearby mine, if 
there are disputes between Hecla and us, or for other reasons.  Even with cash generated by the oxide plant lease, and assuming that 
the remaining principal and interest under the Sentient Note is fully converted into shares of our common stock, our cash balance in 
2016 may not be sufficient to pursue further exploration of our properties in Mexico or cover costs required to start mining and 
processing at any of those properties, requiring us to seek additional funding from equity or debt, from monetization of non-core assets 
or from other business transactions or combinations.

We do not have a credit, off-take or other commercial financing arrangement in place that would finance our general and 

administrative costs and other working capital needs to fund our continuing business activities in the future, and we believe that 
securing credit for these purposes may be difficult given our limited history and the continuing volatility in global credit and 
commodity markets. In addition, commercial financing arrangements may not be available on favorable terms or on terms that would 
not further restrict our flexibility and ongoing ability to meet our cash requirements over a reasonable period of time. Access to public

27

financing has been negatively impacted by the volatility in the credit markets and metals prices, which may affect our ability to obtain 
equity or debt financing in the future and, if obtained, to do so on favorable terms. We also may not be able to obtain funding by 
monetizing additional non-core exploration or other assets at an acceptable price. We cannot assure you that we will be able to obtain 
financing to fund our general and administrative costs and other working capital needs to fund our continuing business activities in the 
future on favorable terms or at all.

If we commence mining in Mexico, we will likely enter into a collective bargaining agreement with a union that, together with 
labor and employment regulations, could adversely affect our mining activities and financial condition.

As was the case at our Velardeña Properties, mine employees in Mexico are typically represented by a union, and our 
relationship with our employees was, and we expect in the future will be, governed by collective bargaining agreements. Any 
collective bargaining agreement that we enter into with a union is likely to restrict our mining flexibility in and impose additional 
costs on our mining activities. In addition, relations between us and our employees in Mexico may be affected by changes in 
regulations or labor union requirements regarding labor relations that may be introduced by the Mexican authorities or by labor 
unions. Changes in legislation or in the relationship between us and our employees may have a material adverse effect on our mining 
activities and financial condition.

We may not mine the Velardeña Properties again.

In mid-November 2015, we shut down the mines and sulfide processing plant at our Velardeña Properties and placed them on 

care and maintenance.  Commencing mining again is subject to numerous risks and uncertainties, including:

(cid:120) whether we are able to create mine plans or gold recovery improvements that can achieve sustainable cash positive 

results at current and future metals prices;

(cid:120)

(cid:120)

(cid:120)

(cid:120)

(cid:120)

(cid:120)

unexpected events, including difficulties in maintaining the properties on a care and maintenance basis, potential 
sabotage or damage to the assets related to the suspension of mining, and variations in ore grade and relative amounts, 
grades and metallurgical characteristics of oxide and sulfide ores;

continued decreases or insufficient increases in gold and silver prices to permit us to achieve sustainable cash positive 
results;

actual holding and care and maintenance costs resulting from the shutdown exceeding current estimates or including 
unanticipated costs;

loss of and inability to adequately replace skilled mining and management personnel;

strikes or other labor problems; and

our ability to obtain additional funding for general and administrative costs and other working capital needs to fund our 
continuing business activities as currently conducted and possibly for a potential restart of our Velardeña Properties.

Based on these risks and uncertainties, there can be no assurance that we will restart mining activities at the Velardeña 

Properties.

Our ability to successfully conduct mining and processing activities resulting in long-term cash flow and profitability will be 
affected by changes in prices of silver, gold and other metals.

Our ability to successfully conduct mining and processing activities in Mexico, Argentina or other countries, to establish 

reserves and advance our exploration properties, and to become profitable in the future, as well as our long-term viability, depend, in 
large part, on the market prices of silver, gold, zinc,  copper and other metals. The market prices for these metals are volatile and are 
affected by numerous factors beyond our control, including:

(cid:120)

(cid:120)

(cid:120)

global or regional consumption patterns;

supply of, and demand for, silver, gold, zinc, lead, copper and other metals;

speculative activities and hedging activities;

28

(cid:120)

(cid:120)

(cid:120)

expectations for inflation;

political and economic conditions; and

supply of, and demand for, consumables required for extraction and processing of metals.

The declines in silver and gold prices in 2013, 2014 and 2015 have had a significant impact on our mining activities, 

resulting in shutdowns in 2013 and 2015 of mining at our Velardeña Properties, and negatively affect mining opportunities at our 
other properties. Additionally, future weakness in the global economy could increase volatility in metals prices or depress metals 
prices, which could also affect our mining and processing plans at our Velardeña Properties or make it uneconomic for us to engage in 
mining or exploration activities. Volatility or sustained price declines may also adversely affect our ability to build or continue our 
business.

Products processed from our Velardeña Properties or other mines could contain higher than expected contaminants, thereby 
negatively impacting our financial condition.

In 2015 we processed mined material to make gold and silver bearing lead, zinc and pyrite concentrates. Concentrate 

treatment charges paid to smelters and refineries include penalties for certain elements, including arsenic and antimony that exceed 
contract limits. It is possible that our concentrates will contain higher amounts of these elements than we anticipate.  This can occur 
due to unexpected variations in the occurrence of these elements in the material mined, problems that occur during blending of 
material from various locations in the mine prior to processing and other unanticipated events. In the future, if our concentrates 
include higher than expected contaminants, we would incur higher treatment expenses and penalty charges, which could increase our 
costs and negatively impact our business, financial condition and results of operations.

As a result of our business combination with ECU, we have assumed all historical ECU liabilities, some of which are known or 
which may become known by Golden Minerals.

In September 2011, we completed a business combination with ECU, which at that time owned the Velardeña Properties. As 
a result of this transaction, we are subject to the environmental, contractual, tax and other obligations and liabilities of ECU, some of 
which may be unknown. There can be no assurance that we are aware of all obligations and liabilities related to the historical business 
of ECU. These liabilities, and other liabilities related to ECU’s business not currently known to us or that prove to be more significant 
than we currently anticipate, could negatively impact our business, financial condition and results of operations.

The Velardeña Properties, the El Quevar project and our other properties may not contain mineral reserves.

We are considered an exploration stage company under SEC Industry Guide 7, and none of the properties at our Velardeña 

Properties, the El Quevar project, or any of our other properties have been shown to contain proven or probable mineral reserves. 
Expenditures made in mining at the Velardeña Properties or the exploration and advancement of our El Quevar project or other 
properties may not result in positive cash flow or in discoveries of commercially recoverable quantities of ore. Most exploration 
projects do not result in the discovery of commercially mineable ore deposits, and we cannot assure you that any mineral deposit we 
identify will qualify as an orebody that can be legally and economically exploited or that any particular level of recovery from 
discovered mineralization will in fact be realized.

Tetra Tech completed a technical report on our Velardeña Properties, which indicated the presence of mineralized material, 

and RungePincockMinarco completed a technical report on our El Quevar property, which indicated the presence of mineralized 
material. Mineralized material figures based on estimates made by geologists are inherently imprecise and depend on geological 
interpretation and statistical inferences drawn from drilling and sampling that may prove to be unreliable or inaccurate. We cannot 
assure you that these estimates are accurate or that proven and probable mineral reserves will be identified at the Velardeña Properties, 
El Quevar or any of our other properties. Even if the presence of reserves is established at a project, the economic viability of the 
project may not justify exploitation. We have spent significant amounts on the evaluation of El Quevar prior to establishing the 
economic viability of that project.

Estimates of reserves, mineral deposits and mining costs also can be affected by factors such as governmental regulations and 

requirements, fluctuations in metals prices or costs of essential materials or supplies, environmental factors, unforeseen technical 
difficulties and unusual or unexpected geological formations. In addition, the grades of ore or material ultimately mined may differ 
from that indicated by drilling results, sampling, feasibility studies or technical reports. Short-term factors relating to reserves, such as 
the need for orderly development of ore bodies or the processing of new or different grades, may also have an adverse effect on

29

mining and on the results of operations. Silver, gold or other minerals recovered in small-scale laboratory tests may not be duplicated 
in large-scale tests under on-site processing conditions.

The Velardeña Properties, the El Quevar project and our other properties are subject to foreign environmental laws and 
regulations which could materially adversely affect our business.

We have conducted mining activities in Mexico and conduct mineral exploration activities primarily in Mexico. Mexico and 

Argentina, where our El Quevar project is located, have laws and regulations that control the exploration and mining of mineral 
properties and their effects on the environment, including air and water quality, mine reclamation, waste generation, handling and 
disposal, the protection of different species of flora and fauna and the preservation of lands. These laws and regulations require us to 
acquire permits and other authorizations for conducting certain activities. In many countries, there is relatively new comprehensive 
environmental legislation, and the permitting and authorization process may not be established or predictable. We may not be able to 
acquire necessary permits or authorizations on a timely basis, if at all. Delays in acquiring any permit or authorization could increase 
the cost of our projects and could suspend or delay the commencement of extraction and processing of mineralized material.

Our Velardeña Properties are subject to regulation by SEMARNAT, the environmental protection agency of Mexico. In order 

to permit new facilities at or expand existing facilities, regulations require that an environmental impact statement, known in Mexico 
as a Manifestación de Impacto Ambiental, be prepared by a third-party contractor for submission to SEMARNAT. Studies required to 
support the Manifestación de Impacto Ambiental include a detailed analysis of soil, water, vegetation, wildlife, cultural resources and 
socio-economic impacts. The Manifestación is then published on SEMARNAT’s web page and in its official gazette in a national and 
local newspaper. The Manifestación is discussed at various open hearings, including hearings in the local communities, at which third 
parties may voice their views. We would be required to provide proof of local community support of the Manifestación as a condition 
to final approval.  We may not be able to obtain community support of future projects.

Environmental legislation in Mexico is evolving in a manner which will require stricter standards and enforcement, increased 

fines and penalties for non-compliance, more stringent environmental assessments of proposed projects, and a heightened degree of 
responsibility for companies and their officers, directors and employees. For example, in January 2011, Article 180 of the Mexican 
Federal General Law of Ecological Balance and Environmental Protection was amended. Among other things, this amendment 
extended the term during which an individual or entity having a legitimate interest may contest administrative acts, including 
environmental authorizations, permits or concessions granted, without the need to demonstrate the actual existence of harm to the 
environment, natural resources, flora, fauna or human health, making it sufficient to argue that harm may be caused. Further, the 
amendment permits the contesting party to challenge a Manifestación de Impacto Ambiental through a variety of administrative or 
court procedures. As a result of the amendment, more legal actions supported or sponsored by non-governmental groups interested in 
halting projects may be filed against companies operating in all industrial sectors, including the mining sector. Mexican operations are 
also subject to the environmental agreements entered into by Mexico, the United States and Canada in connection with the North 
American Free Trade Agreement. Further, in August 2011, certain amendments to the Civil Federal Procedures Code of Mexico 
(“CFPC”) were published in the Official Daily of the Federation. The amendments establish three categories of collective actions by 
which 30 or more people claiming injury resulting from, among other things, environmental harm, will be deemed to have a sufficient 
and legitimate interest in seeking, through a civil procedure, restitution, economic compensation or suspension of the activities from 
which the alleged injury derived. These amendments to the CFPC may result in more litigation by plaintiffs seeking remedies for 
alleged environmental harms, including suspension of the activities alleged to cause harm. Future changes in environmental regulation 
in the jurisdictions where the Velardeña Properties are located may adversely affect our business, make our business prohibitively 
expensive, or prohibit it altogether.

Environmental legislation in many other countries, in addition to Mexico, is evolving in a manner that will likely require 
stricter standards and enforcement, increased fines and penalties for non-compliance, more stringent environmental assessments of 
proposed projects and a heightened degree of responsibility for companies and their officers, directors and employees. We cannot 
predict what environmental legislation or regulations will be enacted or adopted in the future or how future laws and regulations will 
be administered or interpreted. For example, in September 2010, the Argentine National Congress passed legislation which prohibits 
mining activity in glacial and surrounding areas. Although we do not currently anticipate that this legislation will impact the 
El Quevar project, the legislation provides an example of the evolving environmental legislation in the areas in which we operate. 
Compliance with more stringent laws and regulations, as well as potentially more vigorous enforcement policies or regulatory 
agencies or stricter interpretation of existing laws, may (i) necessitate significant capital outlays, (ii) cause us to delay, terminate or 
otherwise change our intended activities with respect to one or more projects, or (iii) materially adversely affect our future exploration 
activities.

The Velardeña Properties and many of our exploration properties are located in historic mining districts where prior owners, 
including ECU in the case of the Velardeña Properties, may have caused environmental damage that may not be known to us or to the 
regulators. At the Velardeña Properties and in most other cases, we have not sought complete environmental analyses of our mineral

30

properties. We have not conducted comprehensive reviews of the environmental laws and regulations in every jurisdiction in which 
we own or control mineral properties. Insurance fully covering many environmental risks (including potential liability for pollution or 
other hazards as a result of disposal of waste products occurring from exploration and mining) is not generally available. To the extent 
environmental hazards may exist on the properties in which we currently hold interests, or may hold interests in the future, that are 
unknown to us at present and that have been caused by us, or previous owners or operators, or that may have occurred naturally, and 
to the extent we are subject to environmental requirements or liabilities, the cost of compliance with these requirements and 
satisfaction of these liabilities could have a material adverse effect on our financial condition and results of operations. If we are 
unable to fully fund the cost of remediation of any environmental condition, we may be required to suspend activities or enter into 
interim compliance measures pending completion of the required remediation.

In addition, U.S. or international legislative or regulatory action to address concerns about climate change and greenhouse 

gas emissions could negatively impact our business.

Title to the Velardeña Properties and our other properties and rights may be defective or may be challenged.

Our policy is to seek to confirm the validity of our rights to, title to, or contract rights with respect to, each mineral property 
in which we have a material interest. However, we cannot guarantee that title to our properties will not be challenged. Title insurance 
is not available for our mineral properties, and our ability to ensure that we have obtained secure rights to individual mineral 
properties or mining concessions may be severely constrained. Accordingly, the Velardeña Properties and our other mineral properties 
may be subject to prior unregistered agreements, transfers or claims, and title may be affected by, among other things, undetected 
defects. In addition, we may be unable to conduct activities on our properties as permitted or to enforce our rights with respect to our 
properties, and the title to our mineral properties may also be impacted by state action. We have not conducted surveys of all of the 
exploration properties in which we hold direct or indirect interests and, therefore, the precise area and location of these exploration 
properties may be in doubt.

In most of the countries in which we operate, failure to comply with applicable laws and regulations relating to mineral right 
applications and tenure could result in loss, reduction or expropriation of entitlements, or the imposition of additional local or foreign 
parties as joint venture partners. Any such loss, reduction or imposition of partners could have a material adverse effect on our 
financial condition, results of operations and prospects.

Under the laws of Mexico, mineral resources belong to the state, and government concessions are required to explore for or 

exploit mineral reserves. Mineral rights derive from concessions granted, on a discretionary basis, by the Ministry of Economy, 
pursuant to the Mexican mining law and regulations thereunder. We hold title to the Velardeña Properties and our other properties in 
Mexico through these government concessions, but there is no assurance that title to the concessions comprising the Velardeña 
Properties and other properties will not be challenged or impaired. The Velardeña Properties and other properties may be subject to 
prior unregistered agreements, interests or native land claims, and title may be affected by undetected defects. There could be valid 
challenges to the title of any of the claims comprising the Velardeña Properties that, if successful, could impair mining with respect to 
such properties in the future. A defect could result in our losing all or a portion of our right, title, and interest in and to the properties 
to which the title defect relates.

Our Velardeña Properties mining concessions and our other mining concessions in Mexico may be terminated if our 

obligations to maintain the concessions in good standing are not satisfied, including obligations to explore or exploit the relevant 
concession, to pay any relevant fees, to comply with all environmental and safety standards, to provide information to the Ministry of 
Economy and to allow inspections by the Ministry of Economy. In addition to termination, failure to make timely concession 
maintenance payments and otherwise comply strictly with applicable laws, regulations and local practices relating to mineral right 
applications and tenure could result in reduction or expropriation of entitlements. Additionally, in 2014, new mining concessions 
became subject to additional review and approval by the Mexico Ministry of Energy.

Mining concessions in Mexico give exclusive exploration and exploitation rights to the minerals located in the concessions 

but do not include surface rights to the real property, which requires that we negotiate the necessary agreements with surface 
landowners. Many of our mining properties are subject to the Mexican ejido system requiring us to contract with the local 
communities surrounding the properties in order to obtain surface rights to land needed in connection with our mining exploration 
activities. In connection with our Velardeña Properties, we have contracts with two ejidos to secure surface rights with a total annual 
cost of approximately $25,000. The first contract is a ten-year contract with the Velardeña ejido, which provides surface rights to 
certain roads and other infrastructure at the Velardeña Properties through 2021. The second contract is a 25-year contract with the 
Vista Hermosa ejido signed in March 2013, which provides exploration access and access rights for roads and utilities for our 
Velardeña Properties. Our inability to maintain and periodically renew or expand these surface rights on favorable terms or otherwise 
could have a material adverse effect on our business and financial condition.

31

Mining and processing activities are dependent on the availability of sufficient water supplies to support our mining activities.

Mining and processing at the Velardeña Properties, as at most mines, requires significant amounts of water.  At the Velardeña 

Properties, our ability to have sufficient water is dependent on our ability to maintain our water rights and claims. Water is provided 
for all of the mines comprising our Velardeña Properties by wells located in the valley adjacent to the Velardeña Properties. We hold 
title to three wells located near the sulfide plant and hold certificates of registration to three wells located near the oxide plant. We are 
licensed to pump water from all six wells up to a permitted amount. We are currently only using water from the three wells associated 
with the oxide plant. We are required to make annual payments to the Mexican government to maintain our rights to these wells. We 
are required to pay a fine to the Mexican Government each year if we use too much water from a particular well or alternatively if we 
do not use a minimum amount of water from a particular well. In addition to these fines, the Mexican Government reserves the right to 
cancel our title to the wells for abuse of these rules.

We currently have a sufficient amount of water for the third party processing activities at the oxide plant.  However, if we 

began processing material from both the sulfide and oxide plants in the future, we may face shortages in our water supply, and 
therefore will need to obtain water from outside sources at higher costs. The loss of some or all water rights for any of our wells, in 
whole or in part, or shortages of water to which we have rights would require us to seek water from outside sources at higher costs and 
could require us to curtail or shut down mining and processing in the future. Laws and regulations may be introduced in the future 
which could limit our access to sufficient water resources in mining activities, thus adversely affecting our business.

There are significant hazards involved in underground mining and processing activities at our Velardeña Properties, not all of 
which are fully covered by insurance. To the extent we must pay the costs associated with such risks, our business may be 
negatively affected.

The mining and processing of the underground mines at our Velardeña Properties, as well as the conduct of our exploration 

programs that frequently require rehabilitation of and drilling in underground mine workings, are subject to numerous risks and 
hazards, including, but not limited to, environmental hazards, industrial accidents, encountering unusual or unexpected geological 
formations, formation pressures, cave-ins, underground fires or floods, power outages, labor disruptions, seismic activity, rock bursts, 
accidents relating to historical workings, landslides and periodic interruptions due to inclement or hazardous weather conditions. 
These occurrences could result in damage to, or destruction of, mineral properties or processing facilities, personal injury or death, 
environmental damage, reduced extraction and processing and delays in mining, asset write-downs, monetary losses and possible legal 
liability. Although we maintain insurance against risks inherent in the conduct of our business in amounts that we consider reasonable, 
this insurance contains, as in the case of our Velardeña Properties, exclusions and limitations on coverage, and will not cover all 
potential risks associated with mining and exploration activities, and related liabilities might exceed policy limits. As a result of any or 
all of the forgoing, particularly if the facilities are older, we could incur significant liabilities and costs that could adversely affect our 
results of operation and financial condition.

Our Velardeña Properties and most of our exploration properties are located in Mexico and are subject to various levels of 
political, economic, legal and other risks.

Our Velardeña Properties are located in Mexico, and, as such, are exposed to various levels of political, economic, legal and 

other risks and uncertainties, including local acts of violence, such as violence from drug cartels; military repression; extreme 
fluctuations in currency exchange rates; high rates of inflation; labor unrest; the risks of war or civil unrest; expropriation and 
nationalization; renegotiation or nullification of existing concessions, licenses, permits and contracts; illegal mining; acts of political 
corruption; changes in taxation policies; restrictions on foreign exchange and repatriation; and changing political conditions, currency 
controls and governmental regulations that favor or require the awarding of contracts to local contractors or require foreign contractors 
to employ citizens of, or purchase supplies from, a particular jurisdiction.

In the past, Mexico has been subject to political instability, changes and uncertainties, which have resulted in changes to 

existing governmental regulations affecting mineral exploration and mining activities. Mexico’s status as a developing country may 
make it more difficult for us to obtain any required funding for our Velardeña Properties or other projects in Mexico in the future.

Our Mexican properties are subject to a variety of governmental regulations governing health and worker safety, employment 

standards, waste disposal, protection of historic and archaeological sites, mine development, protection of endangered and protected 
species, purchase, storage and use of explosives and other matters. Specifically, our activities related to the Velardeña Properties are 
subject to regulation by SEMARNAT, the Comision Nacional del Agua, which regulates water rights, and Mexican mining laws. 
Mexican regulators have broad authority to shut down and levy fines against facilities that do not comply with regulations or 
standards.

32

Our Velardeña Properties and mineral exploration activities in Mexico may be adversely affected in varying degrees by 

changing government regulations relating to the mining industry or shifts in political conditions that increase the costs related to our 
mining and exploration activities or the maintenance of our properties. For example, in January 2014, amendments to the Mexico 
federal corporate income tax law require titleholders of mining concessions to pay annually a 7.5% duty of their mining related profits 
and a 0.5% duty on revenues obtained from the sale of gold, silver and platinum that were effective March 2015. These additional 
duties applicable to Mexico mining concession titleholders will have a significant impact on the annual costs applicable to the 
Velardeña Properties if we have mining related profits or significant revenues in the future.

Changes, if any, in mining or investment policies, changes or increases in the legal rights of indigenous populations or in the 

difficulty or expense of obtaining rights from them that are necessary for our Velardeña Properties or shifts in political attitude may 
adversely affect our business and financial condition. Our mining and exploration activities may be affected in varying degrees by 
government regulations with respect to restrictions on extraction, price controls, export controls, currency remittance, income and 
other taxes, expropriation of property, foreign investment, maintenance of claims, environmental legislation, land use, land claims of 
local people, water use and mine safety. Restart of mining or use of both the oxide and sulfide plant may also require us to assure the 
availability of adequate supplies of water and power, which could be affected by government policy and competing businesses in the 
area. The occurrence of these various factors and uncertainties cannot be accurately predicted and could have an adverse effect on our 
mining and exploration activities and financial condition.

Future changes in applicable laws and regulations or changes in their enforcement or regulatory interpretation could 

negatively impact current or planned exploration or mining activities at our Velardeña Properties or in respect of any of our other 
projects in Mexico or with which we become involved in Mexico. Any failure to comply with applicable laws and regulations, even if 
inadvertent, could result in the interruption of mining and exploration or material fines, penalties or other liabilities.

Most of our costs are subject to exchange control policies, the effects of inflation and currency fluctuations between the U.S. dollar 
and the Mexican peso.

Our revenue and external funding are primarily denominated in U.S. dollars. However, mining, processing, maintenance and 

exploration costs at the Velardeña Properties and most of our exploration properties are denominated principally in Mexican pesos. 
These costs principally include electricity, labor, water, maintenance, local contractors and fuel.  When inflation in Mexico increases 
without a corresponding devaluation of the Mexican peso, our financial position, results of operations and cash flows could be 
adversely affected. The annual inflation rate in Mexico was 2.1% in 2015, 4.1% in 2014 and 4.0% in 2013. At the same time, the peso 
has been subject to significant fluctuation, which may not have been proportionate to the inflation rate and may not be proportionate to 
the inflation rate in the future. The value of the peso decreased by 17% in 2015, decreased by 13% in 2014 and decreased by 0.6% in 
2013. In addition, fluctuations in currency exchange rates may have a significant impact on our financial results. There can be no 
assurance that the Mexican government will maintain its current policies with regard to the peso or that the peso’s value will not 
fluctuate significantly in the future. We cannot assure you that currency fluctuations, inflation and exchange control policies will not 
have an adverse impact on our financial condition, results of operations, earnings and cash flows.

If we are unable to obtain all of our required governmental permits or obtain property rights on favorable terms or at all, our 
business could be negatively impacted.

Future mining and current processing at our Velardeña Properties, the continued evaluation of the El Quevar project and 

other exploration activities will require additional permits from various governmental authorities. Our business is and will continue to 
be governed by laws and regulations governing mining, exploration, prospecting, exports, taxes, labor standards, occupational health, 
waste disposal, toxic substances, land use, environmental protection, mine safety, mining royalties and other matters. We may also be 
required to obtain certain property rights to access or use our properties. Obtaining or renewing licenses and permits, and acquiring 
property rights, can be complex and time-consuming processes. There can be no assurance that we will be able to acquire all required 
licenses, permits or property rights on reasonable terms or in a timely manner, or at all, and that such terms will not be adversely 
changed, that required extensions will be granted, or that the issuance of such licenses, permits or property rights will not be 
challenged by third parties. Delays in obtaining or a failure to obtain any licenses, permits or property rights or any required 
extensions; challenges to the issuance of licenses, permits or property rights, whether successful or unsuccessful; changes to the terms 
of licenses, permits or property rights; or a failure to comply with the terms of any licenses, permits or property rights that have been 
obtained could have a material adverse effect on our business by delaying, preventing or making future mining and processing at our 
Velardeña Properties and other continued processing activities economically unfeasible. U.S. or international legislative or regulatory 
action to address concerns about climate change and greenhouse gas emissions could also negatively impact our business. While we 
will continue to monitor and assess any new policies, legislation or regulations regarding such matters, we currently believe that the 
impact of such legislation on our business will not be significant.

33

We own our interest in the San Diego exploration property in Mexico in a 50-50 joint venture and are therefore unable to control 
all aspects of exploration and advancement of this property.

We hold the San Diego exploration property in Mexico in a 50-50 joint venture with Golden Tag Resources Ltd., which, until 

March 2017, has a right to acquire an additional 10% interest by making expenditures related to further exploration drilling and 
completing an updated resource assessment at the property. Our interest in the San Diego property is subject to the risks normally 
associated with the conduct of joint ventures. A disagreement between joint venture partners on how to conduct business efficiently, 
the inability of joint venture partners to meet their obligations to the joint venture or third parties, or litigation arising between joint 
venture partners regarding joint venture matters could have a material adverse effect on the viability of our interests held through the 
joint venture. For example, in 2009, ECU received a notice of arbitration from Golden Tag Resources Ltd. The dispute was settled in 
September 2010 and resulted in an increase in ECU’s mining property costs of approximately $61,000. Additionally, if Golden Tag 
Resources Ltd. exercises its right to acquire an additional 10% interest, our ability to control exploration and advancement will be 
further reduced.

We depend on the services of key executives.

Our business strategy is based on leveraging the experience and skill of our management team. We are dependent on the 

services of key executives, including Warren Rehn and Robert Vogels. Due to our relatively small size, the loss of any of these 
persons or our inability to attract and retain additional highly skilled employees may have a material adverse effect on our business 
and our ability to manage and succeed in our mining and exploration activities.

The exploration of our mineral properties is highly speculative in nature, involves substantial expenditures and is frequently non-
productive.

Mineral exploration is highly speculative in nature and is frequently non-productive. Substantial expenditures are required to:

(cid:120)

(cid:120)

(cid:120)

(cid:120)

establish mineral reserves through drilling and metallurgical and other testing techniques;

determine metal content and metallurgical recovery processes to process metal from the ore;

determine the feasibility of mine development and production; and

construct, renovate or expand mining and processing facilities.

If we discover a deposit or ore at a property, it usually takes several years from the initial phases of exploration until 

production is possible. During this time, the economic feasibility of a project may change because of increased costs, lower metal 
prices or other factors. As a result of these uncertainties, we may not successfully acquire additional mineral rights, or our exploration 
programs may not result in proven and probable reserves at all or in sufficient quantities to justify developing the El Quevar project or 
any of our exploration properties.

The decisions about future advancement of exploration projects may be based on feasibility studies, which derive estimates 
of mineral reserves, operating costs and project economic returns. Estimates of economic returns are based, in part, on assumptions 
about future metal prices and estimates of average cash operating costs based upon, among other things:

(cid:120)

(cid:120)

(cid:120)

(cid:120)

anticipated tonnage, grades and metallurgical characteristics of ore to be mined and processed;

anticipated recovery rates of silver and other metals from the ore;

cash operating costs of comparable facilities and equipment; and

anticipated climatic conditions.

Actual cash operating costs, production and economic returns may differ significantly from those anticipated by our studies 

and estimates.

Lack of infrastructure could forestall or prevent further exploration and advancement.

Exploration activities, as well as any advancement activities, depend on adequate infrastructure. Reliable roads, bridges, 

power sources and water supply are important factors that affect capital and operating costs and the feasibility and economic viability

34

of a project. Unanticipated or higher than expected costs and unusual or infrequent weather phenomena, or government or other 
interference in the maintenance or provision of such infrastructure, could adversely affect our business, financial condition and results 
of operations.

Our exploration activities are in countries with developing economies and are subject to the risks of political and economic 
instability associated with these countries.

We currently conduct exploration activities almost exclusively in countries with developing economies, including Argentina 

and Mexico. These countries and other emerging markets in which we may conduct business have from time to time experienced 
economic or political instability. We may be materially adversely affected by risks associated with conducting exploration activities in 
countries with developing economies, including:

(cid:120)

political instability and violence;

(cid:120) war and civil disturbance;

(cid:120)

(cid:120)

(cid:120)

(cid:120)

(cid:120)

(cid:120)

(cid:120)

(cid:120)

(cid:120)

acts of terrorism or other criminal activity;

expropriation or nationalization;

changing fiscal, royalty and tax regimes;

fluctuations in currency exchange rates;

high rates of inflation;

uncertain or changing legal requirements respecting the ownership and maintenance of mineral properties, mines and 
mining activities, and inconsistent or arbitrary application of such legal requirements;

underdeveloped industrial and economic infrastructure;

corruption; and

unenforceability of contractual rights.

Changes in mining or investment policies or shifts in the prevailing political climate in any of the countries in which we 

conduct exploration activities could adversely affect our business.

We conduct our business in countries that may be adversely affected by changes in the local government’s policies toward or laws 
governing the mining industry.

We have exploration activities primarily in Mexico and Argentina. In these regions there exist uncertainties regarding future 

changes in applicable law related to mining and exploration. For instance, in January 2014, amendments to the Mexico federal 
corporate income tax law require titleholders of mining concessions to pay annually a 7.5% duty of their mining related profits and a 
0.5% duty on revenues obtained from the sale of gold, silver and platinum that were effective March 2015. These additional duties 
applicable to Mexico mining concession titleholders will have a significant impact on the annual costs applicable to the Velardeña 
Properties if we have mining related profits or significant revenues in the future.

Additionally, effective January 2015, the Argentina National Mining Code was amended, increasing the annual canon 

payment by approximately four times.  In 2014 and 2015, our annual canon fees payable to the Argentine government was $35,000 
and $74,000 respectively, and we expect to pay approximately $114,000 in 2016.

Furthermore, as a result of the termination of a bilateral tax treaty among Spain and Argentina (terminated January 2013), 

certain beneficial tax treatment arising from equity ownership between our Spain and Argentina subsidiaries was eliminated. 
Consequently, we recorded a liability of approximately $21,500 as of December 31, 2015 and could be liable for up to an additional 
approximately $0.3 million stemming from unpaid interest equity tax for years 2009 through 2012 plus fines.

35

In addition to the risk of increased transaction costs, we do not maintain political risk insurance to cover losses that we may 

incur as a result of nationalization, expropriation or similar events in Mexico or Argentina where we explore or have mining and 
processing activities.

We compete against larger and more experienced companies.

The mining industry is intensely competitive. Many large mining companies are primarily makers of precious or base metals 

and may become interested in the types of deposits on which we are focused, which include silver, gold and other precious metals 
deposits or polymetallic deposits containing significant quantities of base metals, including zinc, lead and copper. Many of these 
companies have greater financial resources, experience and technical capabilities than we do. We may encounter increasing 
competition from other mining companies in our efforts to acquire mineral properties and hire experienced mining professionals. 
Increased competition in our business could adversely affect our ability to attract necessary capital funding or acquire suitable mining 
properties or prospects for mineral exploration in the future.

We are dependent on information technology systems, which are subject to certain risks, including cybersecurity risks and data 
leakage risks.

We are dependent upon information technology systems in the conduct of our business. Any significant breakdown, invasion, 

virus, cyber attack, security breach, destruction or interruption of these systems by employees, others with authorized access to our 
systems, or unauthorized persons could negatively impact our business. To the extent any invasion, cyber attack or security breach 
results in disruption to our business, loss or disclosure of, or damage to, our data or confidential information, our reputation, business, 
results of operations and financial condition could be materially adversely affected. Our systems and insurance coverage for protecting 
against cyber security risks may not be sufficient. Although to date we have not experienced any material losses relating to cyber 
attacks, we may suffer such losses in the future. We may be required to expend significant additional resources to continue to modify 
or enhance our protective measures or to investigate and remediate any information security vulnerabilities.

If we default on the Sentient Loan, Sentient will have the right to foreclose on the stock of subsidiaries holding our Velardeña 
Properties and the El Quevar project and exercise other remedies.

In October 2015, pursuant to a senior secured convertible note (the “Sentient Note”), we borrowed $5.0 million (the “Sentient Loan”) 
from a fund managed by The Sentient Group. On February 11, 2016, Sentient converted approximately $3.9 million of principal plus 
$0.1 million accrued interest under the Sentient Loan into 23,355,000 shares of common stock of the Company at a conversion price 
of approximately $.17 per share. Upon conversion, Sentient holds approximately 49% of the Company’s outstanding common stock. 
After conversion, approximately $1.1 million principal amount under the Sentient Note remains outstanding and due at maturity on 
October 27, 2016.

The Sentient Loan is secured by the stock of the Company’s principal subsidiaries, including subsidiaries that are holding 

companies for or directly own the Velardeña Properties and the El Quevar project. In addition, these and other subsidiaries have 
guaranteed the Sentient Loan. Under the related loan agreement (the “Loan Agreement”), our failure to comply with other covenants 
typical of such loan agreements, or to pay principal and interest when due would also result in an event of default under the Loan 
Agreement.  If we were unable to cure defaults, Sentient could accelerate the maturity of the Sentient Note, foreclose on the stock of 
subsidiaries holding our principal assets, and take action to enforce guarantees against certain of our subsidiaries.

We do not currently have sufficient funds to pay the remaining principal and interest on the Sentient Loan and may not have 

sufficient funds to do so prior to the scheduled maturity of the Sentient Loan.  As a result of exercising its remedies in the event of a 
default, Sentient could acquire directly or indirectly the Company’s principal assets, which would materially and adversely affect the 
Company’s business, financial condition and prospects.

We issued a significant number of shares of common stock upon the partial conversion of the Sentient Note and may issue a 
significant number of additional shares of common stock upon total conversion of the Sentient Note, which could significantly 
dilute our existing stockholders and depress the market price of our common stock.

On February 11, 2016, Sentient converted approximately $3.9 million of principal plus $0.1 million accrued interest under the Sentient 
Loan into 23,355,000 shares of common stock of the Company at a conversion price of approximately $.17 per share. Upon 
conversion of the Sentient Note, Sentient remains the Company’s largest stockholder, holding approximately 49% or 37,578,734 
shares of the Company’s issued and outstanding common stock, which totals 76,690,333 shares of common stock outstanding after 
conversion. After conversion, approximately $1.1 million principal amount under the Sentient Note remains outstanding and due at 
maturity on October 27, 2016.

36

Sentient has the right to convert the remaining principal and accrued interest under the Sentient Note at a conversion price 
equal to the lowest of (i) $0.29, equal to 90 percent of the 15-day volume weighted average price (“VWAP”) of our Common Stock 
for the period immediately preceding the loan closing date, (ii) 90 percent of the 15-day VWAP for the period immediately preceding 
the loan conversion date, or (iii) an anti-dilution adjusted price based on the lowest price for which the Company has sold its stock 
following the borrowing date (subject to certain exceptions set forth in the Sentient Note). If Sentient converts the remaining amount 
of principal and interest due at the loan maturity date, estimated at approximately $1.2 million, at $0.29, Sentient would own 
approximately 55% of the Company’s then outstanding common stock, assuming no other issuances of common stock.  A lower stock 
price prior to the conversion date or the effects of an anti-dilution adjustment in the Sentient Note could further reduce the conversion 
price significantly, and significantly increase the number of shares of common stock issuable on conversion, and Sentient’s resulting 
ownership percentage.

The common stock issuable upon conversion of the Sentient Note may represent overhang that may adversely affect the 

market price of our common stock. Overhang occurs when there is a greater supply of a company’s stock in the market than there is 
demand for that stock. When this happens the price of the company’s stock typically decreases, and any additional shares which 
stockholders attempt to sell in the market further decrease the share price.  $.29 is the highest price at which the Sentient Note may be 
converted.   Decreases in our stock price below $0.29 have the effect of decreasing the conversion price and increasing the number of 
shares to be issued on conversion, which could further decrease our stock price. A significant increase in the number of our 
outstanding shares resulting from conversion of the Sentient Note could exert downward pressure on the market price for our common 
stock and would significantly dilute the voting power of our outstanding common stock.

Whether or not Sentient converts the remaining principal and interest due under the Sentient Note, we will require additional 
funding to support our business, including for general and administrative costs and other working capital needs to fund our continuing 
business activities as currently conducted. Because debt financing is difficult to obtain for early-stage mining companies, it is likely 
that we will seek such financing in the equity markets. If we were to engage in any type of equity financing, the current ownership 
interest of our stockholders would be diluted.

The issuance of a significant number of shares of common stock upon the conversion of the Sentient Note resulted in a change of 
control.

As a result of the February 2016 loan conversion described above, Sentient’s ownership increased from 27% to 49% of the 
Company’s outstanding common stock. If Sentient converts the remaining amount of principal and interest due at the loan maturity 
date, estimated at approximately $1.2 million, at $0.29, Sentient would own approximately 55% of the Company’s then outstanding 
common stock, assuming no other issuances of common stock.  The ownership increase to 49% effectively resulted in a change of 
control of the Company. With this increased ownership, Sentient could exert significant control over the Company, including over the 
election of directors, changes in the size or the composition of the board of directors, and mergers and other business combinations 
involving the Company. Through control of the board of directors and increased voting power, including an ability to prevent a 
quorum at stockholders meetings, Sentient could control certain decisions, including decisions regarding qualification and 
appointment of officers, operations of the business including acquisition or disposition of our assets or purchases and sales of mining 
or exploration properties, dividend policy, and access to capital (including borrowing from third-party lenders and the issuance of 
equity or debt securities).

The existence of a significant number of warrants may have a negative effect on the market price of our common stock.

In connection with our financing in September 2014, we issued warrants to acquire 4,746,000 shares of our common stock at 

$1.21 per share expiring in September 2019. In connection with our financing in September 2012, we issued five year warrants to 
purchase 3,431,649 shares of our common stock at an exercise price of $8.42 per share expiring September 2017. Pursuant to a 
weighted average dilution calculation based on the pricing in the September 2014 financing, the exercise price for the September 2012 
warrants was reduced to $7.17 and the number of shares issuable on exercise of the warrants increased to 4,031,409. As a result of the 
Sentient conversion on February 11, 2016, pursuant to the weighted average dilution calculation in the 2012 and 2014 warrants, (i) the 
exercise price for the September 2012 warrants was further reduced to $5.09 and the number of shares issuable on exercise of the 
warrants increased to 5,677,757, and (ii) the exercise price for the September 2014 warrants was reduced to $0.91 and the number of 
shares issuable on exercise of the warrants increased to 5,365,983. The existence of securities available for exercise and resale is 
referred to as an “overhang,” and, particularly if the warrants are “in the money,” the anticipation of potential sales could exert 
downward pressure on the market price of our common stock.

37

Failure to meet the maintenance criteria of the NYSE MKT may result in the delisting of our common stock, which could result in 
lower trading volumes and liquidity, lower prices of our common shares and make it more difficult for us to raise capital.

Our common stock is listed on the NYSE MKT, and we are subject to its continued listing requirements, including maintaining certain 
share prices and a minimum amount of shareholders equity.  The market price of our common stock has been recently and may 
continue to be subject to significant fluctuation.  If we are unable to comply with the NYSE MKT continued listing requirements, 
including its trading price requirements, our common stock may be suspended from trading on and/or delisted from the NYSE MKT.  
Alternatively, in order to avoid delisting by the NYSE MKT, we may be required to effect a reverse split of our common stock. 
Although we have not been notified of any delisting proceedings, there is no assurance that we will not receive such notice in the 
future or that we will be able to then comply with NYSE MKT listing standards.  The delisting of our common stock from the NYSE 
MKT may materially impair our stockholders’ ability to buy and sell our common stock and could have an adverse effect on the 
market price of, and the efficiency of the trading market for, our common stock. In addition, the delisting of our common stock could 
significantly impair our ability to raise capital.

If our common stock were delisted and determined to be a “penny stock,” a broker-dealer could find it more difficult to trade our 
common stock and an investor may find it more difficult to acquire or dispose of our common stock in the secondary market.

If our common stock were removed from listing on the NYSE MKT, it may be subject to the so-called “penny stock” rules. The SEC 
has adopted regulations that define a “penny stock” to be any equity security that has a market price per share of less than $5.00, 
subject to certain exceptions, such as any securities listed on a national securities exchange. For any transaction involving a “penny 
stock,” unless exempt, the rules impose additional sales practice requirements on broker-dealers, subject to certain exceptions. If our 
common stock were delisted and determined to be a “penny stock,” a broker-dealer may find it more difficult to trade our common 
stock and an investor may find it more difficult to acquire or dispose of our common stock on the secondary market.   These factors 
could significantly negatively affect the market price of our common stock and our ability to raise capital.

ITEM 1B:  UNRESOLVED STAFF COMMENTS

None.

ITEM 3:  LEGAL PROCEEDINGS

None.

ITEM 4:  MINE SAFETY DISCLOSURES

Not applicable.

38

PART II

ITEM 5:  MARKET FOR REGISTRANT’S COMMON EQUITY, RELATED STOCKHOLDER MATTERS AND ISSUER 
PURCHASES OF EQUITY SECURITIES

Our common stock began trading on the NYSE MKT under the symbol “AUMN” on March 19, 2010. The following table 
sets forth the high and low sales prices per share and volume traded on the NYSE MKT from January 1, 2014 through December 31, 
2015.

2014
First Quarter
Second Quarter
Third Quarter
Fourth Quarter

2015
First Quarter
Second Quarter
Third Quarter
Fourth Quarter

High

Low

1.28
1.58
1.59
0.78

0.67
0.49
0.42
0.41

$
$
$
$

$
$
$
$

0.49
0.50
0.57
0.42

0.39
0.32
0.23
0.19

Low

High

$
$
$
$

$
$
$
$

Volume
Traded
(shares)

33,281,000
15,413,700
21,963,800
10,307,300

Volume
Traded
(shares)

6,947,400
4,651,700
5,637,700
6,150,200

Our common stock is also listed on the Toronto Stock Exchange, also referred to as the “TSX”, and trades under the symbol 

“AUM”. The following table sets forth the high and low sales prices per share expressed in Canadian dollars and volume traded on the 
TSX from January 1, 2014 through December 31, 2015.

2014
First Quarter
Second Quarter
Third Quarter
Fourth Quarter

2015
First Quarter
Second Quarter
Third Quarter
Fourth Quarter

High
(Cdn$)(1)

Low
(Cdn$)(1)

$
$
$
$

$
$
$
$

1.42
1.70
1.69
0.91

High
(Cdn$)(1)

0.82
0.64
0.51
0.47

$
$
$
$

$
$
$
$

0.54
0.55
0.65
0.53

Low
(Cdn$)(1)

0.44
0.36
0.31
0.26

Volume
Traded
(shares)

2,556,600
1,543,500
1,377,300
784,900

Volume
Traded
(shares)

917,000
249,900
435,600
825,800

(1)

Prices are in Canadian dollars.

As of February 24, 2016, we had 214 record holders of our common stock of record based upon the stockholders list 

provided by our transfer agent, Computershare Trust Company, N.A.

39

Dividends

We have not declared or paid any cash dividends on our common stock and do not anticipate paying any cash dividends on 

our common stock in the foreseeable future. We currently intend to retain all future earnings, if any, to fund the growth of our 
business.

ITEM 6:  SELECTED CONSOLIDATED FINANCIAL DATA

The selected consolidated financial data for all periods presented has been derived from our audited financial statements for 

that period. Our financial statements are reported in U.S. dollars and have been prepared in accordance with generally accepted 
accounting principles in the United States. The following selected consolidated financial data should be read in conjunction with the 
consolidated financial statements and the related notes thereto and “Management’s Discussion and Analysis of Financial Condition 
and Results of Operations” included in this Form 10-K.

Statement of Operations:

Revenue
Net Loss(1)
Net Loss per common share

Balance Sheet Data:
Total assets
Long term liabilities
Dividends:
Cash dividends declared per common share

2015

The Year Ended December 31,
2012
2014
2013
(in thousands, except per share amounts)

2011

8,071
$
(25,383) $
(0.48) $

$
235
(18,823) $
(0.41) $

10,680
$
(240,380) $
(5.61) $

26,086
$
(92,025) $
(2.45) $

1,836
(62,671)
(2.94)

2015

2014

At December 31,
2013

2012

2011

17.001
2,840

$
$

41,258
4,334

$
$

54,881
2,655

$
$

348,102
49,524

$
$

413,015
59,672

— $

— $

— $

— $

—

$
$
$

$
$

$

(1)

The year ended December 31, 2015 includes a $13.2 million impairment of long-lived assets charge. The impairment charge 
is related to our Velardeña Properties in Mexico and is the result of the shutdown of mining and sulfide processing at the 
Velardeña Properties in November 2015, which was an event requiring an assessment of the recoverability of the Velardeña 
Properties assets. The year ended December 31, 2013 includes a $244.0 million impairment of long-lived assets charge and 
an $11.7 million impairment of goodwill charge. Both charges are related to our Velardeña Properties in Mexico and are the 
result of a significant decrease in metals prices during 2013 and the shutdown of mining and processing at the Velardeña 
Properties at the end of the second quarter 2013, which were events requiring an assessment of the recoverability of the 
Velardeña Properties assets. The year ended December 31, 2012 includes a $58.5 million impairment of goodwill charge 
related to our Velardeña Properties in Mexico and is the result of an approximately 20% decrease in our forecast of future 
gold and silver prices and certain assumptions related to ore processing throughput rates and other aspects of the long-term 
mining plan.

40

ITEM 7:  MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF 
OPERATIONS

You should read the following discussion and analysis of our financial condition and results of operations together with our 

financial statements and related notes beginning on page F-1 in this annual report on Form 10-K. This discussion and analysis 
contains forward-looking statements that involve risks, uncertainties and assumptions. Our actual results may differ materially from 
those anticipated in these forward-looking statements as a result of many factors, including those set forth under “Risk Factors” in 
this annual report on Form 10-K.

Our Company

We were incorporated in Delaware under the Delaware General Corporation Law in March 2009, and are the successor to 

Apex Silver for purposes of reporting under the Exchange Act. During the year ended December 31, 2015, our only sources of income 
were revenues from the sale of lead, zinc and pyrite concentrates from our Velardeña Properties, revenue from the lease of our oxide 
plant, sales of non-core assets, and a tax refund received by a Mexican subsidiary. We incurred net operating losses for the years 
ended December 31, 2015 and 2014.

2015 Highlights

Due to continuing net operating losses, in November 2015 we suspended mining and sulfide processing activities at the 

Velardeña Properties in order to conserve the future value of the asset. We have placed the mine and sulfide processing plant on care 
and maintenance to enable a re-start of either the mine or the mill when mining and processing plans and metals prices support a cash 
positive outlook for the property.  Results for 2015 are summarized below.

On October 27, 2015 the Company closed on a $5.0 million secured convertible loan from The Sentient Group (“Sentient”), 
our largest stockholder.  The proceeds from the loan enabled us to fund the suspension of mining and sulfide processing activities at 
the Velardeña Properties and continue our long term business strategy into 2016.

In July 2015 we entered into a leasing agreement with a third party, which for a monthly fixed fee and a variable tonnage fee 
will allow the third party to control and process its own material through our oxide plant at the Velardeña Properties for a period of up 
to 30 months.  We are primarily focused on evaluating and searching for mining opportunities in North America (including Mexico) 
with high precious metal grades and low development costs with near term prospects of mining, and particularly properties within 
reasonable haulage distances of our Velardeña Properties, which may include the Santa Maria Mine located in the Parral District in 
Chihuahua State, the Santa Rosa vein located in the San Luis de Cordero district in Durango, or the Rodeo property located west of 
the Velardeña Properties in Durango. We also continued to advance certain exploration properties located primarily in Mexico and to 
hold the El Quevar advanced exploration property in Argentina until we can find a partner to further advance the project.  We also 
continue to review strategic opportunities from time to time.

Suspension of Mining and Processing activities at the Velardeña Properties

(cid:120) In November 2015 we suspended mining and sulfide processing activities at our Velardeña Properties in order to conserve 
the asset until we are able to develop mining and processing plans that at then current prices for silver and gold indicate a 
sustainable positive operating margin (defined as revenues less costs of sales) or we are able to locate, acquire and develop 
alternative mineral sources that could be economically mined and transported to the Velardeña Properties for processing.  We 
placed the mine and sulfide processing plant on a care and maintenance program to enable a re-start of either the mine or 
mill.  In the fourth quarter 2015, we incurred approximately $1.2 million in related costs for employee severance, material 
and supplies inventory write downs, and other shutdown expenditures to place the property on care and maintenance, and we 
expect to incur approximately $0.3 million in quarterly holding costs for as long as mining and processing activities remain 
suspended.

Sentient Loan Financing

(cid:120) On October 27, 2015, we borrowed $5.0 million from Sentient, the entire amount available pursuant to the terms of a Senior 
Secured Convertible Note (the “Sentient Note”) and Loan Agreement (the “Sentient Loan”), with principal and accrued 
interest due on October 27, 2016.  We received stockholder approval on January 19, 2016 to allow the Sentient Note principal 
and accrued interest to be converted, solely at Sentient’s option, into shares of the Company’s common stock at a conversion 
price equal to the lowest of: (i) $0.29, 90 percent of the 15-day volume weighted average price (“VWAP”) for the period

41

immediately preceding the loan closing date, (ii) 90 percent of the 15-day VWAP for the period immediately preceding the 
loan conversion date, or (iii) an anti-dilution adjustment price based on the lowest price for which we, if applicable, sell our 
stock following the loan closing date.  The Sentient Loan bears interest at a rate of 9 percent per annum, compounded monthly 
due and payable on the earlier of the conversion date of the loan or at the loan maturity date. The Sentient Loan is subject to 
customary borrower representations, warranties, covenants and default provisions and is secured by ownership in the stock of 
our principal subsidiaries, including the stock in the subsidiaries that own directly or indirectly the Velardeña Properties and 
El Quevar project.

On February 11, 2016, Sentient converted approximately $3.9 million of principal and $0.1 million of accrued interest 
(representing the total amount of accrued interest at the conversion date) into 23,335,000 shares of our common stock at an 
exercise price of approximately $0.172 per share, equal to 90% of the 15-day volume weighted average price (“VWAP”) 
immediately preceding the conversion date.  Following the conversion, approximately $1.1 million of principal remained 
outstanding.  If the remaining principal and additional accrued interest from February 11, 2016 is not converted into our 
common stock, we would owe approximately $1.2 million to Sentient on the October 27, 2016 maturity date.

Mining and Processing activities at the Velardeña Properties

(cid:120) At the Velardeña Properties, during 2015 we generated approximately 465,000 payable silver equivalent ounces, including 

approximately 327,000 ounces of silver and 1,975 ounces of gold, and sold approximately 494,000 silver equivalent ounces.  
Silver equivalent ounces include silver and gold but exclude lead and zinc and are calculated at a ratio of 70 silver ounces to 
1 gold ounce.  Full year 2015 cash costs were $22.16 per payable silver ounce net of by-product credits.  “Cash costs per 
payable silver ounce, net of by-product credits” is a non-GAAP financial measure defined below in “—Non-GAAP Financial 
Measures”.

Velardeña Oxide Plant Lease Agreement

(cid:120)

In July 2015 a wholly-owned subsidiary of Hecla Mining Company leased our Velardeña oxide plant for an initial term of 18 
months beginning July 1, 2015.  Hecla may extend the initial 18 month term for six additional months at its option, and then 
for a subsequent six months unless we elect to use the plant to process material from our own sources.  The lease contains 
typical covenants and termination rights. Hecla is responsible for all costs associated with the start-up, operation and 
maintenance of the oxide plant. Hecla began making nominal monthly payments to us beginning July 1, 2015 and began 
processing material in mid-December, which increased the monthly fixed fee under the lease and commenced variable 
charges for tonnes processed.  Approximately 6,000 tonnes of material were processed at the leased oxide plant in December, 
resulting in revenues of approximately $130,000 in addition to fixed fees and reimbursable expenses totaling approximately 
$520,000.  Once Hecla reaches its intended processing throughput of approximately 400 tonnes per day, monthly cash 
payments to us, net of reimbursable costs, should total approximately $400,000 per month, including variable and fixed fees, 
or nearly $5.0 million annually.

Santa Maria

(cid:120) At the Santa Maria mine west of Hildalgo de Parral, Chihuahua, which we have the right to acquire under an option 

agreement, we continued exploration work during 2015.  During the third quarter we mined approximately 3,000 tonnes of 
material from a mineralized shoot as bulk samples with grades of approximately 500 gpt silver and 0.9 gpt gold.  We do not 
have sufficient drilling data to predict the ultimate size of this higher grade zone.  During the third and fourth quarters of 
2015 we processed the bulk sample through a toll milling facility, generating approximately 113 tonnes of concentrates 
containing approximately 47,000 ounces of silver and 80 ounces of gold.  The concentrates were sold to a third party netting 
proceeds of approximately $370,000 from approximately 32,000 payable ounces of silver and 45 payable ounces of gold, 
which offset exploration costs.

San Luis del Cordero

(cid:120) We recently acquired the mining rights for the Santa Rosa vein in the San Luis del Cordero Project in Durango State, 

Mexico, pursuant to an exploration and exploitation agreement with a wholly-owned Mexican subsidiary of Prospero Silver 
(“Prospero”). The Santa Rosa vein is approximately two meters wide and as currently defined extends for about 400 meters 
on strike.  Records show that the Santa Rosa vein has been mined to a depth of about 100 meters and can be partially 
accessed from historic underground workings. We started a $0.5 million drilling program in February 2016 to test extensions 
of the Santa Rosa vein on strike and to complete infill drilling.  Our objective is to increase the size and upgrade the quality 
of the deposit.  If our exploration results are successful, we expect to issue an NI 43-101 resource estimate and preliminary 
economic analysis in 2016.  The preliminary results of our initial metallurgical testing of material from the Santa Rosa vein 
indicates that the material is suitable for concentration by flotation.

42

If the results of our exploration and metallurgical work are successful, we could mine the vein from the existing underground 
mine following completion of certain rehabilitation and access projects and truck mined material for processing to our 
recently idled Velardena sulfide mill for processing.  We would require external funding to fund capital and working capital 
costs associated with mining the Santa Rosa vein, preliminarily estimated at approximately $3.0 to 4.0 million.

El Quevar

(cid:120) We continue to hold our El Quevar property on care and maintenance while we seek a partner to fund further exploration.

Other Exploration

(cid:120) We completed a 2,000 meter, three-hole drilling program at our 6,200 hectare Celaya project located 45 kilometers southeast 

of and on trend with the historic Guanajuato District of Mexico.  Drilling has identified epithermal gold and silver 
mineralization beneath a portion of the widespread clay-silica alteration on the claims comprising the Celaya project.  The 
Company has entered into discussions with a third party regarding a joint venture farm-out of the project.

(cid:120) We acquired the Rodeo and Rodeo 2 claims comprising 1,866 hectares 80 kilometers west of the Velardeña Properties in 

Durango, Mexico where previous exploration by other companies has identified a gold-bearing epithermal system exposed at 
surface.  We plan to conduct a 2,000 meter core drilling program in 2016 or early 2017 at an estimated cost of $300,000 to 
$400,000.  If our exploration efforts are successful, material from these properties could be trucked to the Velardeña oxide 
plant for processing after the third party lease has terminated.

Results of Operations

For the results of operations discussed below, we compare the results of operations for the year ended December 31, 2015 to 

the results of operations for the year ended December 31, 2014.

Revenue from the sale of metals.  We recorded $7.4 million and $.02 million of revenue for the years ended December 31, 

2015 and 2014, respectively, all from the sale of metals from our Velardeña Properties in Mexico. The amount of revenue in 2014 is 
primarily the result of the suspension of mining and processing at our Velardeña Properties from June 2013 until processing mined 
material resumed in November 2014, and was again suspended in November 2015.

Costs of metals sold.  We recorded $9.9 million and $1.7 million of costs applicable to sales for the years ended 

December 31, 2015 and 2014, respectively. The lower amount of cost of metals sold in 2014 is primarily the result of the absence of 
mining and processing at our Velardeña Properties until mining activity resumed in July 2014 and processing resumed in 
November 2014. Included in costs of metals sold for the period ended December 31, 2014 was a $1.2 million write down of finished 
goods inventory to estimated net realizable value.

Revenue from oxide plant lease.  As discussed above, in July 2015 a third party leased our inactive Velardeña oxide plant. 
We recorded revenue of $0.7 million during the year ended December 31, 2015 related to the lease. The oxide plant was not leased 
during the year ended December 31, 2014.

Oxide plant lease costs.  During the year ended December 31, 2015 we recorded $0.2 million of costs related to the oxide 

plant lease consisting primarily of reimbursable labor and utility costs which for accounting purposes were also included in revenue 
from the oxide plant lease. See Note 4 to the consolidated financial statements for a full description of the accounting treatment. The 
oxide plant was not leased recorded during the year ended December 31, 2014.

Exploration Expense.  Our exploration expense, including property holding costs and allocated administrative expenses, 
totaled $3.6 million for the year ended December 31, 2015, as compared to $5.5 million for the year ended December 31, 2014.  
Exploration expense for both years was incurred primarily in Mexico,  and Argentina, excluding amounts spent at the El Quevar 
project, and includes property holding costs and costs incurred by our local exploration offices. The decrease in exploration expenses 
in 2015 as compared to 2014 was primarily related to the absence in 2015 of the 2014 drilling program at our Velardeña Properties.

Velardeña Project Expense.  During the years ended December 31, 2015 and 2014 we incurred approximately $0.1 million 
and $3.1 million of expenses. The 2015 and 2014 expenses were primarily related to the restart of mining and processing activities in 
2014 and the construction of the San Mateo ramp and other mine construction and engineering work.  In addition to amounts 
expensed, we incurred capital expenditures of approximately $0.5 million in 2014 versus a nominal amount incurred during 2015.

43

Velardeña shutdown and care and maintenance costs.  We recorded $1.2 million and $2.5 million for the years ended 

December 31, 2015 and 2014, respectively, for expenses related to shut down and care and maintenance at our Velardeña Properties. 
We suspended mining and processing activities at the Velardeña Properties from June 2013 until mining activity resumed in July 2014 
and processing mined material resumed in November 2014. We again suspended mining and processing activities at the Velardeña 
Properties in November 2015.

El Quevar Project Expense.  During the years ended December 31, 2015 and 2014 we incurred $1.0 million and $1.6 million 

of expenses, respectively, primarily related to holding costs at our El Quevar project in Argentina. The reduction in costs for 2015 is 
primarily the result of placing the El Quevar project in a holding and maintenance state beginning in 2014.  For both years, costs 
incurred in Argentina and not related to the El Quevar project are included in “—Exploration Expense”, discussed above.

Administrative Expense.  Administrative expenses totaled $4.2 million for the year ended December 31, 2015 compared to 

$4.6 million for the year ended December 31, 2014. Administrative expenses, including costs associated with being a public company, 
are incurred primarily by our corporate activities in support of the Velardeña Properties, El Quevar project and our exploration 
portfolio. The $4.2 million of administrative expenses we incurred during 2015 is comprised of $2.0 million of employee 
compensation and directors’ fees, $1.0 million of professional fees, $1.2 million of insurance, travel expenses, rents, utilities and other 
office costs.  The $4.6 million of administrative expenses we incurred during 2014 is comprised of $1.9 million of employee 
compensation and directors’ fees, $1.2 million of professional fees and $1.5 million of insurance, rents, travel expenses, utilities and 
other office costs.

Stock based compensation.  During the year ended December 31, 2015 we incurred expense related to stock based 
compensation in the amount of $0.5 million compared to $0.9 million for the year ended December 31, 2014. Stock based 
compensation varies from period to period depending on the number and timing of shares granted, the type of grant, the market value 
of the shares on the date of grant and other variables.

Reclamation and accretion expense.  During each of the years ended December 31, 2015 and 2014 we incurred $0.2 million 

of reclamation expense related to the accretion of an asset retirement obligation at the Velardeña Properties.

Impairment of long lived assets and goodwill.  We assess the recoverability of our property, plant and equipment and 

goodwill whenever events or changes in circumstances indicate that the carrying value of the assets may not be recoverable. The 
continued negative operating margin and the suspension of mining and sulfide processing activities at the Velardeña Properties in 
early November 2015 were events that required an assessment of the recoverability of the Velardeña Properties asset group at 
September 30, 2015. We completed an impairment analysis at September 30, 2015 and determined that our mineral and exploration 
properties at the Velardeña Properties were impaired (see Note 3 of our consolidated financial statements). As a result we recorded a 
$13.2 million impairment charge related to long-lived assets.  There were no such charges during the year ended December 31, 2014.

Other Operating Income, Net.  We recorded other operating income of $0.5 million for the year ended December 31, 2015 

compared to $0.7 million for the year ended December 31, 2014. The net amounts for both years consist primarily of net gains 
recorded on the sales of certain fixed assets and non-strategic exploration properties.

Depreciation, depletion and amortization.  During the year ended December 31, 2015 we incurred depreciation, depletion 
and amortization expense of $4.5 million compared to $3.1 million for the year ended December 31, 2014. The 2014 depreciation, 
depletion and amortization includes a $0.6 million write down of finished goods inventory to estimated net realizable. The increase in 
depreciation, depletion and amortization in 2015 is primarily the result of increased mining and processing activities at our Velardeña 
Properties during 2015 as compared to 2014.

Interest expense.  During the year ended December 31, 2015 we recorded approximately $0.1 million of interest expense 
related to the Sentient Loan.  During the year ended December 31, 2014 we had no debt outstanding and consequently no interest 
expense was recorded.

Interest and Other Income.  During the year ended December 31, 2015 we recorded approximately $3.1 million of interest 
and other income which included a $2.1 million reduction of a loss contingency liability related to foreign withholding taxes that the 
government could have asserted were owed by the Company, acting as withholding agent, on certain interest payments made to a third 
party. Interest and other income for 2015 also includes a tax refund received in Mexico of approximately $0.8 million. During the year 
ended December 31, 2014 we recorded approximately $1.7 million of interest and other income primarily related to the reduction of 
the loss contingency.

Warrant Income.  For the years ended December 31, 2015 and 2014 we recorded approximately $1.3 million and $1.7 

million, respectively of other income related to a decrease in the fair value of the liability recorded for warrants to acquire the 
Company’s stock (see Note 14 of our consolidated financial statements). The warrant liability was recorded at fair value as of

44

December 31, 2015 and 2014 based primarily on a valuation performed by a third party expert using a Monte Carlo simulation, which 
falls within Level 3 of the fair value hierarchy.  The valuation method is discussed in detail in Note 14 of our consolidated financial 
statements.

Derivative Income Loss.  The beneficial conversion feature of the Sentient Note represents an imbedded derivative as defined 

by ASC 815. ASC 815 provides that a derivative instrument’s fair value must be bifurcated from the host contract and separately 
recorded on the Company’s Consolidated Balance Sheets.  The Company used a third party consultant to value the imbedded 
derivative in the Sentient Note employing a Monte Carlo type probability analysis, which falls within Level 3 of the fair value 
hierarchy. The valuation method is discussed in detail in Note 14 of our consolidated financial statements. The derivative is recorded 
at fair value with subsequent mark-to-market changes in the value of the derivative recorded as income or loss in the Consolidated 
Statements of Operations. For the year ended December 31, 2015 we recorded a $0.6 million gain loss related to the fair value 
adjustment to the imbedded derivative. For the year ended December 31, 2014 we had no such gain or loss.

Gain (Loss) on Foreign Currency.  We recorded a $0.1 million foreign currency loss for the year ended December 31, 2015 

compared to a $0.1 million foreign currency gain for the year ended December 31, 2014. Foreign currency gains and losses are 
primarily related to the effect of currency fluctuations on monetary assets net of liabilities held by our foreign subsidiaries that are 
denominated in currencies other than US dollars.

Income Taxes.  We recorded no income tax expense or benefit for the years ended December 31, 2015 and 2014.

Liquidity and Capital Resources

At December 31, 2015 our aggregate cash and cash equivalents totaled $4.1 million. With the cash balance at December 31, 

2015 and based on the assumptions described below we expect to have sufficient funds to continue our long term business strategy 
through December 31, 2016.  Our cash and cash equivalents balance at December 31, 2015 of $4.1 million is $4.5 million lower than 
the $8.6 million in similar assets held at December 31, 2014 due primarily to the negative operating margin (defined as revenues less 
costs of sales) at the Velardeña Properties of $2.5 million, $1.2 million in shutdown and care and maintenance costs at the Velardeña 
Properties, $3.6 million in exploration expenditures, $1.1 million in care and maintenance and property holding costs at the El Quevar 
project and $4.2 million in general and administrative expenses, offset in part by $5.0 million in proceeds received from the issuance 
of the Sentient Note, $0.5 of net revenue (defined as revenue less lease costs) received from the lease of the oxide plant to a third 
party, $0.5 million of proceeds from sales of non-strategic property and equipment, $0.8 million received as a tax refund and a $1.3 
million reduction in working capital and other items primarily due to collections of value added tax (“VAT”) receivables, and a net 
decrease in working capital consisting of trade receivables, inventories and accounts payable associated with the shutdown of mining 
and processing activities at the Velardeña Properties.

With the cash balance at December 31, 2015 of $4.1 million and assuming that we receive $4.8 million of net cash flow from 
the lease of the oxide plant in 2016 and that the remaining principal and interest under the Sentient Note is fully converted into shares 
of the Company’s common stock at or prior to maturity on October 27, 2016, we plan to spend the following amounts totaling 
approximately $8.4 million during the full year 2016, resulting in a balance of cash and cash equivalents at December 31, 2016 of 
approximately $0.5 million.

(cid:120) Approximately $1.2 million at the Velardeña Properties for care and maintenance;

(cid:120) Approximately $0.8 million on other exploration activities and property holding costs related to the Company’s portfolio of 

exploration properties located primarily in Mexico;

(cid:120) Approximately $0.5 million at the El Quevar project to fund ongoing maintenance activities, property holding costs, and 

continuing project evaluation costs;

(cid:120) Approximately $1.4 million in exploration, project assessment, and development costs relating to the newly acquired San 

Luis del Cordero property and other properties;

(cid:120) Approximately $3.4 million on general and administrative costs; and

(cid:120) Approximately $1.1 million on an increase in working capital primarily related to a reduction in current liabilities, including 
an advanced payment of $0.5 million received in 2015 from the oxide plant lease and the payment of $0.4 million in equity 
taxes owed in a foreign jurisdiction.

45

The actual amount that we spend during 2016 and the projected yearend cash balance may vary significantly from the 

amounts specified above and will depend on a number of factors, including variations from anticipated care and maintenance costs at 
the Velardeña Properties and costs for continued exploration, project assessment, and development at our other exploration properties, 
including San Luis del Cordero.

On February 11, 2016, Sentient converted approximately $3.9 million of principal and $0.1 million of accrued interest 

(representing the total amount of accrued interest at the conversion date) into 23,335,000 shares of our common stock at an exercise 
price of approximately $0.172 per share, reflecting 90% of the 15-day volume weighted average price (“VWAP”) immediately 
preceding the conversion date.  Following the conversion, approximately $1.1 million of principal remained outstanding.  If the 
remaining principal and additional accrued interest from February 11, 2016 is not converted into our common stock, we would owe 
approximately $1.2 million to Sentient on the October 27, 2016 maturity date.

We do not currently expect we will generate sufficient funds internally to pay the remaining principal and interest on the Sentient 
Loan when it becomes due on October 27, 2016.  We plan, and are required by the Loan Agreement, to seek external funding through 
the sale of equity or securities convertible into equity.  There can be no assurance that we will be successful in obtaining sufficient 
external funding on terms acceptable to us or at all.  If the Sentient Note is converted in full, the Company’s projected cash balance at 
year-end of 2015 and the anticipated net cash flow from the oxide plant lease should provide adequate funds to continue our business 
plans through 2016.

The financial statements have been prepared on a going concern basis under which an entity is considered to be able to 

realize its assets and satisfy its liabilities in the normal course of business.  However, the continuing operations are dependent upon 
our ability to secure sufficient funding and to generate future profitable operations.  The underlying value and recoverability of the 
amounts shown as property, plant and equipment in Note 9 of our consolidated financial statements are dependent on our ability to 
generate positive cash flows from operations and to continue to fund exploration and development activities that would lead to 
profitable mining activities or to generate proceeds from the disposition of property, plant and equipment.  There can be no assurance 
that we will be successful in generating future profitable operations or securing additional funding in the future on terms acceptable to 
us or at all.  These material uncertainties, including repayment of the Sentient Loan, may cast significant doubt on our ability to 
continue as a going concern.  These consolidated financial statements do not include any adjustments relating to the recoverability and 
classification of recorded assets or liabilities which might be necessary should we not be able to continue as a going concern.

Non-GAAP Financial Measures

Cash costs, net of by-product credits, per payable ounce of silver is a non-GAAP financial measure that is widely used in the 

mining industry. Under generally accepted accounting principles in the United States (GAAP), there is no standardized definition of 
cash cost, net of by-product credits, per payable ounce of silver, and therefore our forecasted cash costs may not be comparable to 
similar measures reported by other companies.

The full year 2015 cash costs of $22.16 for the Velardeña Properties include all direct and indirect costs associated with the 

physical activities that would generate concentrate products for sale to customers, including mining to gain access to mineralized 
materials, mining of mineralized materials and waste, milling, third-party related treatment, refining and transportation costs, on-site 
administrative costs and royalties. Cash costs do not include depreciation, depletion, amortization, exploration expenditures, 
reclamation and remediation costs, sustaining capital, financing costs, income taxes, or corporate general and administrative costs not 
directly or indirectly related to the Velardeña Properties. By-product credits include revenues from gold, lead and zinc contained in the 
products sold to customers during the period. Cash costs, after by-product credits, are divided by the number of payable silver ounces 
generated by the plant for the period to arrive at cash costs, after by-product credits, per payable ounce of silver.

The following table sets forth the cash costs, net of by-product credits, per payable ounce of silver calculation:

46

Twelve months ended December 31, 2015

Cash costs
Silver treatment and refining charges (included in sale of metals 

above)

By-product credits (included in sale of metals above)

Gold
Lead
Zinc
Cash costs, net of by-product credits (1)

Cash cost per unit

Payable silver ounces generated

Cash costs
Treatment and refining charges
By-product credits
Cash costs, net of by-product credits, per payable ounce of 

silver (1)

$

$

$

$

Cash Costs, Net of By-product Credits,
Per Payable Ounce of Silver (1)
(in thousands except per unit amounts)

9,363

778

(2,195)
16
(724)
7,238

326,651
28.66
2.38
(8.89)

22.16

(1) Cash costs, net of by-product credits, per payable ounce of silver is a non-GAAP financial measure defined 

below

We provide cash costs, after by-product credits to provide additional information regarding the performance of the Velardeña 

Properties, and believe the use of this measure provides investors with useful information about the underlying costs of our mining 
activities. Cash costs, after by-product credits, is an important statistic that the Company uses to measure the Velardeña Properties’
performance. It also allows us to benchmark the performance of the Velardeña Properties against those operations of our competitors. 
The statistic is also useful in identifying acquisition and investment opportunities since it provides a common tool for measuring the 
financial performance of other mines with varying geologic, metallurgical and mining and processing characteristics.

Cost of sales is the most comparable financial measure, calculated in accordance with GAAP, to cash costs. As compared to 

cash costs, cost of sales includes adjustments for changes in inventory and excludes net revenue from by-products and third-party 
related treatment, refining and transportation costs, which are reported as part of revenue in accordance with GAAP.

The following table presents a reconciliation for the year ended December 31, 2015 between the non-GAAP measure of cash 

cost, net of by-product credits, per payable ounce of silver, to the most directly comparable GAAP measure, cost of metals sold.

The Year Ended December 31, 2015

Cash costs
Reconciliation to GAAP

Change in inventory (excluding depreciation, depletion and 

amortization)
Cost of metals sold

$

$

Critical Accounting Policies and Estimates

Reconciliation of Costs of Metals Sold (GAAP)
to Cash Costs (Non-GAAP)
(in thousands)

9,363

503
9,866

The selection and application of accounting policies is an important process that has developed as our business activities have 

evolved and as the accounting rules have changed. Accounting rules generally do not involve a selection among alternatives, but 
involve an implementation and interpretation of existing rules, and the use of judgment, to the specific set of circumstances existing in 
our business. Discussed below are the accounting policies that we believe are critical to our financial statements due to the degree of 
uncertainty regarding the estimates or assumptions involved and the magnitude of the asset, liability, revenue or expense being 
reported.

47

Mineral Reserves

When and if we determine that a mineral property has proven and probable reserves, subsequent development costs are 

capitalized to mineral properties. When mineral properties are developed and operations commence, capitalized costs are charged to 
operations using the units-of-production method over proven and probable reserves. “Mineralized material” as used in this annual 
report, although permissible under SEC’s Industry Guide 7, does not indicate “reserves” by SEC standards, and therefore all 
development costs incurred by us are expensed when incurred. The Company cannot be certain that any part of the deposits at the 
Velardeña Properties or the Yaxtché deposit at the El Quevar project will ever be confirmed or converted into SEC Industry Guide 7 
compliant “reserves”.

Asset Retirement Obligations

We record asset retirement obligations in accordance with Auditing Standards Codification (“ASC”) 410, “Asset Retirement 
and Environmental Obligations” (“ASC 410”), which establishes a uniform methodology for accounting for estimated reclamation and 
abandonment costs. According to ASC 410, the fair value of a liability for an asset retirement obligation (“ARO”) is recognized in the 
period in which it is incurred if a reasonable estimate of fair value can be made. An offsetting asset retirement cost is capitalized as 
part of the carrying value of the assets with which it is associated, and depreciated over the useful life of the asset.

Long Lived Assets

We assess the recoverability of our long lived assets whenever events or changes in circumstances indicate that the carrying 

value of the assets may be impaired.  Prices for silver during the first three quarters of 2015 remained well below year to date 2015 
cash costs per payable silver ounce, net of by-product credits, at the Velardeña Properties, generating negative operating margin 
through September 30, 2015.  “Cash costs per payable silver ounce, net of by-product credits” is a non-GAAP financial measure 
defined in “—Non-GAAP Financial Measures”.  Ongoing efforts during 2015 to improve the grade of mined material delivered to the 
sulfide plant for processing by limiting dilution in the stopes did not improve grades to a level sufficient to generate positive operating 
margins at current metals prices.  As a result, the Company suspended mining and processing activities at the Velardeña mine and 
sulfide plant during November 2015.

The Velardeña Properties consists of two separate asset groups, one involving the oxide plant, which has been leased to a 

third party, and the other involving the mineral and exploration properties, sulfide plant, and mining and other equipment and working 
capital related to the mining and processing activities at the Velardeña Properties (the “Mineral Properties Asset Group”).  The 
continued negative operating margin and the suspension of mining and sulfide processing activities at the Velardeña Properties during 
November 2015 were events that required an assessment of the recoverability of the carrying value of the Mineral Properties Asset 
Group at September 30, 2015. Per the guidance of ASC 360, “Property, Plant and Equipment”, recoverability of an asset group is not 
achieved if the projected undiscounted, pre-tax cash flows related to the asset group are less than its carrying amount. In its analysis of 
projected cash flows for the Mineral Properties Asset Group, the Company determined that the Mineral Properties Asset Group was 
impaired. As a result, at September 30, 2015 the Company recorded impairment charges totaling $13.2 million to arrive at a remaining 
book value for the Mineral Properties Asset Group of $3.7 million at September 30, 2015.

Table of Contractual Obligations

The following table summarizes our contractual obligations at December 31, 2015:

Contractual Obligations

Total

Less Than
1 Year

1 - 3
Years
(in thousands of $)

3 - 5
Years

More
Than
5 Years

Operating leases(1)
El Quevar and Velardeña 
concession payments(2)

1,149

770

285

154

589

308

275

308

—

—(3)

(1)

(2)

The operating lease obligations are related to our corporate headquarters office in Golden, Colorado, which 
expires November 30, 2019, as well as another office lease associated with our Velardeña Properties.

We expect to make annual maintenance payments of approximately $15,000 to the Mexico federal 
government to maintain the Velardeña Properties concessions and $25,000 to maintain related surface rights 
under a contract with the local community ejido. In  2016 and subsequent years, we expect to pay

48

approximately $114,000 per year to the Argentina federal government as a result of an amendment to the 
National Mining Code effective January 2015, increasing the annual payment by approximately four times.

(3)

We cannot currently estimate the life of the Velardeña Properties or El Quevar project. This table assumes 
that no annual maintenance payments will be made more than five years after December 31, 2015. If we have 
mining and processing activities at the Velardeña Properties beyond five years, we expect that we would make 
annual maintenance payments of approximately $15,000 per year for the life of the Velardeña mine. If we 
continue to construct a mine at the El Quevar project, we expect that we would make annual maintenance 
payments of approximately $114,000 per year for the life of the El Quevar mine.

From time to time we enter into lease or option agreements related to exploration properties that are of interest to us. These 

agreements typically contain escalating payments required to maintain our exploration rights to the property. Such agreements are not 
included in the above table because exploration success is historically low and we have the right to terminate the agreements at any 
time.

Off-Balance Sheet Arrangements

We do not have any off balance sheet arrangements.

ITEM 7A:  QUANTITATIVE AND QUALITATIVE DISCLOSURES ABOUT MARKET RISK

Interest Rate Risk

We invest substantially all of our excess cash in U.S. government and debt securities rated “investment grade” or better. The 

rates received on such investments may fluctuate with changes in economic conditions. Based on the average cash, restricted cash, 
investments and restricted investment balances outstanding during the year ended December 31, 2015, a 1.0% decrease in interest 
rates would have resulted in a reduction in interest income for the period of less than approximately $0.1 million.

Foreign Currency Exchange Risk

Although most of our expenditures are in U.S. dollars, certain purchases of labor, supplies and capital assets are denominated 

in other currencies. As a result, currency exchange fluctuations may impact the costs of our mining and exploration activities. To 
reduce this risk, we maintain minimum cash balances in foreign currencies and complete most of our purchases in U.S. dollars.

Commodity Price Risk

We are primarily engaged in the exploration and mining of properties containing silver, gold, zinc, lead and other minerals. 
As a result, decreases in the price of any of these metals have the potential to negatively impact our ability to establish reserves and 
mine on our properties. For further detail regarding the effect on our expected cash flow from fluctuations in silver and gold prices, 
see “Item 7: Management’s Discussion and Analysis—Liquidity and Capital Resources” above.

ITEM 8:  FINANCIAL STATEMENTS AND SUPPLEMENTARY DATA

The consolidated financial statements and supplementary information filed as part of this Item 8 are listed under 
Part IV, Item 15, “Exhibits, Financial Statement Schedules” and contained in this annual report on Form 10-K at page F-1.

ITEM 9:  CHANGES IN AND DISAGREEMENTS WITH ACCOUNTANTS ON ACCOUNTING AND FINANCIAL 
DISCLOSURE

None.

ITEM 9A:  CONTROLS AND PROCEDURES

Disclosure Controls and Procedures

The management of Golden Minerals Company has evaluated, under the supervision and with the participation of our Chief 

Executive Officer and Chief Financial Officer, the effectiveness of our disclosure controls and procedures as of December 31, 2015.

49

Based on that evaluation, the Chief Executive Officer and Chief Financial Officer have concluded that, as of December 31, 
2015, our disclosure controls and procedures (as defined in Rules 13a-15(e) and 15d-15(e) under the Exchange Act) were effective 
and designed to provide reasonable assurance that (i) information required to be disclosed in our reports filed under the Exchange Act 
is recorded, processed, summarized and reported within the time periods specified in the SEC’s rules and forms, and (ii) information is 
accumulated and communicated to management, including the Chief Executive Officer and Chief Financial Officer, as appropriate to 
allow timely decisions regarding required disclosures.

The management of Golden Minerals, including the Chief Executive Officer and Chief Financial Officer, does not expect that 

our disclosure controls and procedures or our internal control over financial reporting will prevent all errors and all fraud. A control 
system, no matter how well conceived and operated, can provide only reasonable, not absolute, assurance that the objectives of the 
control system are met.

Further, the design of a control system must reflect the fact that there are resource constraints and the benefits of controls 
must be considered relative to their costs. Because of the inherent limitations in all control systems, no evaluation of controls can 
provide absolute assurance that all control issues and instances of fraud, if any, within the Company have been detected.

Management’s Report on Internal Control over Financial Reporting

Management is responsible for establishing and maintaining adequate internal control over financial reporting (as defined in 

Rule 13a-15(f) under the Exchange Act). Under the supervision and with the participation of management, including our Chief 
Executive Officer and Chief Financial Officer, we assessed the effectiveness of our internal control over financial reporting as of 
December 31, 2015. In making this assessment, management used the criteria set forth by the Committee of Sponsoring Organizations 
of the Treadway Commission (COSO) in Internal Control—Integrated Framework. Based on our assessment, management has 
concluded that, as of December 31, 2015, our internal control over financial reporting is effective based on these criteria.

Changes in Internal Control over Financial Reporting

There have been no changes in the Company’s internal control over financial reporting during the year  ended December 31, 

2015 that have materially affected, or are reasonably likely to materially affect, the Company’s internal control over financial 
reporting.

ITEM 9B:  OTHER INFORMATION

None.

50

ITEM 10:  DIRECTORS, EXECUTIVE OFFICERS AND CORPORATE GOVERNANCE

PART III

For Information regarding our executive officers, see “Items 1 and 2: Business and Properties—Executive Officers of Golden 

Minerals” and “Items 1 and 2: Business and Properties—Board of Directors of Golden Minerals.”

Additional information is incorporated by reference from the information in our proxy statement for the 2016 Annual 

Meeting of Stockholders, which we will file with the Securities and Exchange Commission within 120 days of the end of the fiscal 
year to which this report relates.

We have adopted a code of ethics that applies to all of our employees, including the principal executive officer, principal 

financial officer, principal accounting officer, and those of our officers performing similar functions. The full text of our code of ethics 
can be found on the Corporate Governance page on our website. In the event our Board of Directors approves an amendment to or 
waiver from any provision of our code of ethics, we will disclose the required information pertaining to such amendment or waiver on 
our website.

ITEM 11:  EXECUTIVE COMPENSATION

Incorporated by reference from the information in our proxy statement for the 2016 Annual Meeting of Stockholders, which 

we will file with the Securities and Exchange Commission within 120 days of the end of the fiscal year to which this report relates.

ITEM 12:  SECURITY OWNERSHIP OF CERTAIN BENEFICIAL OWNERS AND MANAGEMENT AND RELATED 
STOCKHOLDER MATTERS

Incorporated by reference from the information in our proxy statement for the 2016 Annual Meeting of Stockholders, which 

we will file with the Securities and Exchange Commission within 120 days of the end of the fiscal year to which this report relates.

ITEM 13:  CERTAIN RELATIONSHIPS AND RELATED TRANSACTIONS, AND DIRECTOR INDEPENDENCE

Incorporated by reference from the information in our proxy statement for the 2016 Annual Meeting of Stockholders, which 

we will file with the Securities and Exchange Commission within 120 days of the end of the fiscal year to which this report relates.

ITEM 14:  PRINCIPAL ACCOUNTING FEES AND SERVICES

Incorporated by reference from the information in our proxy statement for the 2016 Annual Meeting of Stockholders, which 

we will file with the Securities and Exchange Commission within 120 days of the end of the fiscal year to which this report relates.

ITEM 15:  EXHIBITS, FINANCIAL STATEMENT SCHEDULES

PART IV

(a)

Documents filed as part of this annual report on Form 10-K or incorporated by reference:

(1)

(2)

Our consolidated financial statements are listed on the “Index to Financial Statements” on Page F-1 to this 
report.

Financial Statement Schedules (omitted because they are either not required, are not applicable, or the 
required information is disclosed in the notes to the financial statements or related notes).

(3)

The following exhibits are filed with this annual report on Form 10-K or incorporated by reference.

51

Exhibit
Number

1.1

1.2

3.1

3.2

3.3

4.1

EXHIBITS

Description

Underwriting Agreement between Golden Minerals Company and Wells Fargo Securities, LLC dated as of 
September 13, 2012.(1)

Underwriting Agreement between Golden Minerals Company and Roth Capital Partners, LLC, dated as of 
September 5, 2014.(11)

Amended and Restated Certificate of Incorporation of Golden Minerals Company.(2)

First Amendment to the Amended and Restated Certificate of Incorporation of Golden Minerals Company.(3)

Bylaws of Golden Minerals Company.(2)

Specimen of Common Stock Certificate.(4)

4.2 Warrant Agreement by and between Golden Minerals Company and Computershare Trust Company N.A. dated as of 

September 19, 2012.(1)

4.3 Warrant by and between Golden Minerals Company and Sentient Global Resources Fund IV, L.P. dated as of 

September 19, 2012.(1)

4.4 Warrant Agreement by and between Golden Minerals Company and Computershare Trust Company N.A. dated as of 

September 10, 2014 (Public Offering). (11)

4.5 Warrant Agreement by and between Golden Minerals Company and Computershare Trust Company N.A. dated as of 

September 10, 2014 (Sentient Private Placement). (12)

10.1

Form of Indemnification Agreement.(2)

10.2

Form of Change of Control Agreement.(2)

10.3

Amendment No. 1 to Change of Control Agreement.(5)

10.4

Golden Minerals Company Amended and Restated 2009 Equity Incentive Plan.(6)

10.5

Form of Restricted Stock Award Agreement Pursuant to the 2009 Equity Incentive Plan.(7)

10.6

Non-Employee Directors Deferred Compensation and Equity Award Plan.(7)

10.7

10.8

10.9

10.10

10.11

Form of Non-Qualified Stock Option Award Agreement Pursuant to the Amended and Restated 2009 Equity 
Incentive Plan.(8)

Registration Rights Agreement by and among Golden Minerals Company, Sentient Global Resources Fund III, L.P., 
SGRF III Parallel I, L.P. and Sentient Global Resources Fund IV, L.P. dated as of October 7, 2011.(9)

Registration Rights Agreement between Golden Minerals Company and Sentient Global Resources Fund IV, L.P. 
dated as of September 19, 2012.(1)

Subscription Agreement between Golden Minerals Company and Sentient Global Resources Fund IV, L.P. dated as 
of September 10, 2014.(12)

Registration Rights Agreement between Golden Minerals Company and Sentient Global Resources Fund IV, L.P. 
dated as of September 10, 2014.(11)

10.12

Golden Minerals Company 2013 Key Employee Long-Term Incentive Plan.(10)

52

Exhibit
Number

Description

10.13 Master Agreement and Lease Agreement, dated as of July 1, 2015, by and between Minera William S.A de C.V. and 

Minera Hecla, S.A. de C.V. (13)

10.14

10.15

10.16

Contract of Mining Exploration and Exploitation, dated as of November 13, 2015, by and between Minera William 
S.A. de C.V. and Minera Fumarola, S.A. de C.V, a wholly owned subsidiary of Prospero Silver Corp. (14)

Loan Agreement, dated as of October 27, 2015, by and between Golden Minerals Company and Sentient Global 
Resources Fund IV, L.P. (15)

Senior Secured Convertible Note, dated as of October 27, 2015, by and between Golden Minerals Company and 
Sentient Global Resources Fund IV, L.P. (15)

10.17

Form of Change of Control Benefit Waiver Agreements entered into October 27, 2015. (15)

10.18

Registration Rights Agreement between Golden Minerals Company and Sentient Global Resources Fund IV, L.P. 
dated as of February 11, 2016.(16)

21.1

Subsidiaries of the Company.*

23.1

Consent of EKS&H, LLLP.*

23.2

Consent of Tetra Tech.*

23.3

Consent of RungePincockMinarco.*

31.1

31.2

32.1

Certification of Chief Executive Officer of Periodic Report Pursuant to Rule 13a-14(a) and Rule 15d-14
(a) (Section 302 of the Sarbanes-Oxley Act of 2002).*

Certification of Chief Financial Officer of Periodic Report Pursuant to Rule 13a-14(a) and Rule 15d-14
(a) (Section 302 of the Sarbanes-Oxley Act of 2002).*

Certificate of Principal Executive Officer and Principal Financial Officer pursuant to 18 U.S.C. 1350 (Section 906 of 
the Sarbanes-Oxley Act of 2002).**

101.INS

XBRL Instance Document*

101.SCH

XBRL Taxonomy Extension Schema Document*

101.CAL

XBRL Taxonomy Calculation Linkbase Document*

101.DEF

XBRL Taxonomy Definition Document*

101.LAB

XBRL Taxonomy Label Linkbase Document*

101.PRE

XBRL Taxonomy Presentation Linkbase Document*

(1)

(2)

(3)

(4)

(5)

Incorporated by reference to our Current Report on Form 8-K filed September 19, 2012.

Incorporated by reference to our Current Report on Form 8-K filed March 30, 2009.

Incorporated by reference to our Current Report on Form 8-K filed September 9, 2011.

Incorporated by reference to our Form S-1/A Registration Statement filed November 16, 2009.

Incorporated by reference to our Current Report on Form 8-K filed May 28, 2013.

53

(6)

(7)

(8)

(9)

Incorporated by reference to our Quarterly Report on Form 10-Q filed August 6, 2014.

Incorporated by reference to our Quarterly Report on Form 10-Q filed August 10, 2009.

Incorporated by reference to our Quarterly Report on Form 10-Q filed May 4, 2010.

Incorporated by reference to our Current Report on Form 8-K filed October 11, 2011.

(10)

Incorporated by reference to our Current Report on Form 8-K filed December 18, 2013.

(11)

Incorporated by reference to our Current Report on Form 8-K filed September 10, 2014.

(12)

(13)

Incorporated by reference to our Quarterly Report on Form 10-Q filed November 6, 2014.

Incorporated by reference to our Current Report on Form 8-K filed July 20, 2015.

(14)

Incorporated by reference to our Current Report on Form 8-K filed on November 18, 2015.

(15)

Incorporated by reference to our Quarterly Report on Form 10-Q filed on November 16, 2015.

(16)

Incorporated by reference to our Current Report on Form 8-K filed on February 18, 2016.

*
**

Filed herewith.
Furnished herewith.

54

Pursuant to the requirements of Section 13 or 15(d) of the Securities Exchange Act of 1934, the registrant has duly caused 

this report to be signed on its behalf by the undersigned, thereunto duly authorized.

SIGNATURES

Dated: February 25, 2016

GOLDEN MINERALS COMPANY 
Registrant

By:

/s/ WARREN M. REHN
Warren M. Rehn
President and Chief Executive Officer

Pursuant to the requirements of the Securities Exchange Act of 1934, this report has been signed below by the following 

persons on behalf of the registrant and in the capacities and on the dates indicated.

Signature

Title

Date

/s/ WARREN M. REHN
Warren M. Rehn

President and Chief Executive Officer (Principal Executive 
Officer)

February 25, 2016

/s/ ROBERT P. VOGELS
Robert P. Vogels

Senior Vice President and Chief Financial Officer (Principal 
Financial and Accounting Officer)

February 25, 2016

/s/ JEFFREY G. CLEVENGER
Jeffrey G. Clevenger

/s/ W. DURAND EPPLER
W. Durand Eppler

/s/ MICHAEL T. MASON
Michael T. Mason

/s/ IAN MASTERTON-HUME
Ian Masterton-Hume

/s/ KEVIN R. MORANO
Kevin R. Morano

/s/ TERRY M. PALMER
Terry M. Palmer

/s/ ANDREW N. PULLAR
Andrew N. Pullar

/s/ DAVID H. WATKINS
David H. Watkins

Chairman of the Board of Directors

February 25, 2016

Director

Director

Director

Director

Director

Director

Director

55

February 25, 2016

February 25, 2016

February 25, 2016

February 25, 2016

February 25, 2016

February 25, 2016

February 25, 2016

GOLDEN MINERALS COMPANY
FINANCIAL STATEMENTS AND SUPPLEMENTARY DATA INDEX

Report of Independent Registered Public Accounting Firms

Consolidated Balance Sheets at December 31, 2015 and 2014

Consolidated Statements of Operations and Comprehensive Loss for the years ended December 31, 2015 and 
December 31, 2014

Consolidated Statements of Changes in Equity for the years ended December 31, 2015 and December 31, 2014

Consolidated Statements of Cash Flows for the years ended December 31, 2015 and December 31, 2014

Notes to the Consolidated Financial Statements

F-1

Page

F-2

F-3

F-4

F-5

F-6

F-7

REPORT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM

Board of Directors and Stockholders
Golden Minerals Company
Golden, Colorado

We have audited the consolidated accompanying balance sheets of Golden Minerals Company and subsidiaries (the “Company”) as of 
December 31, 2015 and 2014, and the related consolidated statements of operations and comprehensive loss, changes in equity, and 
cash flows for the years then ended. The Company’s management is responsible for these financial statements. Our responsibility is to 
express an opinion on these financial statements based on our audits.

We conducted our audits in accordance with the standards of the Public Company Accounting Oversight Board (United States). Those 
standards require that we plan and perform the audit to obtain reasonable assurance about whether the financial statements are free of 
material misstatement. The company is not required to have, nor were we engaged to perform, an audit of its internal control over 
financial reporting. Our audit included consideration of internal control over financial reporting as a basis for designing audit 
procedures that are appropriate in the circumstances, but not for the purpose of expressing an opinion on the effectiveness of the 
company’s internal control over financial reporting. Accordingly, we express no such opinion. An audit also includes examining, on a 
test basis, evidence supporting the amounts and disclosures in the financial statements, assessing the accounting principles used and 
significant estimates made by management, as well as evaluating the overall financial statement presentation. We believe that our 
audits provide a reasonable basis for our opinion.

In our opinion, the financial statements referred to above present fairly, in all material respects, the financial position of Golden 
Minerals Company and subsidiaries as of December 31, 2015 and 2014, and the results of their operations and their cash flows for the 
years then ended in conformity with accounting principles generally accepted in the United States of America.

The accompanying financial statements have been prepared assuming that the Company will continue as a going concern. The 
Company has experienced recurring losses and has a working capital deficit at December 31, 2015. As discussed in Note 2 to the 
financial statements, management does not expect the Company will have sufficient funds to pay principal and interest on a 
convertible note due October 27, 2016, raising substantial doubt about the Company’s ability to continue as a going concern. 
Management’s plans in regard to these matters are also described in Note 2. The financial statements do not include any adjustments 
that might result from the outcome of this uncertainty.

EKS&H LLLP

February 25, 2016
Denver, Colorado

F-2

GOLDEN MINERALS COMPANY
CONSOLIDATED BALANCE SHEETS
(Expressed in United States dollars)

Assets
Current assets

Cash and cash equivalents (Note 5)
Short-term investments (Note 5)
Trade receivables
Inventories (Note 7)
Value added tax receivable (Note 8)
Prepaid expenses and other assets (Note 6)

Total current assets

Property, plant and equipment, net (Note 9)

Total assets

Liabilities and Equity
Current liabilities

Accounts payable and other accrued liabilities (Note 10)
Convertible note payable (Note 11)
Derivative liability (Note 11)
Deferred revenue (Note 17)
Other current liabilities (Note 13)

Total current liabilities

Asset retirement and reclamation liabilities (Note 12)
Warrant liability (Note 14)
Other long term liabilities (Note 13)

Total liabilities

Commitments and contingencies (Note 21)
Equity (Note 16)

Common stock, $.01 par value, 100,000,000 shares authorized; 53,335,333 and 53,162,833 

shares issued and outstanding, respectively

Additional paid in capital
Accumulated deficit
Accumulated other comprehensive income loss

Shareholders’ equity
Total liabilities and equity

The accompanying notes form an integral part of these consolidated financial statements.

F-3

December 31,
2015

December 31,
2014

(in thousands, except share data)

$

$

$

$

$

$

$

4,077
72
546
330
400
451
5,876
11,125
17,001

1,144
3,702
488
500
556
6,390
2,546
210
84
9,230

8,579
—
—
1,497
1,316
835
12,227
29,031
41,258

1,639
—
—
—
2,551
4,190
2,685
1,554
95
8,524

534
484,742
(477,378)
(127)
7,771
17,001

$

532
484,197
(451,995)
—
32,734
41,258

GOLDEN MINERALS COMPANY
CONSOLIDATED STATEMENTS OF OPERATIONS AND COMPREHENSIVE LOSS
(Expressed in United States dollars)

The Years Ended December 31,

2015

2014

(in thousands except per share data)

Revenue:

Sale of metals (Note 17)
Oxide plant lease (Note 17)

Total revenue

Costs and expenses:

Cost of metals sold (exclusive of depreciation shown below) (Note 17)
Oxide plant lease costs (Note 17)
Exploration expense
El Quevar project expense
Velardeña project expense
Velardeña shutdown and care & maintenance costs
Administrative expense
Stock based compensation
Reclamation expense
Impairment of long lived assets (Note 3)
Other operating income, net
Depreciation, depletion and amortization

Total costs and expenses

Loss from operations

Other income and (expenses):
Interest expense (Note 11)
Interest and other income (Note 18)
Warrant derivative income (Note 19)
Derivative income (Note 19)
Gain (loss) on foreign currency

Other total income, net
Loss before income taxes
Income taxes (Note 15)
Net loss

Other comprehensive loss:

Unrealized loss on securities, net of tax
Comprehensive loss

Net loss per common share — basic (1)

Loss

Weighted average Common Stock outstanding - basic (1)

$

$

7,418
653
8,071

(9,866)
(199)
(3,634)
(1,042)
(119)
(1,228)
(4,242)
(453)
(256)
(13,181)
471
(4,480)
(38,229)
(30,158)

(126)
3,083
1,344
553
(79)
4,775
(25,383)
—
(25,383) $

(127) $
(25,510) $

235
—
235

(1,655)
—
(5,528)
(1,597)
(3,126)
(2,457)
(4,642)
(926)
(199)
—
691
(3,128)
(22,567)
(22,332)

—
1,708
1,693
—
108
3,509
(18,823)
—
(18,823)

—
(18,823)

$

$
$

$

(0.48) $

52,972,352

(0.41)
45,862,419

(1)  Potentially dilutive shares have not been included because to do so would be anti-dilutive

The accompanying notes form an integral part of these consolidated financial statements

F-4

GOLDEN MINERALS COMPANY
CONSOLIDATED STATEMENTS OF CHANGES IN EQUITY
(Expressed in United States dollars)

Common Stock

Shares

Amount

Additional
Paid-in
Capital

Accumulated
Deficit

Accumulated
Other
Comprehensive
income
(loss)

Total
Equity

(in thousands except share data)
$

$

(448,626) $

494,647
924
12

Balance, December 31, 2013
Stock compensation accrued
KELTIP mark-to-market
Registered offering stock units, net 

(Note 16)

Private placements stock units, net 

(Note 16)

Reclassification to reflect warrant 

liability (Note 16)

Net loss
Balance, December 31, 2014
Stock compensation accrued
KELTIP mark-to-market
KELTIP shares issued
Unrealized loss on marketable 
equity securities, net of tax

Net loss
Balance, December 31, 2015

$

43,530,833
140,000
—

3,692,000

5,800,000

—
—
53,162,833
—
—
172,500

—
—
53,335,333

$

$

435
2
—

37

58

—
—
532
—
—
2

—
—
534

1,502

2,729

(15,617)
—
484,197
453
40
52

—
—
484,742

$

$

$

$

—
—

—

—

15,454
(18,823)
(451,995) $

—
—
—

—
(25,383)
(477,378) $

(127)
—
(127) $

— $
—
—

—

—

—
—
— $
—
—
—

46,456
926
12

1,539

2,787

(163)
(18,823)
32,734
453
40
54

(127)
(25,383)
7,771

The accompanying notes form an integral part of these consolidated financial statements.

F-5

GOLDEN MINERALS COMPANY
CONSOLIDATED STATEMENTS OF CASH FLOWS
(Expressed in United States dollars)

Cash flows from operating activities:

Net cash used in operating activities (Note 20)
Cash flows from (used in) investing activities:

Proceeds from sale of assets
Additions to property, plant and equipment

Net cash from investing activities
Cash flows from financing activities:

Proceeds from issuance of common stock, net of issue costs
Proceeds from the issuance of convertible note
Convertible note costs

Net cash from financing activities
Net decrease in cash and cash equivalents
Cash and cash equivalents, beginning of period
Cash and cash equivalents, end of period

Supplemental information:

Interest paid, net of amounts capitalized
Income taxes paid

The Years Ended December 31,

2015

2014

(in thousands)

$

(9,935) $

(18,459)

789
(44)
745

—
5,000
(312)
4,688
(4,502)
8,579
4,077

$

982
(500)
482

7,410
—
—
7,410
(10,567)
19,146
8,579

— $
— $

—
—

$

$
$

The accompanying notes form an integral part of these consolidated financial statements.

F-6

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS
(Expressed in United States dollars)

1. Nature of Operations

The Company is a mining company, holding a 100% interest in the Velardeña and Chicago precious metals mining properties and 

associated oxide and sulfide processing plants in Mexico (the “Velardeña Properties”).  During November 2015 the Company 
suspended mining and sulfide processing activities at its Velardeña Properties in order to conserve the asset until the Company is able 
to develop mining and processing plans that at then current prices for silver and gold indicate a sustainable positive operating margin 
(defined as revenue less costs of sales) or the Company is able to locate, acquire and develop alternative mineral sources that could be 
economically mined and transported to the Velardeña Properties for processing.  The Company has placed the mine and sulfide 
processing plant on care and maintenance to enable a re-start of either the mine or mill when mining and processing plans and metals 
prices support a cash positive outlook.  The Company has incurred approximately $1.2 million in related costs for employee severance 
and other shutdown expenditures to place the property on care and maintenance in the fourth quarter 2015 and expects to incur 
approximately $0.3 million in quarterly holding costs while mining and processing remain suspended.  The Company has retained a 
core group of employees, most of whom have been assigned to operate the oxide plant, which is leased to a third party and not 
affected by the shutdown.  The oxide plant began processing material under the lease agreement in December 2015, and the Company 
expects to receive net cash folw under the lease of between $4.0 and $5.0 million in 2016.  The retained employees also include an 
exploration group and an operations and administrative group to continue to advance the Company’s plans in Mexico, oversee 
corporate compliance activities, and to maintain and safeguard the longer term value of the Velardeña assets.

The Company remains focused on evaluating and searching for mining opportunities in North America (including Mexico) with 

near term prospects of mining, and particularly for properties within reasonable haulage distances of our Velardeña Properties in order 
to generate sufficient revenue to fund continuing business activities. These assets may include the Santa Maria Mine located in the 
Parral District in Chihuahua State, the Santa Rosa vein, located in the San Luis de Cordero District in Durango, or the Rodeo property 
located west of the Velardeña Properties in Durango. The Company is continuing its exploration efforts on selected properties in its 
portfolio of approximately 10 exploration properties located primarily in Mexico. It continues to hold its El Quevar advanced 
exploration property in Argentina on care and maintenance until it can find a partner to further advance the project. The Company also 
reviews strategic opportunities from time to time.

The Company is considered an exploration stage company under the criteria set forth by the SEC as the Company has not yet 
demonstrated the existence of proven or probable mineral reserves, as defined by SEC Industry Guide 7, at the Velardeña Properties, 
or any of the Company’s other properties.  As a result, and in accordance with GAAP for exploration stage companies, all 
expenditures for exploration and evaluation of the Company’s properties are expensed as incurred. As such the Company’s financial 
statements may not be comparable to the financial statements of mining companies that do have proven and probable mineral 
reserves.  Such companies would typically capitalize certain development costs including infrastructure development and mining 
activities to access the ore. The capitalized costs would be amortized on a units-of-production basis as reserves are mined.  The 
amortized costs are typically allocated to inventory and eventually to cost of sales as the inventories are sold.  As the Company does 
not have proven and probable reserves, substantially all expenditures at the Company’s Velardeña Properties for mine construction 
activity, as well as costs associated with the mill facilities, and for items that do not have a readily identifiable market value apart from 
the mineralized material, have been expensed as incurred. Such costs are charged to cost of metals sold or project expense during the 
period depending on the nature of the costs. Certain of the costs may be reflected in inventories prior to the sale of the product. The 
term “mineralized material” as used herein, although permissible under SEC Industry Guide 7, does not indicate “reserves” by SEC 
standards. The Company cannot be certain that any deposits at the Velardeña Properties or any other exploration property will ever be 
confirmed or converted into SEC Industry Guide 7 compliant “reserves”.

2. Liquidity, Capital Resources and Going Concern

At December 31, 2015 the Company’s aggregate cash and cash equivalents totaled $4.1 million. With the cash balance at 
December 31, 2015 and based on the assumptions described below we expect to have sufficient funds to continue our long term 
business strategy through December 31, 2016.  The Company’s cash and cash equivalents

F-7

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

balance at December 31, 2015 of $4.1 million is $4.5 million lower than the $8.6 million in similar assets held at December 31, 2014 
due primarily to the negative operating margin (defined as revenue less costs of sales) at the Velardeña Properties of $2.5 million, $1.2 
million in shutdown and care and maintenance costs at the Velardeña Properties, $3.6 million in exploration expenditures, $1.1 million 
in care and maintenance and property holding costs at the El Quevar project and $4.2 million in general and administrative expenses, 
offset in part by $5.0 million in proceeds received from the issuance of the Sentient Note, $0.5 million of net revenue (defined as 
revenue less costs of sales) received from the lease of the oxide plant to a third party, $0.5 million of proceeds from sales of non-
strategic property and equipment, $0.8 million received as a tax refund,  a $1.3 million reduction in working capital and other items 
primarily due  to collections of value added tax (“VAT”) receivables, and a net decrease in working capital consisting of trade 
receivables, inventories and accounts payable associated with the shutdown of mining and processing activities at the Velardeña 
Properties.

On October 27, 2015, the Company borrowed $5.0 million (the “Sentient Loan”) from Sentient Global Resources Fund IV, 

L.P. (“Sentient”), the entire amount available pursuant to the terms of a Senior Secured Convertible Note (the “Sentient Note”) and 
Loan Agreement, with principal and accrued interest due on October 27, 2016.  See Note 11 for a full discussion of the Sentient Loan.  
On February 11, 2016, Sentient converted approximately $3.9 million of principal and $0.1 million of accrued interest (representing 
the total amount of accrued interest at the conversion date) into 23,335,000 shares of the Company’s common stock at an exercise 
price of approximately $0.172 per share, equal to 90% of the 15-day volume weighted average price (“VWAP”) immediately 
preceding the conversion date.  (See Note 25).  Following the conversion, approximately $1.1 million of principal remained 
outstanding.  If the remaining principal and interest accrued  from February 11, 2016 is not converted into the Company’s common 
stock, the Company would owe approximately $1.2 million to Sentient on the October 27, 2016 maturity date.

With the cash balance at December 31, 2015 of $4.1 million and assuming the Company receives $4.8 million in net cash 

flow from the lease of the oxide plant during 2016 and that the remaining balance of the Sentient Note is fully converted into shares of 
the Company’s common stock at or prior to the maturity of the loan on October 27, 2016, the Company plans to spend the following 
amounts totaling approximately $8.4 million during the full year 2016, resulting in a balance of cash and cash equivalents at 
December 31, 2016 of $0.5 million.

(cid:120) Approximately $1.2 million at the Velardeña Properties for care and maintenance;

(cid:120) Approximately $0.8 million on other exploration activities and property holding costs related to the Company’s portfolio 

of exploration properties located primarily in Mexico,

(cid:120) Approximately $0.5 million at the El Quevar project to fund ongoing maintenance activities, property holding costs, and 

continuing  project evaluation costs; and

(cid:120) Approximately $1.4 million in exploration, project assessment, and development costs relating to the newly acquired San 

Luis de Cordero property and other properties;

(cid:120) Approximately $3.4 million on general and administrative costs;

(cid:120) Approximately $1.1 million on an increase in working capital primarily related to a reduction in current liabilities, 

including an advanced payment of $0.5 million received in 2015 from the oxide plant lease and the payment of $0.4 
million in equity taxes owed in a foreign jurisdiction.

The actual amount that the Company spends during 2016 and the projected yearend cash balance may vary significantly from 
the amounts specified above and will depend on a number of factors, including variations from anticipated care and maintenance costs 
at the Velardeña Properties and costs for continued exploration, project assessment, and development at the Company’s other 
exploration properties, including San Luis de Cordero.

The Company does not currently expect it will generate sufficient funds internally to pay the remaining principal and interest on 

the Sentient Loan when it becomes due on October 27, 2016.  The Company plans, and is required by the Loan Agreement, to seek 
external funding through the sale of equity or securities convertible into equity.  There can

F-8

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

be no assurance that the Company will be successful in obtaining sufficient external funding on terms acceptable to the Company or at 
all.  If the remaining balance of the Sentient Loan is converted in full, the Company’s projected cash balance at the end of 2015 and 
the anticipated net cash flow from the leasing of the oxide plant should provide adequate funds to continue the Company’s business 
plans through 2016.

The financial statements have been prepared on a going concern basis under which an entity is considered to be able to realize its 

assets and satisfy its liabilities in the normal course of business.  However, the continuing operations of the Company are dependent 
upon its ability to secure sufficient funding and to generate future profitable operations.  The underlying value and recoverability of 
the amounts shown as property, plant and equipment in Note 9 are dependent on the ability of the Company to generate positive cash 
flows from operations and to continue to fund exploration and development activities that would lead to profitable mining activities or 
to generate proceeds from the disposition of property, plant and equipment.  There can be no assurance that the Company will be 
successful in generating future profitable operations or securing additional funding in the future on terms acceptable to the Company 
or at all.  These material uncertainties, including repayment of the remaining Sentient Loan, may cast significant doubt on the 
Company’s ability to continue as a going concern.  These consolidated financial statements do not include any adjustments relating to 
the recoverability and classification of recorded assets or liabilities which might be necessary should the Company not continue as a 
going concern.

3.

Impairment of Long Lived Assets

Velardeña Properties Asset Groups

The Velardeña Properties consists of two separate asset groups, one involving the oxide plant, which has been leased to a third 

party, and the other involving the mineral and exploration properties, sulfide plant, and mining and other equipment and working 
capital related to the mining and processing activities at the Velardeña Properties (the “Mineral Properties Asset Group”). Per the 
guidance of ASC 360, “Property, Plant and Equipment” (“ASC 360”), the Company assesses the recoverability of its long-lived assets, 
including property, plant and equipment whenever events or changes in circumstances indicate that the carrying value of the assets 
may not be recoverable.  Mining and processing activities generated negative operating margin through September 30, 2015.  Ongoing 
efforts during 2015 to improve the grade of mined material delivered to the sulfide plant for processing by limiting dilution in the 
stopes did not improve grades to a level sufficient to generate positive operating margins at 2015 metals prices.  As a result, the 
Company suspended mining and processing activities at the Velardeña mine and sulfide plant during November 2015 (see Note 1).

The continued negative operating margin and the suspension of mining and sulfide processing activities at the Velardeña 
Properties during November 2015 were events that required an assessment of the recoverability of the Mineral Properties Asset Group 
at September 30, 2015. Per the guidance of ASC 360, recoverability of an asset group is not achieved if the projected undiscounted, 
pre-tax cash flows related to the asset group are less than its carrying amount. In its analysis of projected cash flows for the Mineral 
Properties Asset Group, the Company determined that the Mineral Properties Asset Group was impaired. As a result, at September 30, 
2015 the Company recorded impairment charges totaling $13.2 million to arrive at a remaining book value for the Mineral Properties 
Asset Group of $3.7 million at September 30, 2015, as shown in the table below.

To determine whether the Mineral Properties Asset Group was impaired at September 30, 2015 the Company used a cash flow 
valuation approach, which the Company deemed reasonable under the circumstances, that considered metals price projections using a 
greater weighting of current prices.  Based on the metals price projections and current operating experience for silver and gold grades, 
recoveries, and mining and processing costs, total projected net cash flow from mining and processing activities was negative, 
requiring that each of the individual components of the Mineral Properties Asset Group be written down to fair value.

The Mineral Properties Asset Group includes the mineral and exploration properties associated with the mining and sulfide 
processing activities at the Velardeña Properties.  The discounted cash flow analysis performed by the Company implies a zero value 
for the mineral and exploration properties from mining and processing activities in the current economic environment, but the 
Company believes those properties have a residual value that could be realized from a sale to a third party.  With assistance from a 
third-party mining consulting and engineering firm, in reviewing

F-9

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

comparable sales of similar properties in the region and considering the location of the Company’s properties to other active mining 
operations in close proximity to the Company’s properties, the Company concluded that the mineral and exploration properties 
included in the Mineral Properties Asset Group had a fair value of $1.4 million at September 30, 2015.

The tangible assets included in the Mineral Properties Asset Group, which includes buildings, plant and equipment,  were 
separately analyzed by a third party valuation firm in 2013 using available market data to determine a fair value based on the net 
realizable value that could be received in a sale to a third party. The market data was derived by researching the secondary equipment 
market on sales and/or offers for sale of similar assets. The Mineral Properties Asset Group tangible assets were determined to have a 
fair value of approximately $6.0 million as of June 30, 2013, and have since been further depreciated, reflecting a current net book 
value of approximately $3.2 million as of September 30, 2015.  The Company believes the current net book value of the Mineral 
Properties Asset Group tangible assets did  not exceed fair value at September 30, 2015.  The assets continue to be used or held in 
condition for use to support future profitable operations from the acquisition, exploration and development of other mineral sources 
located near the Velardeña Properties.

The following table details the components of the impairment of the Mineral Properties Asset Group:

Mineral and exploration properties
Exploration properties
Buildings, plant and equipment
Asset retirement cost
Other working capital, net

Net Book Value
Prior to
Impairment at
Sept. 30, 2015

Sept. 30, 2015
Impairment
Charges
(in thousands)

Net Book Value
After
Impairment at
Sept. 30, 2015

$

$

13,660
458
3,236
417
(872)
16,899

$

$

12,306
458
—
417
—
13,181

$

$

1,354
—
3,236
—
(872)
3,718

Prior to assessing the recoverability of the assets comprising the Mineral Properties Asset Group, the Company also assessed the 

fair value of its material and supplies inventory at September 30, 2015, which is included in the Mineral Properties Asset Group.  
Because of the suspension of mining and processing activities at the Velardeña Properties, as noted above, a portion of the material 
and supplies inventory is expected to be sold at a discount to its pre-shutdown book value or to decline in value prior to its use in 
future mining and processing activities.  As a result, the Company increased its reserve for obsolescence of the materials and supplies 
inventory and recorded a noncash charge to shut down costs of approximately $0.4 million at September 30, 2015. At December 31, 
2015, the Company re-evaluated its material and supplies inventory taking into account consumption and purchases during the quarter 
and reduced the reserve for obsolescence by approximately $0.1 million.

Because of the close proximity of the asset group involving the oxide plant (the “Oxide Plant Asset Group”) the Company also 

assessed the recoverability of the Oxide Plant Asset Group at September 30, 2015.  The Oxide Plant Asset Group, which has been 
leased to a third party, consists primarily of the oxide plant facilities with a carrying value at September 30, 2015 of $1.3 million.  The 
projected net cash flows from the lease are in excess of the carrying value of the Oxide Plant Asset Group and the Company therefore 
determined that the Oxide Plant Asset Group was not impaired.

The market approach used in the determination of fair value falls within Level 3 of the fair value hierarchy per ASC 820, “Fair 
Value Measurements and Disclosures” (“ASC 820”) (see Note 14) and relied upon a review of comparable sales of similar properties 
in the region and considered the location of the Company’s properties to other active mining operations in close proximity to the 
Company’s properties.

Based on the Company’s assessment of the recoverability of the Velardeña Properties at December 31, 2014 no impairment was 

deemed to have occurred during 2014.

F-10

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

4.

Summary of Significant Accounting Policies

The Company’s consolidated financial statements have been prepared in accordance with U.S. GAAP. The preparation of the 

Company’s consolidated financial statements requires management to make estimates and assumptions that affect the reported 
amounts of assets and liabilities and related disclosure of contingent assets and liabilities at the date of the consolidated financial 
statements and the reported amounts of revenues and expenses during the reporting period. The more significant areas requiring the 
use of management estimates and assumptions relate to mineralized material and related future metals prices that are the basis for 
future cash flow estimates utilized in impairment calculations and units-of-production depreciation, depletion and amortization 
calculations; environmental reclamation and closure obligations; estimates of recoverable metals in stockpiles; valuation allowances 
for deferred tax assets and the fair value of financial instruments. The Company based its estimates on historical experience and on 
various other assumptions that are believed to be reasonable under the circumstances. Actual results may differ significantly from 
these estimates under different assumptions or conditions.

The policies adopted, considered by management to be significant, are summarized as follows:

a.

Basis of consolidation

All of the Company’s consolidated subsidiaries are 100% owned and as such the Company does not have a noncontrolling interest 

in any of its subsidiaries.   All intercompany transactions and balances have been eliminated at consolidation.

b.

Translation of foreign currencies

Substantially all expenditures and sales are made in U.S. dollars. Accordingly, the Company and its subsidiaries use the U.S. 

dollar as their functional and reporting currency.

c.

Cash and cash equivalents

The Company considers all highly liquid investments with a maturity of three months or less when purchased to be cash 

equivalents.

d.

Inventories

Metals inventory at the Velardeña Properties consisted of marketable products including concentrates and precipitates.  Metals 
inventory was carried at the lower of average cost or net realizable value.  Net realizable value represents the estimated future sales 
price of the product based on spot and futures metals prices through estimated sale and settlement dates, less the estimated costs to 
complete processing and bring the product to sale. Costs included in metals inventory included direct and indirect costs of mining and 
processing, including depreciation.  The Company had no metals inventories at December 31, 2015 as the result of the suspension of 
operations at its Velardeña Properties during November 2015 (see Note 1).  At December 31, 2014 the Company had written down its 
metals inventory to net realizable value with excess costs included in cost of sales and depreciation (see Note 7).

Materials and supplies inventories are valued at the lower of average cost or net realizable value. Cost includes applicable 
taxes and freight. The Company routinely counts and evaluates its material and supplies to determine the existence of any obsolete 
stock that is subject to impairment (see Note 3).

F-11

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

e. Mining properties, exploration and development costs

The Company expenses general prospecting costs and the costs of acquiring and exploring unevaluated mineral properties. 

When a mineral property is determined to have proven and probable reserves, subsequent development costs are capitalized to mineral 
properties.  For acquired mineral properties with proven and probable reserves, the Company capitalizes acquisition costs and 
subsequent development costs.  When mineral properties are developed and operations commence, capitalized costs are charged to 
operations using the units-of-production method over proven and probable reserves. Upon abandonment or sale of a mineral property, 
all capitalized costs relating to the specific property are written off in the period abandoned or sold and a gain or loss is recognized in 
the accompanying Consolidated Statements of Operations and Comprehensive Loss.

As discussed in Note 1, the Company is considered an exploration stage company under the criteria set forth by the SEC 

since it has not yet demonstrated the existence of proven or probable reserves at the Velardeña Properties, or any of the Company’s 
other properties. As such, the Company expenses costs as incurred related to the extraction of mineralized material at its Velardeña 
Properties.  The Company established a cost basis for the mineralized material at the Velardeña Properties as a result of purchase 
accounting for the Company’s business combination transaction with ECU Silver Mining Inc. (“ECU”) in September 2011, the 
transaction pursuant to which the Company acquired the Velardeña Properties. Mineral properties acquired in the ECU merger were 
recorded at estimated fair market value based on valuations performed with the assistance of an independent appraisal firm and a 
minerals engineering company. Although the Company has not demonstrated the existence of proven and probable reserves, and the 
Company has not completed a pre-feasibility economic assessment, the Company had established the existence of mineralized 
material that was used in assigning value to mineral properties for purchase accounting purposes. The subsequent extraction of this 
mineralized material has provided a reasonable basis for the calculation of units-of-production depreciation for the cost basis in the 
mineral properties.

On a quarterly basis the Company evaluates its exploration properties to determine if they meet the Company’s minimum 

requirements for continued evaluation.  The rights to the properties that do not meet the minimum requirements are relinquished and 
the carrying values, if any, are written off and reflected in other operating gains and losses, net on the accompanying Consolidated 
Statements of Operations and Comprehensive Loss.  Costs of exploration subsequent to the application of fresh start accounting have 
been and will continue to be expensed.

f.

Property, plant and equipment and long lived asset impairment

Buildings are depreciated using the straight—line method over the estimated useful lives of 30 to 40 years or the life of the 

mine whichever is shorter.  Mining equipment and machinery, excluding the plant, are depreciated using the straight-line method over 
useful lives of three to eight years or the lease period, whichever is shorter.  Mineral properties and the plant are depreciated using 
units of production based on estimated mineralized material.  Other furniture and equipment are depreciated using the straight-line 
method over estimated useful lives of three to five years.  Depreciation on plant and equipment used in the construction of an asset is 
capitalized to the constructed asset.

As discussed above, the Company does not have any properties with proven or probable reserves including the the Velardeña 

Properties.

Property, plant and equipment are recorded at cost and per the guidance of ASC 360 the Company assesses the recoverability 
of its property, plant and equipment, including goodwill, whenever events or changes in circumstances indicate that the carrying value 
of the assets may not be recoverable.   If the sum of estimated future net cash flows on an undiscounted basis is less than the carrying 
amount of the related asset, impairment is considered to exist. The related impairment loss is measured by comparing estimated future 
net cash flows on a discounted basis or by comparing other market indicators to the carrying amount of the asset (see Notes 3 and 9).

g.

Asset Retirement Obligations

The Company records asset retirement obligations (“ARO”) in accordance with ASC 410, “Asset Retirement and 

Environmental Obligations” (“ASC 410”), which establishes a uniform methodology for accounting for estimated

F-12

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

reclamation and abandonment costs. According to ASC 410, the fair value of an ARO is recognized in the period in which it is 
incurred if a reasonable estimate of fair value can be made. An offsetting asset retirement cost (“ARC”) is capitalized as part of the 
carrying value of the assets with which it is associated, and depreciated over the useful life of the asset (see Note 14).

The Company prepares estimates of the timing and amount of expected cash flows when an ARO is incurred. The fair value 
of the ARO is measured by discounting the expected cash flows using a discount rate that reflects the credit adjusted risk-free rate of 
interest. The Company records the fair value of an ARO when it is incurred and layer adjustments of the ARO are recorded as an 
adjustment to the corresponding ARC. The ARO is adjusted to reflect the passage of time (accretion cost) calculated by applying the 
discount rate implicit in the initial fair value measurement to the beginning-of-period carrying amount of the ARO. The Company 
records accretion costs to expense as incurred.

h.

Revenue Recognition

Following the guidance of ASC 605, “Revenue Recognition” (“ASC 605”), the Company recognizes “Revenue from the sale of 

metals” at the earliest point that both risk of loss and title transfer to the purchaser pursuant to the terms of the Company’s sales 
agreements. Prices for concentrate and precipitate sales are fixed according to terms included in the sales agreements, which generally 
call for final pricing based on average metals prices observed over specific periods that range from 10 days prior to the transfer of title 
to the month following the month the product is received by the purchaser.  Revenue is recorded based on estimated metals contained 
in the product from assay data and using either actual or projected prices for the pricing period specified in the sales agreement.  Upon 
final settlement revenue may be adjusted for changes in actual contained metals and final metals prices.

The Company recognizes oxide plant lease fees and reimbursements for labor, utility and other costs as “Revenue from Oxide 
plant lease” in the Consolidated Statements of Operations and Comprehensive Loss following the guidance of ASC 605 regarding 
“income statement characterization of reimbursements received for “out-of-pocket” expenses incurred” and “reporting revenue gross 
as a principal versus net as an agent”.  ASC 605 supports recording as gross revenue fees received for the reimbursement of expenses 
in situations where the recipient is the primary obligor and has certain discretion in the incurrence of the reimbursable expense.  The 
actual costs incurred for the reimbursed labor, utility and other costs are reported as “Oxide plant lease costs” in the statement of 
operations. The Company recognizes lease fees during the period the fees are earned per the terms of the lease (see Note 17).

i.

Stock compensation

Stock based compensation costs are recognized per the guidance of ASC 718, “Compensation — Stock Compensation” (“ASC 
718”), using a graded vesting attribution method whereby costs are recognized over the requisite service period for each separately 
vesting portion of the award (see Note 16).  Stock grants are valued at their grant date at fair value which in the case of options 
requires the use of the Black-Scholes option pricing model. Per ASC 718 the grants may be classified as equity grants or liability 
grants depending on the terms of the grant.

j.

Net income (loss) per Share of Common Stock

Basic income (loss) per share is computed by dividing net income (loss) available to holders of the Company’s Common 

Stock by the weighted average number of shares of Common Stock outstanding for the period.  Diluted income (loss) per share 
reflects the potential dilution that would occur if securities or other contracts to issue Common Stock were exercised or converted into 
Common Stock.

At December 31, 2015 and 2014, all potentially dilutive shares were excluded from the computation of diluted earnings per 

share because to include them would have been anti-dilutive.

F-13

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

k.

Comprehensive Income (Loss)

Comprehensive income (loss) is defined as all changes in equity (deficit), exclusive of transactions with stockholders, such as 

capital investments.  Comprehensive income (loss) includes net income (loss) and changes in certain assets and liabilities that are 
reported directly in equity.  For the years ended December 31, 2015 and 2014 Comprehensive Loss included the change in the market 
value of available for sale securities and is reported on the Consolidated Statements of Operations and Comprehensive Loss.

l.

Income Taxes

The Company accounts for income taxes in accordance with the provisions of ASC 740, “Income Taxes” (“ASC 740”), on a tax 

jurisdictional basis.  The Company files United States and certain other foreign country income tax returns, and pays taxes reasonably 
determined to be due.  The tax rules and regulations in these countries are highly complex and subject to interpretation.  The 
Company’s income tax returns are subject to examination by the relevant taxing authorities and in connection with such examinations, 
disputes can arise with the taxing authorities over the interpretation or application of certain tax rules within the country involved.  In 
accordance with ASC 740, the Company identifies and evaluates uncertain tax positions, and recognizes the impact of uncertain tax 
positions for which there is a less than more-likely-than-not probability of the position being upheld when reviewed by the relevant 
taxing authority.  Such positions are deemed to be unrecognized tax benefits and a corresponding liability is established on the balance 
sheet.

The Company classifies income tax related interest and penalties as income tax expense.

m.

Recently Adopted Standards

In April 2015, the Financial Accounting Standards Board (“FASB”) issued Accounting Standards Update (“ASU”) No. 2015-03, 

“Interest—Imputation of Interest (Subtopic 835-30): Simplifying the Presentation of Debt Issuance Costs” (“ASU 2015-03”).  The 
purpose of the standard update is to simplify presentation of debt issuance costs. ASU 2015-03 requires that debt issuance costs 
related to a recognized debt liability be presented in the balance sheet as a direct deduction from the carrying amount of that debt 
liability, consistent with debt discounts. Amortization of the discount or premium shall be reported as interest expense in the case of 
liabilities or as interest income in the case of assets. Amortization of debt issuance costs also shall be reported as interest expense. 
ASU No. 2015-03 becomes effective for fiscal years beginning after December 15, 2015, and interim periods within those fiscal years. 
Early adoption is permitted and the Company adopted ASU 2015-03 in 2015. The adoption of this standard did not have a material 
impact on the Company’s financial position or results of operations.

In April 2014 the FASB issued ASU No. 2014-08, “Presentation of Financial Statements (Topic 205) and Property, Plant, and 
Equipment (Topic 360): Reporting Discontinued Operations and Disclosures of Disposals of Components of an Entity” (“ASU 2014-
08”). ASU 2014-08 changes the criteria for reporting discontinued operations while enhancing disclosures in this area. Under ASU 
2014-08, only disposals representing a strategic shift in operations will be presented as discontinued operations. Additionally, ASU 
2014-08 requires expanded disclosures about discontinued operations that will provide financial statement users with more 
information about the assets, liabilities, income, and expenses of discontinued operations. ASU 2014-08 became effective for the 
Company January 1, 2015. The adoption of ASU 2014-08 did not have a material impact on the Company’s consolidated financial 
position or results of operations.

In July 2013 the FASB issued ASU No. 2013-11, “Income Taxes (Topic 740): Presentation of an Unrecognized Tax Benefit 

When a Net Operating Loss Carryforward, a Similar Tax Loss, or a Tax Credit Carryforward Exists” (“ASU 2013-11”), which 
requires an unrecognized tax benefit to be presented as a reduction to a deferred tax asset for a net operating loss carryforward, a 
similar tax loss or a tax credit carryforward that the entity intends to use and is available for settlement at the reporting date. ASU 
2013-11 became effective for the Company January 1, 2014. The adoption of ASU 2013-11 has not had a material impact on the 
Company’s consolidated financial position or results of operations.

F-14

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

n.

Recently Issued Pronouncements

In January 2016, the FASB issued ASU No. 2016-01, “Recognition and Measurement of Financial Assets and Financial 

Liabilities” (“ASU 2016-01”) which amended its standards related to the accounting of certain financial instruments. This amendment 
addresses certain aspects of recognition, measurement, presentation and disclosure. The new rules will become effective for annual 
and interim periods beginning after December 15, 2017. Early adoption is not permitted. We are in the process of evaluating the 
impact the amendment will have on our consolidated financial position or results of operations.

In November 2015, the FASB issued ASU No. 2015-17, “Income Taxes: Balance Sheet Classification of Deferred Taxes” (“ASU 
2015-17”). ASU 2015-17 requires that deferred tax assets and liabilities be classified as noncurrent on the balance sheet. This update 
is effective for fiscal years, and interim periods within those years, beginning after December 15, 2016. The adoption of this update is 
not expected to have a material impact on the Company’s consolidated financial position or results of operations.

In July 2015, the FASB issued ASU No. 2015-11, “Inventory, Simplifying the Measurement of Inventory” (“ASU 2015-11”). ASU 
2015-11 affects reporting entities that measure inventory using first-in, first-out or average cost. ASU 2015-11 requires that inventory 
be measured at the lower of cost and net realizable value. Net realizable value is the estimated selling prices in the ordinary course of 
business, less reasonably predictable costs of completion, disposal, and transportation. ASU 2015-11 is effective for annual periods 
beginning after December 15, 2016, with early adoption permitted. The adoption of ASU 2015-11 is not expected to have a material 
impact on the consolidated financial position or results of operations.

On August 27, 2014, the FASB issued ASU No. 2014-15, “Presentation of Financial Statements - Going Concern (Subtopic 205-

40), Disclosure of Uncertainties about an Entity’s  Ability to Continue as a Going Concern” (“ASU 2014-15”).  ASU 2014-15 will 
require management to evaluate whether there are conditions and events that raise substantial doubt about the Company’s ability to 
continue as a going concern within one year after the financial statements are issued on both an interim and annual basis. Management 
will be required to provide certain footnote disclosures if it concludes that substantial doubt exists or when its plans alleviate 
substantial doubt about the Company’s ability to continue as a going concern. ASU 2014-15 becomes effective for annual periods 
beginning in 2016 and for interim reporting periods starting in the first quarter of 2017. The Company does not expect the adoption of 
this amendment to have a material impact on its consolidated financial position or results of operations.

In May 2014, FASB and the International Accounting Standards Board issued ASU No. 2014-09, “Revenue from Contracts with 
Customers (Topic 606)” (“ASU 2014-09”). ASU 2014-09 outlines a single comprehensive model for entities to use in accounting for 
revenue arising from contracts with customers and supersedes most current revenue recognition guidance, including industry-specific 
guidance. In addition, the guidance requires improved disclosures to help users of financial statements better understand the nature, 
amount, timing and uncertainty of revenue that is recognized and the related cash flows. ASU 2014-09 is effective for interim and 
annual periods beginning after December 15, 2017; early adoption is not permitted. ASU 2014-09 was originally effective 
December 15, 2016 but ASU 2015-14 deferred the effective date by one year. The Company is evaluating the financial statement 
implications of adopting ASU 2014-09 but does not believe adoption of ASU 2014-09 will have a material impact on its consolidated 
financial position or results of operations.

5.

Cash and Cash Equivalents and Short-Term Investments

The Company considers all highly liquid investments with a maturity of three months or less when purchased to be cash 

equivalents. Short-term investments include investments with maturities greater than three months, but not exceeding 12 months, or 
highly liquid investments with maturities greater than 12 months that the Company intends to liquidate during the next 12 months for 
working capital needs.

F-15

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

The following tables summarize the Company’s short-term investments at December 31, 2015:

December 31, 2015

Investments:
Short-term:

Cost

Estimated 
Fair Value
(in thousands)

Carrying 
Value

Available for sale common stock

Total available for sale
Total short term

$

$

199
199
199

$

$

72
72
72

$

$

72
72
72

6.

Prepaid Expenses and Other Assets

Prepaid expenses and other assets consist of the following:

December 31,

2015

2014

Prepaid insurance
Prepaid contractor fees and vendor advances
Taxes receivable
Recoupable deposits and other

$

$

7.

Inventories

Inventories at the Velardeña Properties were as follows:

$

(in thousands)
302
12
—
137
451

$

542
100
90
103
835

Metals inventory
In-process inventory
Material and supplies

December 31,

2015

2014

(in thousands)
— $
—
330
330

$

477
307
713
1,497

$

$

The Company had no metals or in process inventories at December 31, 2015 as the result of the suspension of mining and 
processing at the Velardeña Properties (see Note 1). The material and supplies inventory at December 31, 2015 is reduced by a $0.3 
million obsolescence charge reflected in shutdown costs.

At December 31, 2014 the Company had written down its metals and in-process inventories to net realizable value including a 

charge to cost of metals sold of $1.2 million and a charge to depreciation expense of approximately $0.7 million.

8. Value added tax receivable

The Company has recorded value added tax (“VAT”) paid in Mexico and related to the Velardeña Properties as a recoverable 
asset. Mexico law allows for certain VAT payments to be recovered through ongoing applications for refunds. The Company expects 
that the current amounts will be recovered within a one year period.

The Company has also paid VAT in Mexico as well as other countries, primarily related to exploration projects, which has been 

charged to expense as incurred because of the uncertainty of recoverability.

F-16

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

9. Property, Plant and Equipment

Property, plant and equipment, net

The components of property, plant, and equipment, net were as follows:

Mineral properties
Exploration properties
Royalty properties
Buildings
Mining equipment and machinery
Other furniture and equipment
Asset retirement cost

Less: Accumulated depreciation & amortization

$

December 31,

2015

2014

$

(in thousands)
9,630
2,518
200
4,377
16,998
841
1,285
35,849
(24,724)
11,125

22,397
2,743
200
4,377
17,695
841
2,002
50,255
(21,224)
29,031

At September 30, 2015 the Company determined that the recoverability of certain mineral property and exploration property 
costs related to theVelardeña Properties Mineral Properties Asset Group was impaired. As such the carrying value of the Mineral 
Properties Asset Group was written down by approximately $13.2 million and an impairment charge for that amount was recorded.  
(See Note 3.)

During the year ended December 31, 2015 the Company received $0.3 million related to an option agreement on its Otuzco 

property in Peru. In addition, the Company sold certain non-strategic mining concessions and equipment for net proceeds of 
approximately $0.5 million and recorded a $0.2 million gain on the transactions. The net gains for the above transactions are reflected 
in other operating income, net on the accompanying Consolidated Statements of Operations and Comprehensive Loss.

During the year ended December 31, 2014 the Company sold 45 mining concessions totaling 770 hectares located in the 

Zacatecas District, Zacatecas State, Mexico, to Capstone Mining Group for $0.7 million and recorded a $0.5 million gain on the sale.  
Also in the third quarter 2014, the Company entered into an option agreement with a private party to sell its 1,100 hectare Otuzco 
property in Peru for approximately $0.5 million.  The Company received approximately $0.2 million under the option agreement 
during 2014, and the remaining $0.3 million was received during 2015, as discussed above.  In addition, the Company sold 
miscellaneous surplus equipment located in Argentina for approximately $0.1 million and recorded a nominal gain. The net gains for 
the above transactions are reflected in other operating income, net on the accompanying Consolidated Statements of Operations and 
Comprehensive Loss.

The ARC) is all related to the Company’s Velardeña Properties. The decrease in the ARC during the period is related to an 

adjustment to the ARO (see Note 12) and to the impairment of the ARC, as discussed below.

At September 30, 2015 the Company reduced the carrying value of the Velardeña Properties mineral and exploration properties 
by $12.8 million and the ARC by $0.4 million and recorded a $13.2 million impairment charge on the accompanying Consolidated 
Statements of Operations and Comprehensive Loss (see Note 3).  The table below sets forth the detail of the impairment charges 
recorded to the Velardeña Properties property, plant and equipment:

F-17

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

Mineral properties
Exploration properties
Royalty properties
Buildings
Mining equipment and machinery
Other furniture and equipment
Asset retirement cost

$

Gross Value
Prior to
Impairment at
Sept. 30, 2015

Impairment
Charge
Minerals
Properties
Asset Group
(in thousands)

Gross Value
After
Impairment at
Sept. 30, 2015

$

21,936
3,001
200
4,377
17,181
841
1,702
49,238

$

12,306
458
—
—
—
—
417
13,181

9,630
2,543
200
4,377
17,181
841
1,285
36,057

The carrying value after the impairment at September 30, 2015 represents the fair value of the assets as discussed in Note 3.

10.

Accounts Payable and Other Accrued Liabilities

The Company’s accounts payable and other accrued liabilities consist of the following:

December 31,

2015

2014

(in thousands)

Accounts payable and accruals
Accrued employee compensation and benefits

$

$

599 $
545
1,144 $

893
746
1,639

December 31, 2015

Accounts payable and accruals at December 31, 2015 consist primarily of $0.3 million due to contractors and suppliers and $0.3 

million related to the Company’s Velardeña Properties and corporate administrative activities, respectively.  In the case of the 
Velardeña Properties, amounts due also include VAT payable that is not an offset to the VAT receivable.

Accrued employee compensation and benefits at December 31, 2015 consist of $0.1 million of accrued vacation payable and $0.4 

million related to withholding taxes and benefits payable, of which $0.2 million is related to activities at the Velardeña Properties.

December 31, 2014

Accounts payable and accruals at December 31, 2014 consist primarily of $0.7 million due to contractors and suppliers and $0.2 

million related to the Company’s Velardeña Properties and corporate administrative activities, respectively.  In the case of the 
Velardeña Properties, amounts due also include VAT payable that is not an offset to the VAT receivable.

Accrued employee compensation and benefits at December 31, 2014 consist of $0.1 million of accrued vacation payable and $0.6 

million related to withholding taxes and benefits payable, of which $0.3 million is related to activities at the Velardeña Properties.

F-18

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

Key Employee Long-Term Incentive Plan

In December 2013, the Board of Directors of the Company approved and the Company adopted the 2013 Key Employee Long-
Term Incentive Plan (the “KELTIP”), which became effective immediately. The KELTIP provides for the grant of units (“KELTIP 
Units”) to certain officers and key employees of the Company, which units will, once vested, entitle such officers and employees to 
receive an amount, in cash or in Company common stock issued pursuant to the Company’s Amended and Restated 2009 Equity 
Incentive Plan, measured generally by the price of the Company’s common stock on the settlement date. KELTIP Units are not an 
actual equity interest in the Company and are solely unfunded and unsecured obligations of the Company that are not transferable and 
do not provide the holder with any stockholder rights. Payment of the settlement amount of vested KELTIP Units is deferred generally 
until the earlier of a change of control of the Company or the date the grantee ceases to serve as an officer or employee of the 
Company.

During 2015, with the retirement of an officer of the Company all outstanding KELTIP Units were settled with the issuance of 

common stock of the Company under the Equity Plan (defined herein). No additional KELTIP Units have been granted and at 
December 31, 2015 the Company has no KELTIP Units outstanding.  At December 31, 2014 after marking the outstanding KELTIP 
Units to market the Company had recorded a $93,000 liability which is included in accrued employee compensation and benefits in 
the table above.

11.

Convertible note payable

On October 27, 2015, the Company borrowed $5.0 million from Sentient, per the terms of the Sentient Note and Loan Agreement 

(the “Sentient Loan”), with principal and accrued interest due on October 27, 2016.  To comply with security regulations and stock 
exchange rules in the United States and Canada, the Company received stockholder approval on January 19, 2016 to allow the 
Sentient Note principal and accrued interest to be converted,  solely at Sentient’s option, into shares of the Company’s common stock 
at a price equal to the lowest of: 1) $0.29, 90 percent of the 15-day volume weighted average price (“VWAP”) for the period 
immediately preceding the Loan closing date, 2) 90 percent of the 15-day VWAP for the period immediately preceding the Loan 
conversion date, or 3) an anti-dilution adjusted price based on the lowest price for which the Company has sold its stock following the 
Loan closing date. The Loan bears interest at a rate of 9.0% per annum, compounded monthly.  The interest is due on the earlier of the 
full conversion of the Sentient Note or at maturity. The Sentient Loan contains customary representations, warranties, covenants and 
default provisions and is secured by the stock of the Company’s principal subsidiaries, including the stock of subsidiaries that own 
directly or indirectly the Velardeña Properties and the El Quevar project.

The Company incurred approximately $0.3 million in legal and other costs associated with the Sentient Loan, including costs 
related to the special meeting of stockholders to approve the convertibility of the Sentient Note. Per the guidance of ASU 2015-03 the 
loan costs are presented as a reduction to the note payable on the accompanying Consolidated Balance Sheets and will be amortized to 
interest expense over the life of the Sentient note using the interest rate method (see Note 4). At December 31, 2015 the balance of the 
note payable was reduced by approximately $0.3 million related to the loan costs and the Company had recognized $54,000 of interest 
expense related to the amortization of the loan costs.

The beneficial conversion feature of the Sentient Note represents an embedded derivative as defined by ASC 815 “Derivatives 
and Hedging”(“ASC 815”). ASC 815 provides that a derivative instrument’s fair value must be bifurcated between the note and the 
embedded derivative and separately recorded on the Company’s Consolidated Balance Sheet. The Company used a third party 
consultant to value the embedded derivative in the Sentient Note employing a Monte Carlo type probability analysis, which falls 
within Level 3 of the fair value hierarchy (see Note 14). For purposes of valuing the embedded derivative as of the Sentient Loan 
closing date and at December 31, 2015 the valuation model takes into account, among other items: 1) the probability of successfully 
achieving stockholder approval of the Sentient Notes’ conversion feature, 2) future variations in the Company’s stock price, and 3) the 
probability of entering into an equity transaction prior to the Sentient Loan maturity date that would lower the conversion price.

The derivative is recorded at fair value with subsequent mark-to-market changes in the value of the derivative recorded as income 

or loss in the Consolidated Statements of Operations and Comprehensive Loss.  It was determined that the embedded

F-19

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

derivative had a fair value of approximately $1.1 million at October 27, 2015, the date the Company entered into the Sentient Loan.  
At December 31, 2015 the embedded derivative had a fair value of approximately $0.5 million and the Company recorded a gain of 
approximately $0.6 million.

Because the proceeds of the Sentient Loan have been bifurcated between the Sentient Note and the embedded derivative, and 
because the Sentient Note has been recorded net of loan costs, which will be amortized to interest expense over the life of the Sentient 
Note, the effective rate of interest on solely the recorded loan obligation is higher than the stated nominal rate of interest on the 
Sentient Note. The effective interest rate on the Sentient Note during the year ended December 31, 2015 is approximately 21%, 
compounded monthly, compared to the stated nominal rate of 9.0% per annum, compounded monthly.

The Company has also agreed to enter into a registration rights agreement (“RRA”) upon the conversion of any part of the 
Sentient Note into shares of common stock of the Company.  The RRA will require the Company to register, at the Company’s 
expense, any shares received by Sentient upon conversion of all or a part of the Sentient Note within a reasonable period of time and 
to maintain the effectiveness of such shares.  The RRA will provide for penalties up to a maximum of 3.0 percent of the value of the 
shares received in the case that the shares are not registered and declared effective within a reasonable timeframe.

On February 11, 2016, Sentient converted approximately $3.9 million of principal and $0.1 million of accrued interest 

(representing the total amount of accrued interest at the conversion date) into 23,335,000 shares of the Company’s common stock at an 
exercise price of approximately $0.172 per share, equal to 90% of the 15-day VWAP immediately preceding the conversion date (see 
Note 25).  Following the conversion, approximately $1.1 million of principal remained outstanding.

12.

Asset Retirement and Reclamation Liabilities

The Company retained the services of a mining engineering firm to prepare a detailed closure plan for the Velardeña Properties. 

The plan was completed during the second quarter 2012 and indicated that the Company had an ARO and offsetting ARC of 
approximately $1.9 million. The estimated $3.5 million ARO and ARC that was recorded at the time of the acquisition of the 
Velardeña Properties was adjusted accordingly.

The Company will continue to accrue additional estimated ARO amounts based on an asset retirement plan as activities requiring 

future reclamation and remediation occur.  During the year ended December 31, 2015 the Company recognized approximately $0.2 
million of accretion expense and approximately $0.2 million of amortization expense related to the ARC.

The following table summarizes activity in the Velardeña Properties ARO:

Beginning balance

Changes in estimates, and other
Accretion expense

Ending balance

December 31,

2015

2014

(in thousands)
2,582 $

(300)
198
2,480 $

2,467

(85)
200
2,582

$

$

The decrease in the ARO recorded during the years ended December 31, 2015 and 2014 is the result of changes in assumptions 

related to inflation factors and discount rates used in the determination of future cash flows.

The ARO set forth on the accompanying Condensed Consolidated Balance Sheets at December 31, 2015 and December 31, 2014 

includes approximately $0.1 million of reclamation liabilities related to activities at the El Quevar project in Argentina.

F-20

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

13.

Other Liabilities

The Company recorded other current liabilities of approximately $0.6 million and $2.6 million at December 31, 2015 and 

December 31, 2014, respectively.  For December 31, 2015 the amount includes $0.4 million related to the Argentina tax on equity due 
for years 2009 through 2012 stemming from a tax audit of those years. The amount includes $0.2 million in taxes and $0.2 million in 
estimated interest and penalties.  The $0.2 million in net taxes due will be paid ratably over a six month period beginning in 
January 2016.  The Company is awaiting the final assessment of interest and penalties, estimated to be approximately $0.2 million, 
payable immediately upon final assessment, which is expected in early 2016 (see Note 21.)  The December 31, 2015 amount also 
includes $0.1 million of accrued interest on the Sentient Loan (see Note 11) and $0.1 million as a loss contingency on a disputed 
contract with a third party contractor in Mexico.

For December 31, 2014 the amount includes $2.3 million related to a loss contingency on foreign withholding taxes that the 
government could assert are owed by the Company, acting as withholding agent, on certain interest payments made to a third party. 
The amounts include estimated interest, penalties and other adjustments. This loss contingency expired during 2015.  The 
December 31, 2014 amount also includes $0.2 million related to the Argentina tax on equity due for years 2009 through 2012 
stemming from a tax audit of those years. The amount includes estimated interest and penalties and is net of certain VAT credits due 
the Company.

14.

Fair Value Measurements

Financial assets and liabilities and nonfinancial assets and liabilities are measured at fair value on a recurring (annual) basis under 
a framework of a fair value hierarchy which prioritizes the inputs into valuation techniques used to measure fair value into three broad 
levels.  This hierarchy gives the highest priority to quoted prices (unadjusted) in active markets and the lowest priority to unobservable 
inputs.  Further, financial assets and liabilities should be classified by level in their entirety based upon the lowest level of input that 
was significant to the fair value measurement.  The three levels of the fair value hierarchy per ASC 820 are as follows:

Level 1:  Unadjusted quoted market prices in active markets for identical assets or liabilities that are accessible at the 

measurement date.

Level 2:  Quoted prices in inactive markets for identical assets or liabilities, quoted prices for similar assets or liabilities in 
active markets, or other observable inputs either directly related to the asset or liability or derived principally from corroborated 
observable market data.

Level 3:  Unobservable inputs due to the fact that there is little or no market activity. This entails using assumptions in models 

which estimate what market participants would use in pricing the asset or liability.

The Company has consistently applied the valuation techniques discussed in Notes 3, 11 and 16 in all periods presented.

Recurring Fair Value Measurements

The following table summarizes the Company’s financial assets and liabilities measured on a recurring basis at fair value at 

December 31, 2015 and 2014 by respective level of the fair value hierarchy:

F-21

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

At December 31, 2015
Assets:

Cash and cash equivalents
Trade accounts receivable
Marketable securities

Liabilities:

Warrant liability
Derivative liability

At December 31, 2014
Assets:

Cash and cash equivalents
Trade accounts receivable

Liabilities:

Warrant liability

Level 1

Level 2

Level 3

Total

(in thousands)

$

$

$

$

$

$

$
$

4,077 $
546
72
4,695 $

— $
—
— $

8,579 $
—
8,579 $

— $
—
—
— $

— $
—
— $

— $
—
— $

— $
—
—
— $

210 $
488
698 $

— $
—
— $

— $
— $

— $
— $

1,554 $
1,554 $

4,077
546
72
4,695

210
488
698

8,579
—
8,579

1,554
1,554

The Company’s cash equivalents, comprised principally of U.S. treasury securities, are classified within Level 1 of the fair value 

hierarchy.

The Company’s trade accounts receivable are classified within Level 1 of the fair value hierarchy, are related to the sale of metals 

at our Velardeña Properties and the oxide plant lease and are valued at published metals prices per the terms of the refining and 
smelting agreements and lease rates per the plant lease agreement.

At December 31, 2015 and 2014, the Company recorded a liability for warrants to acquire the Company’s stock as a result of anti-
dilution clauses in the warrant agreements that could result in a resetting of the warrant exercise price in the event the Company were 
to issue additional shares of its common stock in a future transaction at a price lower than the current exercise price of the warrants 
(see Note 16). The Company assesses the fair value of its warrant liability at the end of each reporting period, with changes in the 
value recorded as a separate line item on the Company’s Condensed Consolidated Statements of Operations and Comprehensive 
Loss.  The valuation policies are approved by the Chief Financial Officer who reviews and approves the inputs used in the fair value 
calculations and the changes in fair value measurements from period to period for reasonableness. Fair value measurements are 
discussed with the Company’s Chief Executive Officer, as deemed appropriate.  The warrant liability has been recorded at fair value 
as of December 31, 2015 and 2014 based primarily on a valuation performed by a third party expert using a Monte Carlo simulation, 
which falls within Level 3 of the fair value hierarchy.  The valuation model takes into account the probability that the Company could 
issue additional shares in a future transaction at a lower price than the current exercise price of the warrants.

The beneficial conversion feature of the Sentient Note represents an embedded derivative as defined by ASC 815. ASC 815 
provides that a derivative instrument’s fair value must be bifurcated from the host contract and separately recorded on the Company’s 
Consolidated Balance Sheets.  At December 31, 2015 the Company had recorded a derivative liability related to the beneficial 
conversion feature of the Sentient Note (see Note 11.) The Company assesses the fair value of the derivative liability at the end of 
each reporting period, with changes in the value recorded as a separate line item on the Company’s Condensed Consolidated 
Statements of Operations and Comprehensive Loss. The valuation policies are approved by the Chief Financial Officer who reviews 
and approves the inputs used in the fair value calculations and the changes in fair value measurements from period to period for 
reasonableness. Fair value measurements are discussed with the Company’s Chief Executive Officer, as deemed appropriate.  The 
derivative liability has been recorded at fair value as of December 31, 2015 based primarily on a valuation performed by a third party 
expert using a Monte Carlo simulation, which falls within Level 3 of the fair value hierarchy. The valuation model

F-22

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

takes into account, among other items: 1) the probability of successfully achieving stockholder approval of the Loan’s conversion 
feature, 2) future variations in the Company’s stock price, and 3) the probability of entering into an equity transaction prior to the 
Loan maturity date that would lower the conversion price.

In addition to the warrant exercise prices (see Note 16) and Sentient Note  conversion price (see Note 11) other significant inputs 

to the warrant valuation model and derivative valuation model included the following as applicable:

Company’s ending stock price
Company’s stock volatility
Applicable risk free interest rate

December 31,

2015

2014

$

$

0.20

85%
1.48%

0.54

90%
1.60%

An increase or decrease in the Company’s stock price, in isolation, would result in a relatively lower or higher fair value 

measurement respectively.  A decrease in the probability of the issuance of additional common stock at a lower price than the current 
warrant exercise price would result in a lower value for the warrants.  The table below highlights the change in fair value of the 
warrant liability and the derivative liability.

Beginning balance at January 1, 2014
Adjustment to record 2012 warrants as a liability 

(Note 16)

Issuance of warrants
Change in estimated fair value
Ending balance at December 31, 2014
Sentient Note, October 27, 2015
Change in estimated fair value
Ending balance at December 31, 2015

$

$

$

Fair Value Measurements
Using Significant Unobservable
Inputs (level 3)

Warrant Liabilities

Derivative Liability

(in thousands)
— $

163
3,084
(1,693)
1,554 $
—
(1,344)

210 $

—

—
—
—
—
1,040
(552)
488

Non-recurring Fair Value Measurements

There were no non-recurring fair value measurements at December 31, 2014.

The Company did conduct a fair value assessment of its mineral properties related to the Velardeña Properties at September 30, 
2015 (see Note 3). The following table summarizes the Company’s non-recurring fair value measurements at September 30, 2015 by 
respective level of the fair value hierarchy:

At September 30, 2015
Assets:

Mineral properties

Level 1

Level 2

Level 3

Total

(in thousands)

$
$

— $
— $

— $
— $

1,354 $
1,354 $

1,354
1,354

The Company assesses the fair value of its long lived assets if circumstances indicate a change in the fair value has occurred.  The 
valuation policies are approved by the Chief Financial Officer who reviews and approves the inputs used in the fair value calculations 
and the changes in fair value measurements from period to period for reasonableness. Fair value measurements are discussed with the 
Company’s Chief Executive Officer, as deemed appropriate.

F-23

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

To determine the fair value of mineral properties the Company uses a discounted cash flow evaluation approach and relied on a 

third party mining consulting and engineering firm to assist with the determination of a residual value for the Velardeña mineral 
properties, which falls within Level 3 of the fair value hierarchy. The discounted cash flow valuation approach relies upon 
assumptions for future metals prices and projected silver and gold grades, recoveries, and mining and processing costs related to the 
Velardeña Properties. In determining the residual value of the mineral properties the third-party mining consulting and engineering 
firm reviewed comparable sales of similar properties in the region and considered the location of the Company’s properties to other 
active mining operations in close proximity to the Company’s properties.  See Note 3 for further details related to the determination of 
fair value.

15.

Income Taxes

The Company accounts for income taxes in accordance with the provisions of ASC 740, “Income Taxes” (“ASC 740”) on a tax 
jurisdictional basis.

Income (loss) from operations before income taxes by country consists of the following:

United States
Other Countries

For the Year Ended December 31,

2015

2014

(in thousands)

$

$

(6,484) $
(18,899)
(25,383) $

(8,207)
(10,616)
(18,823)

In 2014 and 2015 the Company recorded no current or deferred tax expense or benefit, as any tax expense or benefit incurred 

during the year has been offset against a change in the valuation allowance of various deferred tax assets in each country.

A reconciliation of the provision for income taxes computed at the statutory rate to the provision for income taxes as shown in the 

Consolidated Statements of Operations and Comprehensive Loss is summarized below.

Tax expense (benefit) at US rate of 34%
Other adjustments:

Rate differential of other jurisdictions
Effects of foreign earnings
Change in valuation allowance
Provision to tax return true-ups
Exchange rate changes on deferred tax assets
Other

Income tax provision

For the Year Ended December 31,

2015

2014

(in thousands)

(8,630)

$

681
(1,475)
3,745
(10,533)
15,772
440

— $

(6,400)

301
(2,238)
14,127
(18,826)
13,605
(569)
—

$

$

F-24

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

The components of the deferred tax assets and deferred tax liabilities are as follows:

Deferred tax assets:

Net operating loss carryforwards
Stock-based compensation
Property, plant and equipment
Other

Less: Valuation allowance

Total deferred tax assets

Deferred tax liabilities:

Property, plant and equipment
Other

Total deferred tax liabilities
Net deferred tax asset (liability)

For the years ended
December 31,

2015

2014

(in thousands)

$

$

98,571
1,325
9,816
1,139
110,851
(110,510)
341

(189)
(152)
(341)

$

— $

93,364
1,943
13,990
1,289
110,586
(106,764)
3,822

(3,436)
(386)
(3,822)
—

In accordance with ASC 740, the Company presents deferred tax assets net of its deferred tax liabilities on a tax jurisdictional 
basis on its Consolidated Balance Sheets.  The net deferred tax liability as of December 31, 2015 and December 31, 2014 was zero.

At December 31, 2015 the Company had net operating loss carryforwards in the U.S. and in certain non-U.S. jurisdictions totaling 

$330.2 million.  Of these, $92.4 million is related to the Velardeña Properties in Mexico and expires in future years through 2025.  
$22.9 million is related to other Mexico exploration activities and also expires in future years through 2025.  $38.0 million net 
operating losses exist in Luxembourg and have no expiration date, while $118.3 million exist in other non-U.S. countries, which will 
expire in future years through 2035.  In the U.S. there are $58.6 million of net operating loss carryforwards which will expire in future 
years through 2035.

The valuation allowance offsetting the net deferred tax assets of the Company of $111.4 million and $106.8 million at 

December 31, 2015 and 2014, respectively, relates primarily to the uncertain utilization of certain deferred tax assets, primarily net 
operating loss carryforwards, in various tax jurisdictions.  The Company continually assesses both positive and negative evidence to 
determine whether it is more likely than not that deferred tax assets can be realized prior to their expiration.

The Company, a Delaware corporation, and its subsidiaries file tax returns in the United States and in various foreign 

jurisdictions.  The tax rules and regulations in these countries are highly complex and subject to interpretation.  The Company’s tax 
returns are subject to examination by the relevant taxing authorities and in connection with such examinations, disputes can arise with 
the taxing authorities over the interpretation or application of certain tax rules within the country involved.  In accordance with ASC 
740, the Company identifies and evaluates uncertain tax positions, and recognizes the impact of uncertain tax positions for which there 
is less than a more-likely-than-not probability of the position being upheld upon review by the relevant taxing authority.  Such 
positions are deemed to be “unrecognized tax benefits” which require additional disclosure and recognition of a liability within the 
financial statements.  If recognized, none of the unrecognized tax benefits would affect the Company’s effective tax rate.

Below is a reconciliation of the beginning and ending amount of gross unrecognized tax benefits, which excludes any estimated 

penalties and interest on all identified unrecognized tax benefits.  The Company’s unrecognized tax benefits as of December 31, 2015 
and 2014 are completely offset by net deferred tax benefits and therefore do not appear on the Consolidated Balance Sheet.

F-25

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

Gross unrecognized tax benefits at beginning of period
Increases for tax positions taken during prior years
Decreases relating to settlements with taxing authorities
Reductions due to lapse of statute of limitations
Gross unrecognized tax benefits at end of period

The Year Ended December 31,

2015

2014

(in thousands)

1,163

$

(226)
937

$

1,668

(505)
1,163

$

$

Tax years as early as 2010 remain open and are subject to examination in the Company’s principal tax jurisdictions.  The 

Company does not expect a significant change to its net unrecognized tax benefits over the next 12 months.  No interest and penalties 
were recognized in the Consolidated Statement of Operations and Comprehensive Loss for the year ended December 31, 2015 or 
2014, and there were no interest and penalties recognized in the statement of financial position as of December 31, 2015 and 2014.  
The Company classifies income tax related interest and penalties as income tax expense.

16.

Equity

Registered offering

On September 10, 2014 the Company completed a registered public offering (the “Offering”) of 3,692,000 Units (the “Units”), 
with each Unit consisting of one share of the Company’s common stock (the “Shares”) and a warrant to purchase .50 of a share of the 
Company’s common stock (the “Warrants”). Each Unit was priced at $0.86 per Unit, before discount to the underwriters. The 
Warrants became exercisable on March 11, 2015 at an exercise price of $1.21 per share and will expire on September 10, 2019, five 
years from the date of issuance. The Shares and the Warrants are immediately separable and were issued separately. The Company 
received net proceeds from the Offering of approximately $2.7 million after the underwriter commissions and expenses of 
approximately $0.5 million.

In arriving at the value of the Shares and Warrants the Company first valued and recorded the Warrants as a liability on the 
balance sheet as a result of anti-dilution clauses in the warrant agreements that could result in a resetting of the warrant exercise price 
in the event the Company were to issue additional shares of its common stock in a future transaction at an offering price lower than the 
current exercise price of the warrants.  A third party expert determined a value for the Warrants at September 4, 2014, the date prior to 
the announcement of the Offering, using a Monte Carlo simulation, which falls within Level 3 of the fair value hierarchy (see Note 
14).  The valuation model takes into account the probability that the Company could issue additional shares in a future transaction at a 
lower price than the current exercise price of the Warrants.  Significant inputs to the valuation model included the Company’s closing 
stock price at September 4, 2014 of $1.01, the exercise price for the Warrants disclosed above, the Company’s stock volatility 
measured as of September 30, 2014, the applicable risk free interest rate of 1.6%, and the probability of an additional issuance of the 
Company’s common stock at a lower price than the current warrant exercise price.  The fair value of the Warrants was determined to 
be $1.2 million, with the remaining $1.5 million of net proceeds from the Offering being allocated to additional paid in capital.

Private placement

On September 10, 2014 the Company also completed a private placement (the “Private Placement”) with The Sentient Group 

(“Sentient”), the Company’s largest stockholder, pursuant to which Sentient purchased, pursuant to Regulation S under the U.S. 
Securities Act of 1933, a total of 5,800,000 Units (the “Private Placement Units”), with each Private Placement Unit consisting of one 
share of the Company’s common stock (the “Sentient Shares’) and a warrant to purchase 0.50 of a share of the Company’s common 
stock (the “Sentient Warrants”). The Sentient Warrants became exercisable on March 11, 2015 at an exercise price of $1.21 per share 
and will expire on September 10, 2019, five years from the date of issuance. Each Private Placement Unit was priced at $0.817, the 
same discounted price paid by the underwriters in the Offering. The Company received net proceeds from the Private Placement of 
approximately $4.7 million after the discount and expenses of approximately $0.3 million. Following the completion of the Private

F-26

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

Placement and the Offering, Sentient held approximately 27.2% of the Company’s outstanding common stock (excluding restricted 
common stock held by the Company’s employees).

In arriving at the value of the Sentient Shares and Sentient Warrants the Company first valued and recorded the SentientWarrants 

as a liability on the balance sheet as a result of anti-dilution clauses in the warrant agreements that could result in a resetting of the 
warrant exercise price in the event the Company were to issue additional shares of its common stock in a future transaction at a an 
offering price lower than the current exercise price of the Sentient Warrants.  A third party expert determined a value for the Sentient 
Warrants at September 4, 2014, the date prior to the announcement of the Offering, using a Monte Carlo simulation, which falls within 
Level 3 of the fair value hierarchy (see Note 14).  The valuation model takes into account the probability that the Company could issue 
additional shares in a future transaction at a lower price than the current exercise price of the Sentient Warrants.  Significant inputs to 
the valuation model included the Company’s closing stock price at September 4, 2014 of $1.01, the exercise price for the Sentient 
Warrants disclosed above, the Company’s stock volatility measured as of September 30, 2014, the applicable risk free interest rate of 
1.6%, and the probability of an additional issuance of the Company’s common stock at a lower price than the current warrant exercise 
price.  The fair value of the Sentient Warrants was determined to be $1.9M, with the remaining $2.7M of net proceeds from the 
Private Placement being allocated to additional paid in capital.

Equity Incentive Plans

In May 2014, the Company’s stockholders approved amendments to the Company’s 2009 Equity Incentive Plan, adopting the 

Amended and Restated 2009 Equity Incentive Plan (the “Equity Plan”), pursuant to which awards of the Company’s common stock 
may be made to officers, directors, employees, consultants and agents of the Company and its subsidiaries.  The Company recognizes 
stock-based compensation costs using a graded vesting attribution method whereby costs are recognized over the requisite service 
period for each separately vesting portion of the award.

The following table summarizes the status of the Company’s restricted stock grants issued under the Equity Plan at 

December 31, 2015 and 2014 and changes during the years then ended:

The Year Ended December 31,

2015

2014

Weighted 
Average 
Grant Date 
Fair Value 
Per Share

Weighted
Average 
Grant Date 
Fair Value 
Per Share

Number of 
Shares

Number of 
Shares

600,838
—

(516,668)
—
84,170

$

$

1.48
—

1.64
—
0.46

915,971
140,000

(455,133)
—
600,838

$

$

2.47
0.52

3.18
—
1.48

Restricted Stock Grants
Outstanding at beginning of 

year

Granted during the year
Restrictions lifted during 

the year

Forfeited during the year
Outstanding at end of year

No restricted stock grants were made during the year ended December 31, 2015. During the year ended December 31, 2014 

restricted stock grants were made to one officer and one new employee at the date of hire.

Restrictions were lifted on 336,334 shares during the year ended December 31, 2015 on the anniversaries of grants made to 
officers and employees in prior years.  In addition, during 2015 restrictions were lifted on 163,334 shares related to the retirement of 
two officers during the year and restrictions were lifted on 12,000 shares during 2015 in connection with the termination of 
employment of two employees.  Restrictions were lifted on 444,633 shares during the year ended December 31, 2014 on the 
anniversaries of grants made to officers and employees in prior years and restrictions were lifted on an additional 10,500 shares during 
2014 in connection with the termination of employment of two employees.

F-27

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

For the years ended December 31, 2015 and 2014 the Company recognized approximately $0.2 million and $0.5 million, 
respectively, of compensation expense related to the restricted stock grants.  The Company expects to recognize a nominal amount of 
compensation expense related to these grants over the next 12 months.

The following table summarizes the status of the Company’s stock option grants issued under the Equity Plan at December 31, 

2015 and 2014 and changes during the years then ended:

The Year Ended December 31,

2015

2014

Weighted 
Average Grant 
Date Fair 
Value Per 
Share

Number of
Shares

Weighted 
Average 
Grant Date 
Fair Value 
Per Share

Number of 
Shares

245,810
—

$

—
— $
$

245,810

245,810
245,810

$
$

3.47
—

—
—
3.47

3.47
3.47

110,810
150,000

$

—
(15,000) $
245,810
$

95,810
95,810

$
$

8.02
0.56

—
8.00
3.47

8.02
8.02

Equity Plan Options
Outstanding at beginning 

of year

Granted during the year
Restrictions lifted during 

the year

Forfeited during the year
Outstanding at end of year
Exercisable at end of 

period

Granted and vested

The fair value of each option award is estimated on the date of grant using the Black-Scholes option pricing model using the 

assumptions noted in the following table.  Expected volatilities are based on the historical volatilities of the Company’s shares.  The 
Company uses historical data to estimate option exercises and forfeitures within the Black-Scholes model. The expected term of the 
options granted represents the period of time that options granted are expected to be outstanding, based on past experience and future 
estimates and includes data related to both employees and directors.  The risk-free rate for periods within the expected term of the 
option is based on the U.S. Treasury yield curve in effect at the time of grant.  The Company currently does not foresee the payment of 
dividends in the near term.

Expected volatility
Weighted average volatility
Expected dividend yield
Expected term (in years)
Risk-free rate

Grant Date
November 12,
2014

82.64%
82.64%
—
5
0.88%

The grant made during 2014 was to a manager at our Velardeña Properties. The manager’s employment was terminated in 
conjunction with the suspension of operations at our Velardeña Properties and has six months from the termination date to exercise the 
options.

The options that expired during 2014 were options issued to former ECU stock option holders to replace options previously 

issued to them by ECU.

During the year ended December 31, 2015, the Company recognized expense of less than $0.1 million related to the outstanding 

options. The Company does not expect to record any additional expense related to these options.

Also, pursuant to the Equity Plan, the Company’s Board of Directors adopted the Non-Employee Director’s Deferred 
Compensation and Equity Award Plan (the “Deferred Compensation Plan”).  Pursuant to the Deferred Compensation Plan the non-
employee directors receive a portion of their compensation in the form of Restricted Stock Units (“RSUs”) issued under the Equity 
Plan. The RSUs vest on the first anniversary of the grant and each vested RSU

F-28

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

entitles the director to receive one unrestricted share of common stock upon the termination of the director’s board service.

The following table summarizes the status of the RSU grants issued under the Deferred Compensation Plan at December 31, 

2015 and 2014 and changes during the years then ended:

For the Year Ended December 31,

2015

2014

Number of 
Underlying 
Shares

Weighted 
Average Grant
Date Fair Value
Per Share

Number of 
Underlying 
Shares

Weighted 
Average 
Grant Date 
Fair Value 
Per Share

935,285
310,000

$

—
—

1,245,285

$

2.08
0.39

—
—

1.66

585,285
350,000

$

—
—

935,285

$

2.97
0.58

—
—

2.08

Restricted Stock Units
Outstanding at beginning 

of year

Granted during the year
Restrictions lifted during 

the year

Forfeited during the year
Outstanding at end of 

year

For the years ended December 31, 2015 and 2014 the Company recognized approximately $0.2 million and $0.4 million, 
respectively, of compensation expense related to the RSU grants.  The Company expects to recognize additional compensation 
expense related to the RSU grants of less than $0.1 million over the next six months.

Pursuant to the KELTIP (see Note 10), KELTIP Units may be granted to certain officers and key employees of the Company, 

which units will, once vested, entitle such officers and employees to receive an amount in cash or in Company common stock 
measured generally by the price of the Company’s common stock on the settlement date. The KELTIP Units are recorded as a liability 
as discussed in detail in Note 10. All of the outstanding KELTIP Units were settled during 2015 upon the retirement of an officer of 
the Company. The Company issued 172,500 shares of its common stock under the Equity Plan to settle the outstanding KELTIP 
Units.

Common stock warrants

The following table summarizes the status of the Company’s common stock warrants at December 31, 2015 and December 31, 

2014 and changes during the years then ended:

For the Year Ended December 31,

2015

2014

Common Stock Warrants
Outstanding at beginning of year
Granted during period
Dilution adjustment
Expired during period
Exercised during period
Outstanding at end of year

Number of 
Underlying 
Shares
8,777,409 $

—
—
—
—

8,777,409 $

Weighted Average
Exercise Price Per 
Share

Number of
Underlying Shares

Weighted
Average Exercise
Price Per Share

3.95
—
—
—
—
3.95

5,263,578 $
4,746,000
599,760
(1,831,929)
—

8,777,409 $

12.10
1.21
7.17
19.00
—
3.95

The warrants issued during the period are related to the Offering and Private Placement of the Company’s securities completed on 

September 10, 2014 as discussed above.

In September 2012, the Company closed on a registered offering and concurrent private placement with Sentient in which it sold 

units, consisting of one share of common stock and a five-year warrant to acquire one half of a share of common stock at an exercise 
price of $8.42 per share (the “September 2012 Warrants”). Pursuant to certain dilution

F-29

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

adjustment provisions in the warrant agreement governing the September 2012 Warrants, the number of shares of common stock 
issuable upon exercise of the September 2012 Warrants was increased from 3,431,649 shares to 4,031,409 shares (599,760 share 
increase) and the exercise price was reduced from $8.42 per share to $7.17 per share pursuant to a weighted average dilution 
calculation based on the pricing of the Offering and the Private Placement.

The warrants that expired during 2014 were warrants related to the merger with ECU on September 2, 2011 and were issued to 

former ECU warrant holders to replace warrants previously issued to them by ECU.

The warrants issued in September 2012 and September 2014 are being recorded as a liability on the balance sheet as a result of 
anti-dilution clauses in the warrant agreements that could result in a resetting of the warrant exercise price in the event the Company 
were to issue additional shares of its common stock in a future transaction at an offering price lower than the current exercise price of 
the warrants.  At December 31, 2015 the total liability for the warrants was $210,000, consisting of $205,000 for 2014 warrants and 
$5,000 for the 2012 warrants.  The warrant liability has been recorded at fair value as of December 31, 2015 based primarily on a 
valuation performed by a third party expert using a Monte Carlo simulation, which falls within Level 3 of the fair value hierarchy.  
The valuation model takes into account the probability that the Company could issue additional shares in a future transaction at a 
lower price than the current exercise price of the warrants.  Significant inputs to the valuation model included the Company’s closing 
stock price at December 31, 2015 of $0.20, the exercise prices for the warrants disclosed above, the Company’s stock volatility of 
85%, the applicable risk free interest rate of 1.5%, and the probability of an additional issuance of the Company’s common stock at a 
lower price than the current warrant exercise price.  The balances for warrant liability, paid-in capital, and accumulated earnings also 
reflect an adjustment made during 2014 to reflect the impact of recording the 2012 warrants as a liability.  Paid in capital and 
accumulated deficit were reduced by $15.6 million $15.5 million respectively and warrant liability was increased by $0.2 million. The 
adjustments were determined to be immaterial to the Company’s financial statements filed in prior periods.

Subsequent to December 31, 2015, two anti-dilution adjustments have been made to the warrants issued in September 2012 and 

September 2014, resulting from the January 19, 2016 approval by the Company’s stockholders of the convertibility of the Sentient 
Note and from the subsequent February 11, 2016 conversion by Sentient of a portion of the Sentient Note and accrued interest.  (See 
Note 25.)

17.

Revenue and Related Costs

Sale of Metals and Cost of Metals Sold

During the years ended December 31, 2015 and 2014, the Company sold marketable concentrate products from its Velardeña 
Propertiesto three customers.  Under the terms of the Company’s agreements with customers, title generally passes when a provisional 
payment is made, which occurs generally after the product is shipped and customary sales documents are completed.  Costs related to 
the sale of metals products include direct and indirect costs incurred to mine, process and market the products.  At December 31, 2014 
the Company had written down its metals and in-process inventories to net realizable value including a charge to the cost of metals 
sold of approximately $1.2 million and a charge to depreciation expense of approximately $0.7 million. The Company had no metals 
or in-process inventories at December 31, 2015 as a result of the suspension of mining and processing at its Velardeña Properties (see 
Note 1).

Oxide Plant Lease and Oxide Plant Lease Costs

On July 15, 2015 the Company entered into a leasing agreement with a third party, which for a monthly fixed fee and a variable 
tonnage fee will allow the third party to control and process its own material through the oxide plant at the Velardeña Properties for a 
period of up to 30 months and a minimum period of 18 months. In addition, under the terms of the lease the Company is entitled to 
reimbursement for certain costs it incurs related to the lease.  For the year ended December 31, 2015 the Company recorded revenue 
of approximately $0.7 million and related costs of approximately $0.2 million associated with the lease of the oxide plant. In addition, 
the Company received an advance payment of $0.5 million that will be applied to the lease amounts due during the first four months 
of 2016. At December 31, 2015 the advance payment was recorded as deferred revenue on the accompanying Consolidated Balance 
Sheets.

F-30

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

The Company recognizes oxide plant lease fees and reimbursements for labor, utility and other costs as “Revenue from Oxide 
plant lease” in the Consolidated Statements of Operations and Comprehensive Loss following the guidance of ASC 605 regarding 
“income statement characterization of reimbursements received for “out-of-pocket” expenses incurred” and “reporting revenue gross 
as a principal versus net as an agent”.  ASC 605 supports recording as gross revenue fees received for the reimbursement of expenses 
in situations where the recipient is the primary obligor and has certain discretion in the incurrence of the reimbursable expense.  The 
actual costs incurred for reimbursed direct labor and utility costs are reported as “Oxide plant lease costs” in the statement of 
operations. The Company recognizes lease fees during the period the fees are earned per the terms of the lease.

18.

Interest and Other Income

For the year ended December 31, 2015 the Company reported interest and other income of $3.1 million which includes a $2.3 
million reduction and elimination of a loss contingency liability related to foreign withholding taxes that the government could have 
asserted were owed by the Company, acting as withholding agent, on certain interest payments made to a third party (see Note 13). 
Also included in interest and other income is approximately $0.8 million related to a tax refund received in Mexico.

For the year ended December 31, 2014 the Company reported other income of $1.6 million related primarily to the reduction of a 

loss contingency liability related to foreign withholding taxes that the government could assert are owed by the Company, acting as 
withholding agent, on certain interest payments made to a third party (see Note 13).

19.

Derivative Income

During the years ended December 31, 2015 and 2014 the Company recorded approximately $1.3 million and $1.7 million 
respectively, of warrant derivative income related to a decrease in the fair value of the liability recorded for warrants to acquire the 
Company’s common stock (see Note 14).  The warrant liability has been recorded at fair value as of December 31, 2015 and 2014 
based primarily on a valuation performed by a third party expert using a Monte Carlo simulation, which falls within Level 3 of the fair 
value hierarchy.  The valuation model takes into account the probability that the Company could issue additional shares in a future 
transaction at a lower price than the current exercise price of the warrants.  Significant inputs to the valuation model included prices 
for the warrants disclosed above, the probability of an additional issuance of the Company’s common stock at a lower price than the 
current warrant exercise price and the inputs in the table below for the respective periods.

During the year ended December 31, 2015 the Company recorded approximately $0.6 million of derivative income related to a 

decrease in the fair value of the derivative liability related to the Sentient Loan (see Note 11.) The derivative liability has been 
recorded at fair value as of December 31, 2015 based primarily on a valuation performed by a third party expert using a Monte Carlo 
simulation, which falls within Level 3 of the fair value hierarchy.  Significant inputs to the valuation model included: 1) the 
probability of successfully achieving stockholder approval of the Loan’s conversion feature, 2) future variations in the Company’s 
stock price, and 3) the probability of entering into an equity transaction prior to the Loan maturity date that would lower the 
conversion price as well as the inputs in the table below for 2015.

The Company’s
Closing stock price
Volatility
Risk-free rate

At December 31,

2015

2014

$

0.20 $
85.00%
1.48%

F-31

0.54
90.00%
1.60%

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

20.

Cash flow information

The following table reconciles net income (loss) for the period to cash used in operations:

Cash flows from operating activities:

Net loss
Adjustments to reconcile net loss to net cash used in operating 

The Year Ended December 31,

2015

2014

(in thousands)

$

(25,383)

$

(18,823)

activities:
Amortization and depreciation
Gain on sale of assets, net
Accretion of asset retirement obligation
Asset write off
Write off of loss contingency, net
Decrease in warrant liability
Decrease in derivative liability
Amortization of deferred loan costs
Impairment of long lived assets
Foreign exchange gain on loss contingency
Stock compensation

Changes in operating assets and liabilities:

(Increase) decrease in trade accounts receivable
Decrease in prepaid expenses and other assets
Decrease (increase) in inventories
Decrease in value added tax receivable (net)
Increase in accrued interest payable net of amounts capitalized
(Decrease) increase in accounts payable and accrued liabilities
Increase in deferred revenue
(Decrease) increase in deferred leasehold payments
Decrease in reclamation liability

Net cash used in operating activities

$

4,480
(719)
198
27
(1,969)
(1,344)
(553)
54
13,181
(106)
453

(546)
384
861
916
81
(402)
500
(11)
(37)
(9,935)

$

3,128
(689)
200
138
(1,645)
(1,693)

—
—
(281)
926

25
287
(764)
449
—
358
—
42
(117)
(18,459)

The Company did not make any cash payments for interest or income taxes during the years ended December 31, 2015 and 2014.

21.

Commitments and Contingencies

Leases and Purchase Commitments

The Company has non-cancelable operating lease commitments as follows:

2016

2017

2018

2019

2020

Thereafter

El Quevar mining concessions 

(estimated)

Velardeña mining consessions 

(estimated)
Office space

$

$
$

  114

  40
  283

$

$
$

 114

 40
  287

$

$
$

 114

 40
  292

$

$
$

 114

  40
  268

$

$
$

  114

$

$
 40
— $

—

—
—

The Company is required to make payments to the Argentinean government to maintain its rights to the El Quevar mining 
concessions. The Company has made such payments totaling approximately $74,000 and $35,000 for the years ended December 31, 
2015 and 2014, respectively.

F-32

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

The Company is required to pay concession holding fees to the Mexican government to maintain its rights to the Velardeña 
Properties mining concessions. During the years ended December 31, 2015 and 2014 the Company made such payments totaling 
approximately $12,000 each year, and annual payments under its surface right agreement with the local ejido of appromately $25,000.

The Company has office leases for its corporate headquarters in Golden, Colorado, as well as for its Velardeña Properties offices 
in Mexico, and exploration offices in Mexico and Argentina.  The lease for the corporate headquarters office space was renegotiated 
and extended during the first quarter 2014. The new lease reflects an approximately 46% reduction in space and an approximately 
44% reduction in cost beginning March 1, 2014. The new lease expires November 30, 2019. Payments associated with the corporate 
headquarters lease were recorded to rent expense by the Company in the amounts of $227,000 and $259,000 for the years ended 
December 31, 2015 and 2014, respectively.

The Company cannot currently estimate the life of the Velardeña Properties or El Quevar project. The table above assumes that 
no annual maintenance payments will be made more than five years after December 31, 2015. If the Company continues mining and 
processing or evaluations of restart at the Velardeña Properties beyond five years, the Company expects that it would make annual 
maintenance payments of approximately $15,000 per year for the life of the Velardeña mine. If the Company continues to evaluate 
development opportunities at the El Quevar project, the Company expects that it would make annual maintenance payments of 
approximately $114,000 per year for the life of the El Quevar mine.

Payments associated with other exploration concessions the Company owns are not included because the Company has not 
completed exploration work on these concessions.  Exploration success is historically low and the Company has the right to terminate 
the payments and release the concessions at any time.

Contingencies

The Company has recorded loss contingencies of approximately $0.4 million and $2.6 million at December 31, 2015 and 

December 31, 2014, respectively as discussed in Note 13.

22.

Foreign Currency

The Company conducts exploration and mining activities primarily in Mexico and Argentina, and gains and losses on foreign 
currency transactions are related to those activities. The Company’s functional currency is the U.S. dollar but certain transactions are 
conducted in the local currencies resulting in foreign currency transaction gains or losses.

F-33

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

23.

Segment Information

The Company’s sole activity is the mining, construction and exploration of mineral properties containing precious metals.  The 

Company’s reportable segments are based upon the Company’s revenue producing activities and cash consuming activities. The 
Company reports two segments, one for its Velardeña Properties in Mexico and the other comprised of non-revenue producing 
activities including exploration, construction and general and administrative activities.  Intercompany revenue and expense amounts 
have been eliminated within each segment in order to report on the basis that management uses internally for evaluating segment 
performance. The financial information relating to the Company’s segments is as follows:

Revenue

Costs
Applicable
to Sales

Depreciation,
Depletion and
Amortization

Exploration, El
Quevar,
Velardeña and
Administrative
Expense
(in thousands )

Pre-Tax loss

Total Assets

Capital
Expenditures

The Year ended December 31, 2015
Velardeña Properties
Corporate, Exploration & Other

The Year ended December 31, 2014
Velardeña Properties
Corporate, Exploration & Other

$

$

$

$

  8,071 $
—
  8,071 $

  235 $
—
  235 $

 10,065 $
—
 10,065 $

 1,655 $
—
 1,655 $

 3,826 $
654
 4,480 $

 2,353 $
775
 3,128 $

 1,347 $
8,918
 10,265 $

 6,607 $
10,743
 17,350 $

  17,346 $
8,037
  25,383 $

  8,144 $
10,679
  18,823 $

 8,988 $
8,013
 17,001 $

 27,188 $
14,070
 41,258 $

 28
16
 44

 491
9
 500

All of the revenue for the two years presented was from the Company’s Velardeña Properties in Mexico (see Note 17).  The 

revenue for 2015 was attributable to sales of precipitates and concentrates to three customers under varying agreements. The revenue 
for 2014 was attributable to sale of concentrates to one customer. During 2014 the Velardeña Properties were on care and maintenance 
until processing of mined material resumed in early November 2014, resulting in lower revenue and costs applicable to sales. The 
Company suspended operations at its Velardeña properties in November 2015 (see Note 1).

The 2015 Velardeña Properties pre-tax loss includes a $13.2 million impairment charge recorded at September 30, 2015 (see Note 

3). The impairment charge is also reflected in the reduction of the Velardeña Properties total assets for 2015.

24.  Related Party Transactions

Since May, 2009 until her resignation on December 30, 2015, Deborah Friedman devoted approximately half of her time to serve 

as the Company’s Senior Vice President, General Counsel and Corporate Secretary and approximately half of her time to her legal 
practice at Davis Graham & Stubbs LLP (“DGS”) where she is a partner.  During 2014 and 2015 the Company paid a monthly flat fee 
retainer of approximately $15,000 to DGS for approximately one half of Ms. Friedman’s time spent serving as the Company’s Senior 
Vice President, General Counsel and Corporate Secretary, which DGS subsequently remitted to Ms. Friedman, and the Company paid 
her customary hourly rate to DGS for any time spent by Ms. Friedman in excess of that threshold.  Although she was an executive 
officer of the Company for Section 16(a) reporting purposes under the Securities Exchange Act of 1934, Ms. Friedman was not 
employed by the Company.  For the years ended December 31, 2015 and 2014 the Company paid approximately $490,000 and 
$460,000 respectively to DGS for legal services, including the amounts relating to Ms. Friedman described above.  The Company has 
been advised by DGS that these amounts represented a de minimis amount of DGS’s total revenue in each of the two years.  At 
December 31, 2015 and 2014 the Company’s Consolidated Balance Sheets included in accounts payable and other accrued liabilities 
amounts owed to DGS of approximately $25,000 and $21,000 respectively.

25. Subsequent Events

Stockholder approval of Sentient Note Conversion and Warrant Exercise Price Adjustment

Subsequent to December 31, 2015 the Company’s stockholders approved, at a special meeting of the stockholders held on 
January 19, 2016, the issuance of shares of the Company’s common stock upon conversion of the Sentient Note (see Note 11).

Pursuant to certain dilution adjustment provisions in the warrant agreements governing the September 2012 and 2014 Warrants, 

the exercise price of the warrants was adjusted downward as a result of stockholder approval of the convertibility of the Sentient 
Note.  At January 19, 2016, the date of the stockholders’ approval, the lowest conversion price determinable for the Sentient Note, 
pursuant to the terms of the Sentient Note, was $0.29, a price equal to 90 percent of the 15-day VWAP for the period immediately 
preceding the Loan closing date of October 27, 2015.  As a result, effective January 19, 2016, the number of shares of common stock 
issuable upon exercise of the September 2012 Warrants was increased from 4,031,409 shares to 5,084,193 shares (1,052,784 share 
increase) and the exercise price was reduced from $7.17 per share to $5.68 per share.  The number of shares of common stock issuable 
upon exercise of the September 2014 Warrants was increased from 4,746,000 shares to 5,108,347 shares (362,347 share increase) and 
the exercise price was reduced from $1.21 per share to $1.01 per share.

F-34

GOLDEN MINERALS COMPANY
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS — (Continued)
(Expressed in United States dollars)

Conversion of Sentient Note and Warrant Exercise Price Adjustment

Also subsequent to December 31, 2015, on February 11, 2016, Sentient converted approximately $3.9 million of principal and 
$0.1 million of accrued interest (representing the total amount of accrued interest at the conversion date) pursuant to the Sentient Note 
into 23,335,000 shares of the Company’s common stock at an exercise price of approximately $0.172 per share, reflecting 90% of the 
15-day VWAP immediately preceding the conversion date.  Following the conversion, approximately $1.1 million of principal 
remained outstanding.  If the remaining principal and additional accrued interest from February 11, 2016 is not converted into the 
Company’s common stock, the Company would owe approximately $1.2 million to Sentient on the October 27, 2016 maturity date.

As a result ofthe Sentient Note conversion on February 11, 2016, the number of shares of common stock issuable upon exercise of 
the September 2012 Warrants was increased pursuant to applicable anti-dilution provisions from 5,084,193 shares to 5,677,757 shares 
(593,564 share increase) and the exercise price was reduced from $5.68 per share to $5.09 per share.  The number of shares of 
common stock issuable upon exercise of the September 2014 Warrants was increased from 5,108,347 shares to 5,365,983 shares 
(257,636 share increase) and the exercise price was reduced from $1.01 per share to $0.91 per share.

If all or a portion of the remaining principal and interest under the Sentient Loan is converted at a lower conversion price than the 
February 11 $0.172 conversion price, the number of shares of common stock issuable upon exercise of the warrants would be further 
increased and the exercise price of the 2012 and 2014 Warrants would be further decreased.

F-35

NAME
ASM Services S.a r.l.
Silex Spain, S.L.

Silex Argentina S.A.

ECU Silver Mining Inc.

Minera William, S.A. de C.V.

SUBSIDIARIES

Luxembourg
Spain
Argentina
Canada
Mexico

Exhibit 21.1

JURISDICTION OF 
FORMATION

CONSENT OF INDEPENDENT REGISTERED PUBLIC ACCOUNTING FIRM

We hereby consent to the incorporation by reference in the Registration Statements on Form S-3, as amended (Nos. 333-
167026, 333-172363, 333-177117, 333-179993, 333-189693, 333-199026 and 333-200555) and Form S-8 (Nos. 333-159096, 333-
165933, 333-170891, 333-176671, 333-176915, 333-190542 and 333-200557) of Golden Minerals Company of our report dated 
February 25, 2016 relating to the consolidated financial statements, which appears in this Form 10-K.

Exhibit 23.1

Denver, Colorado
February 25, 2016

/s/ EKS&H, LLLP
EKS&H, LLLP

CONSENT OF TETRA TECH

Exhibit 23.2

We hereby consent to the incorporation by reference of any mineralized material and other analyses performed by us in our capacity 
as an independent consultant to Golden Minerals Company (the “Company”), which are set forth in the Company’s Annual Report on 
Form 10-K for the year ended December 31, 2015, in the Company’s Registration Statements on Form S-3 (Nos. 333-167026, 333-
172363, 333-177117, 333-179993, 333-189693, 333-199026 and 333-200555) and Form S-8 (Nos. 333-159096, 333-165933, 333-
170891, 333-176671, 333-176915, 333-190542 and 333-200557), and any amendment, prospectuses or supplements thereto, and in 
any amendment to any of the foregoing.

Date: February 25, 2016

 /s/ Geoffrey J. Elson
 Signature of Qualified Person

Geoffrey J. Elson
Name of Qualified Person

Exhibit 23.3

Runge, Inc. dba
RungePincockMinarco

6251 Greenwood Plaza Blvd.
Suite 275
Greenwood Village, Colorado 80111

CONSENT OF RUNGEPINCOCKMINARCO

We hereby consent to the incorporation by reference of any mineralized material and other analyses performed by us in our capacity 
as an independent consultant to Golden Minerals Company (the “Company”), which are set forth in the Company’s Annual Report on 
Form 10-K for the year ended December 31, 2015, in the Company’s Registration Statements on Form S-3 (Nos. 333-167026, 333-
172363, 333-177117, 333-179993, 333-189693, 333-199026 and 333-200555) and Form S-8 (Nos. 333-159096, 333-165933, 333-
170891, 333-176671, 333-176915, 333-190542 and 333-200557), and any amendment, prospectuses or supplements thereto, and in 
any amendment to any of the foregoing.

Dated: February 23, 2016

/s/ Tim J. Swendseid
Signature of Qualified Person

Tim J. Swendseid, P.E., MBA, CFA
Print name of Qualified Person

Telephone +1 303 986 6950

Email usa@rpmglobal.com

Website www.rpmglobal.com

Exhibit 31.1

I, Warren M. Rehn, certify that:

CERTIFICATION

1.

2.

3.

4.

I have reviewed this annual report on Form 10-K of Golden Mineral Company;

Based on my knowledge, this report does not contain any untrue statement of a material fact or omit to state a material fact 
necessary to make the statements made, in light of the circumstances under which such statements were made, not misleading 
with respect to the period covered by this report;

Based on my knowledge, the financial statements, and other financial information included in this report, fairly present in all 
material respects the financial condition, results of operations and cash flows of the registrant as of, and for, the periods 
presented in this report;

The registrant’s other certifying officer and I are responsible for establishing and maintaining disclosure controls and 
procedures (as defined in Exchange Act Rules 13a-15(e) and 15d-15(e)) and internal control over financial reporting (as 
defined in Exchange Act Rules 13a-15(f) and 15d-15(f)) for the registrant and have:

a.

b.

c.

d.

Designed such disclosure controls and procedures, or caused such disclosure controls and procedures to be designed 
under our supervision, to ensure that material information relating to the registrant, including its consolidated 
subsidiaries, is made known to us by others within those entities, particularly during the period in which this report 
is being prepared;

Designed such internal controls over financial reporting, or caused such internal control over financial reporting to 
be designed under our supervision, to provide reasonable assurance regarding the reliability of financial reporting 
and the preparation of financial statements for external purposes in accordance with generally accepted accounting 
principles;

Evaluated the effectiveness of the registrant’s disclosure controls and procedures and presented in this report our 
conclusions about the effectiveness of the disclosure controls and procedures, as of the end of the period covered by 
this report based on such evaluation; and

Disclosed in this report any change in the registrant’s internal control over financial reporting that occurred during 
the registrant’s most recent fiscal quarter that has materially affected, or is reasonably likely to materially affect, the 
registrant’s internal control over financial reporting; and

5.

The registrant’s other certifying officers and I have disclosed, based on our most recent evaluation of internal control over 
financial reporting, to the registrant’s auditors and the audit committee of registrant’s board of directors:

a.

b.

All significant deficiencies and material weaknesses in the design or operation of internal control over financial 
reporting which are reasonably likely to adversely affect the registrant’s ability to record, process, summarize and 
report financial information; and

Any fraud, whether or not material, that involves management or other employees who have a significant role in the 
registrant’s internal control over financial reporting.

Date: February 25, 2016

/s/ WARREN M. REHN 
Warren M. Rehn 
President and Chief Executive Officer 
(Principal Executive Officer)

Exhibit 31.2

I, Robert P. Vogels, certify that:

CERTIFICATION

1.

2.

3.

4.

I have reviewed this annual report on Form 10-K of Golden Mineral Company;

Based on my knowledge, this report does not contain any untrue statement of a material fact or omit to state a material fact 
necessary to make the statements made, in light of the circumstances under which such statements were made, not misleading 
with respect to the period covered by this report;

Based on my knowledge, the financial statements, and other financial information included in this report, fairly present in all 
material respects the financial condition, results of operations and cash flows of the registrant as of, and for, the periods 
presented in this report;

The registrant’s other certifying officer and I are responsible for establishing and maintaining disclosure controls and 
procedures (as defined in Exchange Act Rules 13a-15(e) and 15d-15(e)) and internal control over financial reporting (as 
defined in Exchange Act Rules 13a-15(f) and 15d-15(f)) for the registrant and have:

a.

b.

c.

d.

Designed such disclosure controls and procedures, or caused such disclosure controls and procedures to be designed 
under our supervision, to ensure that material information relating to the registrant, including its consolidated 
subsidiaries, is made known to us by others within those entities, particularly during the period in which this report 
is being prepared;

Designed such internal controls over financial reporting, or caused such internal control over financial reporting to 
be designed under our supervision, to provide reasonable assurance regarding the reliability of financial reporting 
and the preparation of financial statements for external purposes in accordance with generally accepted accounting 
principles;

Evaluated the effectiveness of the registrant’s disclosure controls and procedures and presented in this report our 
conclusions about the effectiveness of the disclosure controls and procedures, as of the end of the period covered by 
this report based on such evaluation; and

Disclosed in this report any change in the registrant’s internal control over financial reporting that occurred during 
the registrant’s most recent fiscal quarter that has materially affected, or is reasonably likely to materially affect, the 
registrant’s internal control over financial reporting; and

5.

The registrant’s other certifying officers and I have disclosed, based on our most recent evaluation of internal control over 
financial reporting, to the registrant’s auditors and the audit committee of registrant’s board of directors:

a.

b.

All significant deficiencies and material weaknesses in the design or operation of internal control over financial 
reporting which are reasonably likely to adversely affect the registrant’s ability to record, process, summarize and 
report financial information; and

Any fraud, whether or not material, that involves management or other employees who have a significant role in the 
registrant’s internal control over financial reporting.

Date: February 25, 2016

/s/ ROBERT P. VOGELS
Robert P. Vogels
Senior Vice President and Chief Financial Officer
(Principal Financial Officer)

CERTIFICATION PURSUANT TO
18 U.S.C. SECTION 1350,
AS ADOPTED PURSUANT TO
SECTION 906 OF THE SARBANES-OXLEY ACT OF 2002

Exhibit 32.1

In connection with the Annual Report of Golden Minerals Company (the “Company”) on Form 10-K for the year ended 

December 31, 2015, as filed with the SEC on the date hereof (the “Report”), the undersigned hereby certify, pursuant to 18 U.S.C. 
§1350, as adopted pursuant to § 906 of the Sarbanes-Oxley Act of 2002, that:

(1)           The Report fully complies with the requirements of section 13(a) or 15(d) of the Securities Exchange Act 

of 1934; and

(2)           The information contained in the Report fairly presents, in all material respects, the financial condition and 

results of operations of the Company.

/s/ WARREN M. REHN
Warren M. Rehn
President and Chief Executive Officer
(Principal Executive Officer)
February 25, 2016

/s/ ROBERT P. VOGELS
Robert P. Vogels
Senior Vice President and Chief Financial Officer
(Principal Financial Officer)